IDOT contract 62G52 bid tabulation

Section 2018-039-RS. Let by Illinois DOT on June 13, 2025, Will, District 01. 6 bids received; low bid $3,382,064 by K-Five Construction Corporation.

Owner
Illinois DOT
Letting
13 JUN 2025
Pay items
65
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1K-Five Construction Corporation$3,382,064Low
2Builders Paving, LLC$3,756,280+11%
3Gallagher Asphalt Corporation$3,788,246+12%
4Austin Tyler Construction, Inc.$4,048,601+20%
5P. T. Ferro Construction Co.$4,293,213+27%
6R. W. Dunteman Company$4,527,021+34%
IDOT contract 62G52: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. K-Five Construction Corporation2. Builders Paving, LLC3. Gallagher Asphalt Corporation4. Austin Tyler Construction, Inc.5. P. T. Ferro Construction Co.6. R. W. Dunteman Company
1Grading & shap SHLDRS (X2020110)UNIT41$100.00$93.00$200.00$165.00$0.01$208.66
2Temporary ramp SPL (X4060995)SY460$14.00$42.00$60.00$0.01$0.01$12.14
3CC&G RMVL repl < = 10 (X4400501)LF40$200.00$150.00$260.00$108.00$100.00$265.00
4CC&G RMVL repl > 10FT (X4400503)LF80$145.00$150.00$157.00$97.00$100.00$250.00
5SS cleaned 12 (X5537800)LF450$3.00$15.00$3.25$15.00$3.00$15.00
6FR & lids adjust SPL (X6030310)EACH21$1,285.00$1,285.00$1,285.00$1,200.00$1,000.00$1,285.00
7Engrs FLD ofc TY A D1 (X6700407)CAL MO12$3,300.00$2,350.00$500.00$4,500.00$1.00$3,000.00
8Temp info signing (X7200061)SF308.40$16.00$15.00$18.00$14.00$15.00$16.00
9Intercept EX conduit (X8100863)EACH1$745.45$745.00$800.00$500.00$500.00$770.64
10Det loop repl (X8860105)LF2,892$29.51$30.00$31.00$30.00$30.00$30.51
11Vid veh det sys SN AP (X8891009)EACH3$9,722.71$9,725.00$10,500$12,000$12,000$10,051
12Drainage STR cleaned (Z0018500)EACH30$465.00$800.00$400.00$800.00$465.00$800.00
13Tree remov 6-15 (20100110)UNIT40$35.00$59.00$59.00$38.00$35.00$35.00
14Tree prun over 10 (20101350)EACH8$38.00$200.00$200.00$35.00$38.00$38.00
15Topsoil F & P 4 (21101615)SY30$75.00$65.00$60.00$65.00$10.00$65.00
16Sodding salt tolerant (25200110)SY30$75.00$160.00$70.00$160.00$240.00$160.00
17Bit matls tack CT (40600290)LB49,185$0.01$1.00$0.01$0.01$0.01$0.97
18Long joint sealant (40600370)LF43,895$2.60$3.00$3.00$3.50$3.50$2.43
19Mix CR JTS flangewys (40600400)TON109$50.00$350.00$50.00$300.00$0.01$362.23
20HMA surf rem butt JT (40600982)SY410$0.01$25.00$0.01$20.00$0.01$10.00
21HMA repl over patch (40601005)TON2,755$57.00$65.00$80.00$120.00$90.00$139.55
22P HMA BC IL19.0 N90 (40603240)TON9,125$88.00$70.00$105.00$95.00$85.00$102.11
23P HMA SC SMA 9.5 F N80 (40605026)TON7,096$121.00$105.00$140.00$120.00$110.00$123.92
24Protective coat (42001300)SY40$1.00$15.00$3.00$5.00$10.00$1.00
25HMA surf rem 4 (44000165)SY72,400$4.75$10.00$5.70$4.00$6.00$5.93
26HMA RM OV patch 7 1/2 (44002230)SY6,550$0.01$15.00$15.00$33.50$10.00$35.34
27CL D patch T2 9 (44201753)SY580$28.50$50.00$40.00$93.00$80.00$121.64
28CL D patch T3 9 (44201757)SY2,900$28.50$45.00$35.00$88.50$80.00$112.69
29CL D patch T4 9 (44201759)SY2,320$28.50$40.00$35.00$82.00$80.00$109.01
30Agg wedge SHLD type B (48102100)TON139$60.50$55.00$125.00$38.00$60.00$45.37
31CB adjust (60250200)EACH4$550.00$550.00$600.00$750.00$500.00$550.00
32CB reconst (60252800)EACH4$1,650.00$1,650.00$1,700.00$1,350.00$500.00$1,650.00
33Man adjust (60255500)EACH1$550.00$550.00$600.00$750.00$1,000.00$550.00
34Inlets adjust (60260100)EACH1$550.00$550.00$600.00$750.00$500.00$550.00
35FR & grates adjust (60300105)EACH3$550.00$550.00$600.00$750.00$1,000.00$550.00
36FR & lids adjust (60300305)EACH4$550.00$550.00$600.00$750.00$1,000.00$550.00
37Pipe culv cleaned 18 (60920018)LF84$28.00$50.00$3.50$60.00$28.00$50.00
38Mobilization (67100100)LS1$204,277$365,700$227,000$219,000$257,000$246,838
39TR cont & prot 701606 (70102625)LS1$287,156$2,995.00$28,000$500.00$2,995.00$45,821
40TR cont & prot 701601 (70102630)LS1$3,500.00$2,995.00$1.00$5,500.00$2,995.00$3,500.00
41TR cont & prot 701602 (70102632)LS1$1.00$2,995.00$1.00$5,500.00$685,000$1.00
42TR cont & prot 701701 (70102635)LS1$5,000.00$2,995.00$1.00$11,500$2,995.00$5,000.00
43TR cont & prot 701801 (70102640)LS1$1.00$2,995.00$1,500.00$100.00$2,995.00$1.00
44Short term pavt mking (70300100)LF21,805$1.00$1.00$0.80$1.20$0.01$1.29
45SHRT TRM pavt MK rem (70300150)SF2,960$2.00$0.05$3.00$1.00$0.01$2.29
46Temp PVT MK LTR & sym paint (70300211)SF3,985$0.01$1.75$1.45$2.10$1.75$1.25
47Temp PVT MK line 4 - paint (70300221)LF83,580$0.01$0.35$0.32$0.35$0.35$0.25
48Temp PVT MK line 6 - paint (70300241)LF22,110$0.01$0.50$0.48$0.55$0.53$0.35
49Temp PVT MK line 8 - paint (70300251)LF840$0.01$0.70$1.25$0.85$0.70$0.50
50Temp PVT MK line 12 - paint (70300261)LF4,935$0.01$1.00$1.25$1.05$1.06$0.80
51Temp PVT MK line 24 - paint (70300281)LF2,235$0.01$1.60$1.40$2.10$1.60$1.25
52Temp PVT MK L4 T4 tape (70307120)LF5,455$2.15$1.95$1.32$2.50$1.25$2.00
53THPL PVT MK LTR & sym (78000100)SF1,330$4.00$4.00$6.00$4.00$4.00$4.00
54THPL PVT MK line 4 (78000200)LF27,860$0.99$1.00$0.92$0.99$0.99$0.99
55THPL PVT MK line 6 (78000400)LF7,370$1.53$1.50$1.50$1.53$1.53$1.53
56THPL PVT MK line 8 (78000500)LF280$2.05$2.05$1.75$2.05$2.05$2.05
57THPL PVT MK line 12 (78000600)LF1,645$3.07$3.05$3.00$3.07$3.07$3.07
58THPL PVT MK line 24 (78000650)LF745$6.14$6.15$6.00$6.14$6.14$6.14
59Raised refl pavt MKR (78100100)EACH1,129$29.50$29.50$50.00$29.50$29.50$29.50
60Raised ref PVT MK rem (78300200)EACH1,129$9.00$12.50$0.01$13.50$0.01$15.85
61Undrgrd C galvs 2 (81028200)LF71$53.69$54.00$56.00$70.00$70.00$55.50
62HD handhole (81400200)EACH5$4,285.45$4,300.00$4,500.00$5,000.00$5,000.00$4,430.28
63Main EX TR sig instal (85000200)EACH2$525.00$525.00$550.00$2,500.00$2,500.00$542.74
64Drill EX HD handhole (87900205)EACH3$938.93$940.00$1,000.00$2,000.00$2,000.00$970.66
65Remov EX handhole (89502380)EACH5$717.95$720.00$750.00$3,000.00$3,000.00$742.21
IDOT contract 62G52: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of June 13, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy