IDOT contract 62V71 bid tabulation
Section FAP. Let by Illinois DOT on April 24, 2026, Will, District 01. 6 bids received; low bid $2,821,627 by D. Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 24 APR 2026
- Pay items
- 108
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D. Construction, Inc. | $2,821,627 | Low |
| 2 | P. T. Ferro Construction Co. | $2,846,617 | +1.0% |
| 3 | Gallagher Asphalt Corporation | $2,967,327 | +5.0% |
| 4 | K-Five Construction Corporation | $3,115,696 | +10% |
| 5 | Austin Tyler Construction, Inc. | $3,125,700 | +11% |
| 6 | Builders Paving, LLC | $3,206,888 | +14% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D. Construction, Inc. | 2. P. T. Ferro Construction Co. | 3. Gallagher Asphalt Corporation | 4. K-Five Construction Corporation | 5. Austin Tyler Construction, Inc. | 6. Builders Paving, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Prun safety/equip CLR (K1004595) | LS | 1 | $38,500 | $6,500.00 | $7,000.00 | $35,000 | $38,041 | $26,000 |
| 2 | Constructn layout SPL (X0320050) | LS | 1 | $83,600 | $15,000 | $7,534.00 | $5,000.00 | $27,172 | $15,000 |
| 3 | TV inspect of sewer (X0325207) | LF | 565 | $7.70 | $15.00 | $7.45 | $7.00 | $6.52 | $15.00 |
| 4 | Ped signal post 5 FT (X1400378) | EACH | 20 | $2,932.09 | $2,666.00 | $2,840.00 | $2,700.00 | $2,897.17 | $2,666.00 |
| 5 | Tree remov acres SPL (X2010350) | ACRE | 2.30 | $10,450 | $9,500.00 | $10,110 | $15,000 | $10,326 | $9,500.00 |
| 6 | Selective clearing (X2010516) | UNIT | 0.25 | $5,000.00 | $300.00 | $320.00 | $10,800 | $326.07 | $300.00 |
| 7 | Detectable warn SPL (X4240800) | SF | 134 | $50.00 | $35.00 | $30.00 | $65.00 | $33.97 | $40.00 |
| 8 | Brick sidewalk rem (X4400060) | SF | 1,228 | $6.00 | $4.00 | $2.30 | $3.00 | $3.10 | $2.00 |
| 9 | CC&G RMVL repl < = 10 (X4400501) | LF | 50 | $55.00 | $100.00 | $95.00 | $60.00 | $86.71 | $82.00 |
| 10 | CC&G RMVL repl > 10FT (X4400503) | LF | 922 | $45.00 | $65.00 | $56.00 | $50.00 | $55.00 | $65.00 |
| 11 | SS cleaned 12 (X5537800) | LF | 775 | $6.60 | $7.00 | $6.40 | $6.00 | $13.04 | $4.00 |
| 12 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 12 | $5,000.00 | $1.00 | $500.00 | $3,500.00 | $3,260.69 | $2,500.00 |
| 13 | Temp info signing (X7200061) | SF | 210 | $25.00 | $35.00 | $37.30 | $15.00 | $16.30 | $30.00 |
| 14 | Rebld EX DBL handhole (X8140238) | EACH | 2 | $3,580.50 | $3,255.00 | $3,466.00 | $3,255.00 | $2,092.82 | $3,255.00 |
| 15 | Accessible ped signal (X8760200) | EACH | 46 | $2,450.42 | $2,228.00 | $2,370.00 | $2,300.00 | $2,421.23 | $2,228.00 |
| 16 | Conc FDN TY A 12D (X8780012) | LF | 80 | $522.50 | $475.00 | $506.00 | $475.00 | $516.28 | $475.00 |
| 17 | LED SF lens cover (X8809005) | EACH | 1 | $341.00 | $310.00 | $330.00 | $310.00 | $336.94 | $310.00 |
| 18 | Video veh det sys (X8891001) | EACH | 1 | $13,470 | $12,246 | $13,000 | $12,250 | $13,310 | $12,246 |
| 19 | Drainage STR cleaned (Z0018500) | EACH | 10 | $462.00 | $750.00 | $446.00 | $420.00 | $543.45 | $500.00 |
| 20 | RE-optimize TR sig sys 1 (Z0033044) | EACH | 6 | $1,401.40 | $1,274.00 | $1,353.00 | $1,275.00 | $1,384.71 | $1,274.00 |
| 21 | RR prot liability ins (Z0048665) | LS | 1 | $5,000.00 | $10,000 | $3,800.00 | $3,500.00 | $5,434.49 | $12,000 |
| 22 | Tree remov 6-15 (20100110) | UNIT | 225.50 | $30.80 | $28.00 | $30.00 | $36.00 | $30.43 | $28.00 |
| 23 | Tree remov over 15 (20100210) | UNIT | 166.30 | $35.20 | $32.00 | $34.00 | $48.00 | $34.78 | $32.00 |
| 24 | Tree prun 1-10 (20101300) | EACH | 42 | $55.00 | $50.00 | $53.00 | $150.00 | $54.34 | $50.00 |
| 25 | Tree prun over 10 (20101350) | EACH | 11 | $220.00 | $200.00 | $212.00 | $250.00 | $217.38 | $200.00 |
| 26 | Earth excavation (20200100) | CY | 130 | $50.00 | $60.00 | $80.00 | $65.00 | $103.44 | $95.00 |
| 27 | Trench backfill (20800150) | CY | 65 | $60.00 | $50.00 | $45.00 | $85.00 | $66.58 | $85.00 |
| 28 | Topsoil F & P 4 (21101615) | SY | 137 | $5.50 | $0.01 | $1.05 | $14.00 | $15.22 | $14.00 |
| 29 | Nitrogen fert nutr (25000400) | LB | 1.80 | $3.30 | $0.01 | $26.50 | $12.00 | $13.04 | $12.00 |
| 30 | Phosphorus fert nutr (25000500) | LB | 1.80 | $3.30 | $0.01 | $26.50 | $12.00 | $13.04 | $12.00 |
| 31 | Potassium fert nutr (25000600) | LB | 1.80 | $3.30 | $0.01 | $26.50 | $12.00 | $13.04 | $12.00 |
| 32 | Sodding salt tolerant (25200110) | SY | 137 | $66.00 | $0.01 | $52.00 | $50.00 | $54.34 | $50.00 |
| 33 | Supple watering (25200200) | UNIT | 1 | $220.00 | $0.01 | $473.00 | $40.00 | $43.48 | $40.00 |
| 34 | Bit matls tack CT (40600290) | LB | 65,533 | $0.01 | $0.01 | $1.15 | $0.01 | $0.38 | $0.01 |
| 35 | Long joint sealant (40600370) | LF | 52,333 | $2.81 | $2.60 | $2.70 | $2.50 | $4.00 | $2.75 |
| 36 | Mix CR JTS flangewys (40600400) | TON | 146 | $0.01 | $0.01 | $50.00 | $50.00 | $318.44 | $565.00 |
| 37 | HMA surf rem butt JT (40600982) | SY | 756 | $0.01 | $0.01 | $23.60 | $0.01 | $21.96 | $35.00 |
| 38 | P HMA BC IL-4.75 N50 (40603200) | TON | 4,005 | $102.00 | $110.00 | $119.00 | $111.00 | $105.05 | $102.00 |
| 39 | HMA SC IL-9.5 D N70 (40604062) | TON | 8,156 | $82.00 | $89.00 | $96.00 | $93.25 | $81.38 | $79.00 |
| 40 | Protective coat (42001300) | SY | 725 | $1.00 | $1.50 | $0.01 | $1.00 | $2.17 | $0.10 |
| 41 | PC conc sidewalk 5 (42400200) | SF | 4,641 | $9.00 | $12.00 | $8.80 | $10.00 | $10.71 | $9.00 |
| 42 | Detectable warnings (42400800) | SF | 303 | $25.00 | $20.00 | $20.00 | $30.00 | $27.17 | $30.00 |
| 43 | HMA surf rem 2 1/4 (44000158) | SY | 97,085 | $1.97 | $2.70 | $2.25 | $3.00 | $1.97 | $4.50 |
| 44 | Comb curb gutter rem (44000500) | LF | 50 | $10.00 | $20.00 | $14.70 | $15.00 | $15.46 | $15.00 |
| 45 | Sidewalk rem (44000600) | SF | 3,456 | $2.50 | $4.00 | $3.20 | $2.50 | $2.60 | $2.00 |
| 46 | CL D patch T2 14 (44201815) | SY | 40 | $130.00 | $200.00 | $320.00 | $200.00 | $178.76 | $155.00 |
| 47 | CL D patch T3 14 (44201819) | SY | 50 | $130.00 | $175.00 | $175.00 | $200.00 | $173.48 | $155.00 |
| 48 | CL D patch T4 14 (44201821) | SY | 300 | $130.00 | $125.00 | $160.00 | $150.00 | $165.76 | $155.00 |
| 49 | Storm sew CL A 1 12 (550A0050) | LF | 120 | $80.00 | $85.00 | $200.00 | $125.00 | $61.71 | $125.00 |
| 50 | CB TC T23F&G (60208230) | EACH | 3 | $2,000.00 | $2,100.00 | $2,000.00 | $3,500.00 | $2,313.38 | $3,500.00 |
| 51 | Man TA 4 dia T1F CL (60218400) | EACH | 1 | $4,000.00 | $4,000.00 | $2,600.00 | $7,500.00 | $3,117.68 | $7,500.00 |
| 52 | CB adjust (60250200) | EACH | 5 | $700.00 | $350.00 | $360.00 | $800.00 | $414.47 | $800.00 |
| 53 | Man adjust (60255500) | EACH | 3 | $800.00 | $500.00 | $350.00 | $800.00 | $414.47 | $800.00 |
| 54 | Man reconst (60257900) | EACH | 2 | $1,500.00 | $1,500.00 | $1,430.00 | $2,100.00 | $1,962.22 | $2,100.00 |
| 55 | Valve box adj (60266600) | EACH | 2 | $500.00 | $350.00 | $250.00 | $1,000.00 | $331.19 | $1,000.00 |
| 56 | FR & grates adjust (60300105) | EACH | 2 | $650.00 | $350.00 | $380.00 | $800.00 | $414.47 | $800.00 |
| 57 | FR & lids adjust (60300305) | EACH | 41 | $650.00 | $350.00 | $380.00 | $800.00 | $414.47 | $800.00 |
| 58 | FR & lids T1 ADA compl OL (60406001) | EACH | 7 | $600.00 | $600.00 | $240.00 | $600.00 | $577.51 | $600.00 |
| 59 | Comb CC&G TB6.12 (60603800) | LF | 50 | $60.00 | $100.00 | $51.90 | $45.00 | $38.69 | $52.00 |
| 60 | Pipe culv cleaned 12 (60920012) | LF | 85 | $11.00 | $50.00 | $10.60 | $10.00 | $10.87 | $20.00 |
| 61 | Non SPL waste disposl (66900200) | CY | 130 | $70.00 | $90.00 | $60.00 | $125.00 | $118.33 | $130.00 |
| 62 | Soil disposal analy (66900530) | EACH | 3 | $1,595.00 | $1,450.00 | $1,540.00 | $1,450.00 | $1,086.90 | $1,450.00 |
| 63 | Reg sub P-const plan (66901001) | LS | 1 | $3,410.00 | $3,100.00 | $3,293.00 | $3,100.00 | $1,086.90 | $3,100.00 |
| 64 | Reg sub F con report (66901003) | LS | 1 | $1,320.00 | $1,200.00 | $1,274.00 | $1,200.00 | $543.45 | $1,200.00 |
| 65 | Reg sub mon (66901006) | CAL DAY | 10 | $1,000.00 | $680.00 | $722.00 | $680.00 | $815.17 | $680.00 |
| 66 | Mobilization (67100100) | LS | 1 | $100,000 | $150,000 | $138,000 | $186,000 | $186,000 | $284,204 |
| 67 | TR cont & prot 701501 (70102620) | LS | 1 | $0.01 | $350.00 | $350.00 | $500.00 | $5,434.49 | $500.00 |
| 68 | TR cont & prot 701502 (70102622) | LS | 1 | $0.01 | $350.00 | $350.00 | $1.00 | $1.00 | $500.00 |
| 69 | TR cont & prot 701606 (70102625) | LS | 1 | $87,820 | $2,500.00 | $62,000 | $25,000 | $26,086 | $3,500.00 |
| 70 | TR cont & prot 701602 (70102632) | LS | 1 | $0.01 | $115,000 | $10,800 | $1.00 | $1.00 | $15,000 |
| 71 | TR cont & prot 701611 (70102634) | LS | 1 | $0.01 | $350.00 | $350.00 | $1.00 | $1.00 | $500.00 |
| 72 | TR cont & prot 701701 (70102635) | LS | 1 | $0.01 | $500.00 | $500.00 | $1.00 | $2,173.80 | $1,000.00 |
| 73 | TR cont & prot 701801 (70102640) | LS | 1 | $0.01 | $350.00 | $350.00 | $500.00 | $2,173.80 | $1,000.00 |
| 74 | Short term pavt mking (70300100) | LF | 30,198 | $0.01 | $0.01 | $0.01 | $1.00 | $2.17 | $1.00 |
| 75 | SHRT TRM pavt MK rem (70300150) | SF | 2,550 | $0.01 | $0.01 | $0.01 | $12.00 | $3.26 | $2.00 |
| 76 | Temp PVT MK LTR & sym paint (70300211) | SF | 1,602 | $0.01 | $0.01 | $0.01 | $2.00 | $1.74 | $0.01 |
| 77 | Temp PVT MK line 4 - paint (70300221) | LF | 100,144 | $0.01 | $0.01 | $0.01 | $0.30 | $0.29 | $0.01 |
| 78 | Temp PVT MK line 6 - paint (70300241) | LF | 4,762 | $0.01 | $0.01 | $0.01 | $0.45 | $0.43 | $0.01 |
| 79 | Temp PVT MK line 8 - paint (70300251) | LF | 90 | $0.01 | $0.01 | $0.01 | $0.60 | $0.60 | $0.01 |
| 80 | Temp PVT MK line 12 - paint (70300261) | LF | 27,370 | $0.01 | $0.01 | $0.01 | $0.90 | $0.87 | $0.01 |
| 81 | Temp PVT MK line 24 - paint (70300281) | LF | 2,192 | $0.01 | $0.01 | $0.01 | $1.80 | $1.74 | $0.01 |
| 82 | Temp PVT MK L4 T4 tape (70307120) | LF | 7,550 | $0.01 | $0.01 | $0.01 | $1.40 | $2.17 | $1.00 |
| 83 | THPL PVT MK LTR & sym (78000100) | SF | 801 | $4.40 | $4.00 | $4.25 | $4.00 | $5.71 | $6.00 |
| 84 | THPL PVT MK line 4 (78000200) | LF | 50,072 | $0.72 | $0.65 | $0.70 | $0.65 | $0.79 | $0.50 |
| 85 | THPL PVT MK line 6 (78000400) | LF | 2,381 | $1.10 | $1.00 | $1.05 | $1.00 | $1.25 | $0.70 |
| 86 | THPL PVT MK line 8 (78000500) | LF | 45 | $2.20 | $2.00 | $2.10 | $2.00 | $1.63 | $1.25 |
| 87 | THPL PVT MK line 12 (78000600) | LF | 13,685 | $2.20 | $2.00 | $2.10 | $2.00 | $2.45 | $2.50 |
| 88 | THPL PVT MK line 24 (78000650) | LF | 1,096 | $4.40 | $4.00 | $4.25 | $4.00 | $5.71 | $6.00 |
| 89 | Mod ureth PM line 4 (78009004) | LF | 383 | $16.50 | $15.00 | $15.90 | $15.00 | $15.22 | $5.00 |
| 90 | Raised refl pavt MKR (78100100) | EACH | 1,450 | $42.35 | $38.50 | $40.90 | $38.50 | $45.65 | $39.00 |
| 91 | Raised ref PVT MK rem (78300200) | EACH | 1,450 | $7.50 | $0.01 | $0.01 | $14.30 | $16.30 | $14.00 |
| 92 | Undrgrd C galvs 2 (81028200) | LF | 138 | $56.38 | $51.25 | $54.40 | $51.25 | $55.70 | $51.25 |
| 93 | Main EX TR sig instal (85000200) | EACH | 6 | $4,400.00 | $4,000.00 | $4,248.00 | $4,000.00 | $4,347.59 | $4,000.00 |
| 94 | Elcbl C signal 14 2C (87301215) | LF | 3,109 | $5.83 | $5.30 | $5.60 | $5.30 | $5.76 | $5.30 |
| 95 | Elcbl C signal 14 3C (87301225) | LF | 322 | $6.05 | $5.50 | $5.80 | $5.50 | $5.98 | $5.50 |
| 96 | Elcbl C signal 14 5C (87301245) | LF | 328 | $6.16 | $5.60 | $5.95 | $5.60 | $6.09 | $5.60 |
| 97 | Elcbl C lead 14 1PR (87301305) | LF | 378 | $5.83 | $5.30 | $5.60 | $5.30 | $5.76 | $5.30 |
| 98 | Elcbl C egrdc 6 1C (87301900) | LF | 198 | $7.37 | $6.70 | $7.10 | $6.70 | $7.28 | $6.70 |
| 99 | TS post galvs 18 (87502520) | EACH | 1 | $3,795.00 | $3,450.00 | $3,665.00 | $3,450.00 | $3,749.80 | $3,450.00 |
| 100 | Drill EX handhole (87900200) | EACH | 20 | $270.05 | $245.50 | $260.00 | $246.00 | $266.83 | $246.00 |
| 101 | SH LED 1F 3S BM (88030050) | EACH | 1 | $1,513.09 | $1,376.00 | $1,460.00 | $1,400.00 | $1,495.07 | $1,376.00 |
| 102 | Ped SH LED 1F BM CDT (88102717) | EACH | 8 | $1,045.00 | $950.00 | $1,008.00 | $950.00 | $1,032.55 | $950.00 |
| 103 | Inductive loop detect (88500100) | EACH | 4 | $302.50 | $275.00 | $292.00 | $275.00 | $298.90 | $275.00 |
| 104 | Det loop T1 (88600100) | LF | 3,624 | $45.10 | $41.00 | $43.50 | $41.00 | $44.56 | $41.00 |
| 105 | Reloc EX TS equip (89501250) | EACH | 1 | $577.50 | $525.00 | $558.00 | $525.00 | $570.62 | $525.00 |
| 106 | Rem elcbl FR con (89502300) | LF | 2,599 | $1.54 | $1.40 | $1.50 | $1.40 | $1.52 | $1.40 |
| 107 | Remov EX TS equip (89502375) | EACH | 6 | $528.00 | $480.00 | $510.00 | $480.00 | $521.71 | $480.00 |
| 108 | Rebuild EX handhole (89502376) | EACH | 16 | $2,118.05 | $1,925.50 | $2,045.00 | $2,000.00 | $2,092.82 | $1,926.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 24, 2026. Compiled by Mirage Metrics.