IDOT contract 61L72 bid tabulation
Lemont, section 24-00060-00-RS. Let by Illinois DOT on September 19, 2025, Cook, District 01. 6 bids received; low bid $1,092,187 by P. T. Ferro Construction Co..
- Owner
- Illinois DOT
- Letting
- 19 SEP 2025
- Pay items
- 54
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | P. T. Ferro Construction Co. | $1,092,187 | Low |
| 2 | Builders Paving, LLC | $1,107,282 | +1.0% |
| 3 | Gallagher Asphalt Corporation | $1,111,111 | +2.0% |
| 4 | A Lamp Concrete Contractors, Inc. | $1,164,230 | +7.0% |
| 5 | K-Five Construction Corporation | $1,215,204 | +11% |
| 6 | R. W. Dunteman Company | $1,268,300 | +16% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. P. T. Ferro Construction Co. | 2. Builders Paving, LLC | 3. Gallagher Asphalt Corporation | 4. A Lamp Concrete Contractors, Inc. | 5. K-Five Construction Corporation | 6. R. W. Dunteman Company |
|---|---|---|---|---|---|---|---|---|---|
| 1 | CC&G RMVL repl < = 10 (X4400501) | LF | 200 | $88.00 | $82.00 | $80.00 | $74.00 | $70.00 | $98.00 |
| 2 | CC&G RMVL repl > 10FT (X4400503) | LF | 715 | $75.00 | $72.50 | $49.00 | $62.00 | $65.00 | $75.50 |
| 3 | San man reconst (X6026051) | EACH | 7 | $1,200.00 | $1,750.00 | $1,530.00 | $3,250.00 | $1,750.00 | $2,125.00 |
| 4 | FR & lids adjust SPL (X6030310) | EACH | 12 | $1,500.00 | $1,750.00 | $1,300.00 | $700.00 | $1,750.00 | $1,850.00 |
| 5 | Temp info signing (X7200061) | SF | 151 | $20.00 | $18.00 | $18.00 | $20.00 | $18.00 | $18.00 |
| 6 | Det loop repl (X8860105) | LF | 264 | $33.00 | $33.00 | $33.00 | $35.92 | $32.93 | $33.00 |
| 7 | Construction layout (Z0013798) | LS | 1 | $0.01 | $2,000.00 | $6,000.00 | $2,500.00 | $25,500 | $4,000.00 |
| 8 | Drain util STR adj (Z0017400) | EACH | 67 | $0.01 | $450.00 | $0.01 | $450.00 | $450.00 | $450.00 |
| 9 | Drainage STR reconst (Z0018600) | EACH | 19 | $1,500.00 | $1,450.00 | $1,170.00 | $2,100.00 | $1,450.00 | $1,450.00 |
| 10 | Tree trunk protection (20101100) | EACH | 13 | $0.01 | $200.00 | $175.00 | $50.00 | $100.00 | $200.00 |
| 11 | Tree root pruning (20101200) | EACH | 15 | $0.01 | $200.00 | $140.00 | $50.00 | $130.00 | $200.00 |
| 12 | Earth excavation (20200100) | CY | 44 | $50.00 | $105.00 | $80.00 | $74.00 | $100.00 | $157.00 |
| 13 | Topsoil F & P 4 (21101615) | SY | 375 | $6.00 | $12.50 | $15.00 | $7.00 | $6.00 | $12.50 |
| 14 | Sodding salt tolerant (25200110) | SY | 375 | $30.00 | $25.00 | $40.00 | $8.00 | $30.00 | $25.00 |
| 15 | Supple watering (25200200) | UNIT | 12 | $0.01 | $25.00 | $180.00 | $77.00 | $0.01 | $25.00 |
| 16 | Perimeter eros bar (28000400) | LF | 380 | $0.01 | $4.50 | $8.00 | $1.00 | $2.10 | $4.50 |
| 17 | Inlet filters (28000510) | EACH | 32 | $0.01 | $150.00 | $167.00 | $15.00 | $150.00 | $200.00 |
| 18 | Agg base cse B 4 (35101600) | SY | 444 | $13.00 | $7.35 | $8.00 | $9.15 | $7.20 | $15.00 |
| 19 | Bit matls tack CT (40600290) | LB | 17,181 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $1.00 |
| 20 | Long joint sealant (40600370) | LF | 11,302 | $3.10 | $3.00 | $3.40 | $2.68 | $3.50 | $3.00 |
| 21 | Mix CR JTS flangewys (40600400) | TON | 32 | $0.01 | $300.00 | $50.00 | $100.00 | $50.00 | $375.00 |
| 22 | HMA surf rem butt JT (40600982) | SY | 273 | $0.01 | $20.00 | $23.50 | $16.00 | $0.01 | $16.50 |
| 23 | P HMA BC IL-4.75 N50 (40603200) | TON | 1,400 | $115.00 | $108.00 | $124.00 | $132.00 | $125.00 | $123.00 |
| 24 | HMA SC IL-9.5 D N70 (40604062) | TON | 2,495 | $95.00 | $88.00 | $99.00 | $103.00 | $98.00 | $102.50 |
| 25 | PC conc sidewalk 5 (42400200) | SF | 4,763 | $13.00 | $11.80 | $10.00 | $8.25 | $11.00 | $9.25 |
| 26 | Detectable warnings (42400800) | SF | 673 | $20.00 | $36.75 | $45.00 | $35.00 | $30.00 | $37.50 |
| 27 | HMA surf rem 2 1/2 (44000159) | SY | 25,452 | $4.50 | $4.00 | $3.90 | $3.10 | $3.05 | $4.10 |
| 28 | Sidewalk rem (44000600) | SF | 4,818 | $4.20 | $4.10 | $2.00 | $1.25 | $3.00 | $2.35 |
| 29 | CL D patch T1 4 (44201690) | SY | 124 | $75.00 | $34.00 | $100.00 | $30.00 | $20.00 | $64.00 |
| 30 | CL D patch T2 4 (44201692) | SY | 124 | $65.00 | $27.00 | $70.00 | $30.00 | $20.00 | $54.00 |
| 31 | CL D patch T3 4 (44201694) | SY | 248 | $60.00 | $25.00 | $60.00 | $30.00 | $20.00 | $44.00 |
| 32 | CL D patch T4 4 (44201696) | SY | 248 | $53.00 | $22.00 | $50.00 | $30.00 | $20.00 | $40.00 |
| 33 | CL D patch T1 12 (44201785) | SY | 124 | $150.00 | $117.00 | $180.00 | $70.00 | $50.00 | $162.00 |
| 34 | CL D patch T2 12 (44201789) | SY | 124 | $125.00 | $102.00 | $140.00 | $70.00 | $50.00 | $144.00 |
| 35 | CL D patch T3 12 (44201794) | SY | 248 | $110.00 | $99.00 | $125.00 | $70.00 | $50.00 | $123.00 |
| 36 | CL D patch T4 12 (44201796) | SY | 248 | $89.00 | $85.00 | $110.00 | $70.00 | $50.00 | $114.00 |
| 37 | Valve box adj (60266600) | EACH | 9 | $500.00 | $350.00 | $450.00 | $227.00 | $350.00 | $350.00 |
| 38 | FR & grates adjust (60300105) | EACH | 69 | $0.01 | $450.00 | $0.01 | $435.00 | $450.00 | $450.00 |
| 39 | FR & lids T1 CL (60406100) | EACH | 10 | $500.00 | $450.00 | $380.00 | $450.00 | $450.00 | $465.00 |
| 40 | Engr field office A (67000400) | CAL MO | 4 | $1.00 | $2,600.00 | $2,000.00 | $3,500.00 | $3,500.00 | $3,500.00 |
| 41 | Mobilization (67100100) | LS | 1 | $60,000 | $67,601 | $66,500 | $69,000 | $71,000 | $79,009 |
| 42 | TR cont & prot 701502 (70102622) | LS | 1 | $13,000 | $10,800 | $31,018 | $106,000 | $136,850 | $54,000 |
| 43 | TR cont & prot 701701 (70102635) | LS | 1 | $100.00 | $1.00 | $1.00 | $1.00 | $500.00 | $1.00 |
| 44 | TR cont & prot 701801 (70102640) | LS | 1 | $100.00 | $1.00 | $1.00 | $1.00 | $500.00 | $1.00 |
| 45 | Changeable message SN (70107025) | CAL DAY | 80 | $45.00 | $50.00 | $50.00 | $10.00 | $50.00 | $50.00 |
| 46 | Short term pavt mking (70300100) | LF | 12,805 | $1.50 | $1.35 | $0.01 | $0.01 | $1.00 | $0.01 |
| 47 | SHRT TRM pavt MK rem (70300150) | SF | 8,486 | $2.00 | $0.01 | $0.01 | $0.01 | $0.01 | $0.10 |
| 48 | THPL PVT MK LTR & sym (78000100) | SF | 790 | $5.50 | $5.00 | $5.00 | $5.50 | $5.50 | $5.00 |
| 49 | THPL PVT MK line 4 (78000200) | LF | 13,349 | $0.70 | $0.66 | $0.66 | $0.73 | $0.70 | $0.66 |
| 50 | THPL PVT MK line 6 (78000400) | LF | 1,080 | $1.25 | $1.00 | $1.00 | $1.10 | $1.25 | $1.00 |
| 51 | THPL PVT MK line 12 (78000600) | LF | 2,538 | $2.35 | $2.50 | $2.50 | $2.75 | $2.35 | $2.50 |
| 52 | THPL PVT MK line 24 (78000650) | LF | 233 | $5.50 | $5.00 | $5.00 | $5.50 | $5.50 | $5.00 |
| 53 | Raised refl pavt MKR (78100100) | EACH | 305 | $52.00 | $40.00 | $40.00 | $44.00 | $42.00 | $40.00 |
| 54 | Raised ref PVT MK rem (78300200) | EACH | 290 | $0.01 | $12.00 | $0.01 | $25.00 | $20.00 | $20.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of September 19, 2025. Compiled by Mirage Metrics.