IDOT contract 62V71 bid tabulation

Section FAP. Let by Illinois DOT on April 24, 2026, Will, District 01. 6 bids received; low bid $2,821,627 by D. Construction, Inc..

Owner
Illinois DOT
Letting
24 APR 2026
Pay items
108
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1D. Construction, Inc.$2,821,627Low
2P. T. Ferro Construction Co.$2,846,617+1.0%
3Gallagher Asphalt Corporation$2,967,327+5.0%
4K-Five Construction Corporation$3,115,696+10%
5Austin Tyler Construction, Inc.$3,125,700+11%
6Builders Paving, LLC$3,206,888+14%
IDOT contract 62V71: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. D. Construction, Inc.2. P. T. Ferro Construction Co.3. Gallagher Asphalt Corporation4. K-Five Construction Corporation5. Austin Tyler Construction, Inc.6. Builders Paving, LLC
1Prun safety/equip CLR (K1004595)LS1$38,500$6,500.00$7,000.00$35,000$38,041$26,000
2Constructn layout SPL (X0320050)LS1$83,600$15,000$7,534.00$5,000.00$27,172$15,000
3TV inspect of sewer (X0325207)LF565$7.70$15.00$7.45$7.00$6.52$15.00
4Ped signal post 5 FT (X1400378)EACH20$2,932.09$2,666.00$2,840.00$2,700.00$2,897.17$2,666.00
5Tree remov acres SPL (X2010350)ACRE2.30$10,450$9,500.00$10,110$15,000$10,326$9,500.00
6Selective clearing (X2010516)UNIT0.25$5,000.00$300.00$320.00$10,800$326.07$300.00
7Detectable warn SPL (X4240800)SF134$50.00$35.00$30.00$65.00$33.97$40.00
8Brick sidewalk rem (X4400060)SF1,228$6.00$4.00$2.30$3.00$3.10$2.00
9CC&G RMVL repl < = 10 (X4400501)LF50$55.00$100.00$95.00$60.00$86.71$82.00
10CC&G RMVL repl > 10FT (X4400503)LF922$45.00$65.00$56.00$50.00$55.00$65.00
11SS cleaned 12 (X5537800)LF775$6.60$7.00$6.40$6.00$13.04$4.00
12Engrs FLD ofc TY A D1 (X6700407)CAL MO12$5,000.00$1.00$500.00$3,500.00$3,260.69$2,500.00
13Temp info signing (X7200061)SF210$25.00$35.00$37.30$15.00$16.30$30.00
14Rebld EX DBL handhole (X8140238)EACH2$3,580.50$3,255.00$3,466.00$3,255.00$2,092.82$3,255.00
15Accessible ped signal (X8760200)EACH46$2,450.42$2,228.00$2,370.00$2,300.00$2,421.23$2,228.00
16Conc FDN TY A 12D (X8780012)LF80$522.50$475.00$506.00$475.00$516.28$475.00
17LED SF lens cover (X8809005)EACH1$341.00$310.00$330.00$310.00$336.94$310.00
18Video veh det sys (X8891001)EACH1$13,470$12,246$13,000$12,250$13,310$12,246
19Drainage STR cleaned (Z0018500)EACH10$462.00$750.00$446.00$420.00$543.45$500.00
20RE-optimize TR sig sys 1 (Z0033044)EACH6$1,401.40$1,274.00$1,353.00$1,275.00$1,384.71$1,274.00
21RR prot liability ins (Z0048665)LS1$5,000.00$10,000$3,800.00$3,500.00$5,434.49$12,000
22Tree remov 6-15 (20100110)UNIT225.50$30.80$28.00$30.00$36.00$30.43$28.00
23Tree remov over 15 (20100210)UNIT166.30$35.20$32.00$34.00$48.00$34.78$32.00
24Tree prun 1-10 (20101300)EACH42$55.00$50.00$53.00$150.00$54.34$50.00
25Tree prun over 10 (20101350)EACH11$220.00$200.00$212.00$250.00$217.38$200.00
26Earth excavation (20200100)CY130$50.00$60.00$80.00$65.00$103.44$95.00
27Trench backfill (20800150)CY65$60.00$50.00$45.00$85.00$66.58$85.00
28Topsoil F & P 4 (21101615)SY137$5.50$0.01$1.05$14.00$15.22$14.00
29Nitrogen fert nutr (25000400)LB1.80$3.30$0.01$26.50$12.00$13.04$12.00
30Phosphorus fert nutr (25000500)LB1.80$3.30$0.01$26.50$12.00$13.04$12.00
31Potassium fert nutr (25000600)LB1.80$3.30$0.01$26.50$12.00$13.04$12.00
32Sodding salt tolerant (25200110)SY137$66.00$0.01$52.00$50.00$54.34$50.00
33Supple watering (25200200)UNIT1$220.00$0.01$473.00$40.00$43.48$40.00
34Bit matls tack CT (40600290)LB65,533$0.01$0.01$1.15$0.01$0.38$0.01
35Long joint sealant (40600370)LF52,333$2.81$2.60$2.70$2.50$4.00$2.75
36Mix CR JTS flangewys (40600400)TON146$0.01$0.01$50.00$50.00$318.44$565.00
37HMA surf rem butt JT (40600982)SY756$0.01$0.01$23.60$0.01$21.96$35.00
38P HMA BC IL-4.75 N50 (40603200)TON4,005$102.00$110.00$119.00$111.00$105.05$102.00
39HMA SC IL-9.5 D N70 (40604062)TON8,156$82.00$89.00$96.00$93.25$81.38$79.00
40Protective coat (42001300)SY725$1.00$1.50$0.01$1.00$2.17$0.10
41PC conc sidewalk 5 (42400200)SF4,641$9.00$12.00$8.80$10.00$10.71$9.00
42Detectable warnings (42400800)SF303$25.00$20.00$20.00$30.00$27.17$30.00
43HMA surf rem 2 1/4 (44000158)SY97,085$1.97$2.70$2.25$3.00$1.97$4.50
44Comb curb gutter rem (44000500)LF50$10.00$20.00$14.70$15.00$15.46$15.00
45Sidewalk rem (44000600)SF3,456$2.50$4.00$3.20$2.50$2.60$2.00
46CL D patch T2 14 (44201815)SY40$130.00$200.00$320.00$200.00$178.76$155.00
47CL D patch T3 14 (44201819)SY50$130.00$175.00$175.00$200.00$173.48$155.00
48CL D patch T4 14 (44201821)SY300$130.00$125.00$160.00$150.00$165.76$155.00
49Storm sew CL A 1 12 (550A0050)LF120$80.00$85.00$200.00$125.00$61.71$125.00
50CB TC T23F&G (60208230)EACH3$2,000.00$2,100.00$2,000.00$3,500.00$2,313.38$3,500.00
51Man TA 4 dia T1F CL (60218400)EACH1$4,000.00$4,000.00$2,600.00$7,500.00$3,117.68$7,500.00
52CB adjust (60250200)EACH5$700.00$350.00$360.00$800.00$414.47$800.00
53Man adjust (60255500)EACH3$800.00$500.00$350.00$800.00$414.47$800.00
54Man reconst (60257900)EACH2$1,500.00$1,500.00$1,430.00$2,100.00$1,962.22$2,100.00
55Valve box adj (60266600)EACH2$500.00$350.00$250.00$1,000.00$331.19$1,000.00
56FR & grates adjust (60300105)EACH2$650.00$350.00$380.00$800.00$414.47$800.00
57FR & lids adjust (60300305)EACH41$650.00$350.00$380.00$800.00$414.47$800.00
58FR & lids T1 ADA compl OL (60406001)EACH7$600.00$600.00$240.00$600.00$577.51$600.00
59Comb CC&G TB6.12 (60603800)LF50$60.00$100.00$51.90$45.00$38.69$52.00
60Pipe culv cleaned 12 (60920012)LF85$11.00$50.00$10.60$10.00$10.87$20.00
61Non SPL waste disposl (66900200)CY130$70.00$90.00$60.00$125.00$118.33$130.00
62Soil disposal analy (66900530)EACH3$1,595.00$1,450.00$1,540.00$1,450.00$1,086.90$1,450.00
63Reg sub P-const plan (66901001)LS1$3,410.00$3,100.00$3,293.00$3,100.00$1,086.90$3,100.00
64Reg sub F con report (66901003)LS1$1,320.00$1,200.00$1,274.00$1,200.00$543.45$1,200.00
65Reg sub mon (66901006)CAL DAY10$1,000.00$680.00$722.00$680.00$815.17$680.00
66Mobilization (67100100)LS1$100,000$150,000$138,000$186,000$186,000$284,204
67TR cont & prot 701501 (70102620)LS1$0.01$350.00$350.00$500.00$5,434.49$500.00
68TR cont & prot 701502 (70102622)LS1$0.01$350.00$350.00$1.00$1.00$500.00
69TR cont & prot 701606 (70102625)LS1$87,820$2,500.00$62,000$25,000$26,086$3,500.00
70TR cont & prot 701602 (70102632)LS1$0.01$115,000$10,800$1.00$1.00$15,000
71TR cont & prot 701611 (70102634)LS1$0.01$350.00$350.00$1.00$1.00$500.00
72TR cont & prot 701701 (70102635)LS1$0.01$500.00$500.00$1.00$2,173.80$1,000.00
73TR cont & prot 701801 (70102640)LS1$0.01$350.00$350.00$500.00$2,173.80$1,000.00
74Short term pavt mking (70300100)LF30,198$0.01$0.01$0.01$1.00$2.17$1.00
75SHRT TRM pavt MK rem (70300150)SF2,550$0.01$0.01$0.01$12.00$3.26$2.00
76Temp PVT MK LTR & sym paint (70300211)SF1,602$0.01$0.01$0.01$2.00$1.74$0.01
77Temp PVT MK line 4 - paint (70300221)LF100,144$0.01$0.01$0.01$0.30$0.29$0.01
78Temp PVT MK line 6 - paint (70300241)LF4,762$0.01$0.01$0.01$0.45$0.43$0.01
79Temp PVT MK line 8 - paint (70300251)LF90$0.01$0.01$0.01$0.60$0.60$0.01
80Temp PVT MK line 12 - paint (70300261)LF27,370$0.01$0.01$0.01$0.90$0.87$0.01
81Temp PVT MK line 24 - paint (70300281)LF2,192$0.01$0.01$0.01$1.80$1.74$0.01
82Temp PVT MK L4 T4 tape (70307120)LF7,550$0.01$0.01$0.01$1.40$2.17$1.00
83THPL PVT MK LTR & sym (78000100)SF801$4.40$4.00$4.25$4.00$5.71$6.00
84THPL PVT MK line 4 (78000200)LF50,072$0.72$0.65$0.70$0.65$0.79$0.50
85THPL PVT MK line 6 (78000400)LF2,381$1.10$1.00$1.05$1.00$1.25$0.70
86THPL PVT MK line 8 (78000500)LF45$2.20$2.00$2.10$2.00$1.63$1.25
87THPL PVT MK line 12 (78000600)LF13,685$2.20$2.00$2.10$2.00$2.45$2.50
88THPL PVT MK line 24 (78000650)LF1,096$4.40$4.00$4.25$4.00$5.71$6.00
89Mod ureth PM line 4 (78009004)LF383$16.50$15.00$15.90$15.00$15.22$5.00
90Raised refl pavt MKR (78100100)EACH1,450$42.35$38.50$40.90$38.50$45.65$39.00
91Raised ref PVT MK rem (78300200)EACH1,450$7.50$0.01$0.01$14.30$16.30$14.00
92Undrgrd C galvs 2 (81028200)LF138$56.38$51.25$54.40$51.25$55.70$51.25
93Main EX TR sig instal (85000200)EACH6$4,400.00$4,000.00$4,248.00$4,000.00$4,347.59$4,000.00
94Elcbl C signal 14 2C (87301215)LF3,109$5.83$5.30$5.60$5.30$5.76$5.30
95Elcbl C signal 14 3C (87301225)LF322$6.05$5.50$5.80$5.50$5.98$5.50
96Elcbl C signal 14 5C (87301245)LF328$6.16$5.60$5.95$5.60$6.09$5.60
97Elcbl C lead 14 1PR (87301305)LF378$5.83$5.30$5.60$5.30$5.76$5.30
98Elcbl C egrdc 6 1C (87301900)LF198$7.37$6.70$7.10$6.70$7.28$6.70
99TS post galvs 18 (87502520)EACH1$3,795.00$3,450.00$3,665.00$3,450.00$3,749.80$3,450.00
100Drill EX handhole (87900200)EACH20$270.05$245.50$260.00$246.00$266.83$246.00
101SH LED 1F 3S BM (88030050)EACH1$1,513.09$1,376.00$1,460.00$1,400.00$1,495.07$1,376.00
102Ped SH LED 1F BM CDT (88102717)EACH8$1,045.00$950.00$1,008.00$950.00$1,032.55$950.00
103Inductive loop detect (88500100)EACH4$302.50$275.00$292.00$275.00$298.90$275.00
104Det loop T1 (88600100)LF3,624$45.10$41.00$43.50$41.00$44.56$41.00
105Reloc EX TS equip (89501250)EACH1$577.50$525.00$558.00$525.00$570.62$525.00
106Rem elcbl FR con (89502300)LF2,599$1.54$1.40$1.50$1.40$1.52$1.40
107Remov EX TS equip (89502375)EACH6$528.00$480.00$510.00$480.00$521.71$480.00
108Rebuild EX handhole (89502376)EACH16$2,118.05$1,925.50$2,045.00$2,000.00$2,092.82$1,926.00
IDOT contract 62V71: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of April 24, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy