IDOT contract 62X02 bid tabulation
Section (K-B-2)BR. Let by Illinois DOT on June 13, 2025, Cook, District 01. 2 bids received; low bid $4,238,796 by D. Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 13 JUN 2025
- Pay items
- 109
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D. Construction, Inc. | $4,238,796 | Low |
| 2 | Rausch Infrastructure, LLC | $6,141,473 | +45% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D. Construction, Inc. | 2. Rausch Infrastructure, LLC |
|---|---|---|---|---|---|
| 1 | Pro SS conn to EX SS (X0322916) | EACH | 1 | $2,500.00 | $3,400.00 |
| 2 | Explor trench SPL (X2130010) | LF | 200 | $50.00 | $152.00 |
| 3 | Inlet protection SPL (X2800500) | EACH | 2 | $495.00 | $555.00 |
| 4 | Temp access- com ent (X4022000) | EACH | 1 | $1,500.00 | $34,000 |
| 5 | Floor drain extension (X5030530) | EACH | 16 | $1,500.00 | $1,400.00 |
| 6 | Structural STL removl (X5051204) | LB | 2,160 | $10.00 | $12.00 |
| 7 | Struct steel repair (X5051206) | LB | 20,550 | $50.00 | $105.00 |
| 8 | Clean/paint bearings (X5060700) | EACH | 14 | $2,563.00 | $2,800.00 |
| 9 | Clean drainage system (X5230152) | LS | 1 | $5,500.00 | $6,100.00 |
| 10 | Abandon fill SS (X5509900) | LF | 15 | $150.00 | $154.00 |
| 11 | Pro SS conn to EX man (X5510011) | EACH | 2 | $2,500.00 | $5,000.00 |
| 12 | SS cleaned 12 (X5537800) | LF | 402 | $2.20 | $2.25 |
| 13 | SS cleaned 54 (X5538900) | LF | 182 | $18.70 | $21.00 |
| 14 | Pro man/CB con OV SS (X6025604) | EACH | 4 | $5,000.00 | $4,400.00 |
| 15 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 12 | $5,000.00 | $7,400.00 |
| 16 | Traf cont & prot SPL (X7010216) | LS | 1 | $31,500 | $70,000 |
| 17 | Temp info signing (X7200061) | SF | 178 | $30.00 | $24.00 |
| 18 | RRPM reflector removl (X7830050) | EACH | 132 | $10.00 | $9.00 |
| 19 | RRPM reflector replac (X7830052) | EACH | 132 | $48.40 | $19.00 |
| 20 | Appr slab repair (PD) (Z0001800) | SY | 2 | $1,000.00 | $5,000.00 |
| 21 | C&D lead PT CL RS N1 (Z0007101) | LS | 1 | $192,126 | $320,000 |
| 22 | Clean & PT STL BR N1 (Z0010501) | LS | 1 | $768,640 | $870,000 |
| 23 | Conc BR deck scar 3/8 (Z0012102) | SY | 2,037 | $50.00 | $38.00 |
| 24 | BR DK TH poly ovl 3/8 (Z0012193) | SY | 2,037 | $72.00 | $102.00 |
| 25 | STR rep con DP = < 5 (Z0012754) | SF | 129 | $150.00 | $240.00 |
| 26 | STR rep con DP over 5 (Z0012755) | SF | 33 | $200.00 | $265.00 |
| 27 | Construction layout (Z0013798) | LS | 1 | $20,000 | $37,000 |
| 28 | Deck slab rep (part) (Z0016200) | SY | 18 | $800.00 | $1,500.00 |
| 29 | Drainage STR cleaned (Z0018500) | EACH | 12 | $440.00 | $494.00 |
| 30 | Temp TR signal timing (Z0073510) | EACH | 4 | $660.00 | $864.00 |
| 31 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 |
| 32 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 |
| 33 | Nitrogen fert nutr (20101400) | LB | 2 | $5.50 | $6.00 |
| 34 | Potassium fert nutr (20101600) | LB | 2 | $5.50 | $6.00 |
| 35 | Earth excavation (20200100) | CY | 23 | $100.00 | $200.00 |
| 36 | Trench backfill (20800150) | CY | 605 | $50.00 | $50.00 |
| 37 | Topsoil F & P 6 (21101625) | SY | 95 | $22.00 | $24.00 |
| 38 | Seeding CL 2A (25000210) | ACRE | 0.25 | $6,600.00 | $7,400.00 |
| 39 | Erosion contr blanket (25100630) | SY | 95 | $17.60 | $19.00 |
| 40 | Inlet filters (28000510) | EACH | 32 | $302.50 | $339.00 |
| 41 | Stone riprap CL A3 (28100105) | SY | 19 | $165.00 | $525.00 |
| 42 | Filter fabric (28200200) | SY | 19 | $10.00 | $89.00 |
| 43 | Sub gran mat B 2 (31101180) | SY | 25 | $20.00 | $136.00 |
| 44 | Bit matls tack CT (40600290) | LB | 1,334 | $0.01 | $0.01 |
| 45 | Long joint sealant (40600370) | LF | 800 | $15.94 | $24.00 |
| 46 | Mix CR JTS flangewys (40600400) | TON | 3 | $600.00 | $1,000.00 |
| 47 | P HMA BC IL-4.75 N50 (40603200) | TON | 83 | $130.00 | $284.00 |
| 48 | HMA SC IL-9.5 D N70 (40604062) | TON | 166 | $130.00 | $203.00 |
| 49 | PC conc sidewalk 5 (42400200) | SF | 205 | $16.00 | $24.00 |
| 50 | HMA surf rem 2 1/4 (44000158) | SY | 1,976 | $10.00 | $9.00 |
| 51 | CL D patch T2 8 (44201741) | SY | 40 | $130.00 | $834.00 |
| 52 | CL D patch T3 8 (44201745) | SY | 31 | $130.00 | $853.00 |
| 53 | CL D patch T4 8 (44201747) | SY | 304 | $130.00 | $256.00 |
| 54 | Agg wedge SHLD type B (48102100) | TON | 14 | $50.00 | $256.00 |
| 55 | Conc rem (50102400) | CY | 23.20 | $2,500.00 | $4,000.00 |
| 56 | Protective shield (50157300) | SY | 1,621 | $325.00 | $50.00 |
| 57 | Conc sup-STR (50300255) | CY | 23.20 | $2,500.00 | $6,000.00 |
| 58 | Protective coat (50300300) | SY | 3,155 | $1.00 | $8.00 |
| 59 | F & E struct steel (50500405) | LB | 2,160 | $20.00 | $80.00 |
| 60 | Reinf bars, epoxy CTD (50800205) | LB | 3,060 | $3.50 | $4.50 |
| 61 | Bar splicers (50800515) | EACH | 68 | $50.00 | $182.00 |
| 62 | Parapet railing (50901750) | LF | 16 | $437.65 | $491.00 |
| 63 | Pref JT strip seal (52000110) | LF | 256 | $250.00 | $384.00 |
| 64 | Storm sew CL A 2 10 (550A0330) | LF | 18 | $146.00 | $169.00 |
| 65 | Storm sew CL A 2 12 (550A0340) | LF | 68 | $146.00 | $267.00 |
| 66 | Storm sew CL A 2 18 (550A0380) | LF | 62 | $152.00 | $385.00 |
| 67 | Storm sew CL A 2 24 (550A0410) | LF | 29 | $164.00 | $465.00 |
| 68 | Storm sew CL A 2 30 (550A0430) | LF | 25 | $186.00 | $559.00 |
| 69 | Storm sew CL A 2 36 (550A0450) | LF | 22 | $215.00 | $677.00 |
| 70 | Storm sewer rem 8 (55100300) | LF | 21 | $30.00 | $41.00 |
| 71 | Storm sewer rem 12 (55100500) | LF | 70 | $30.00 | $41.00 |
| 72 | Storm sewer rem 15 (55100700) | LF | 163 | $30.00 | $102.00 |
| 73 | Concrete sealer (58700300) | SF | 6,050 | $2.56 | $2.50 |
| 74 | Epoxy crack injection (59000200) | LF | 144 | $71.50 | $55.00 |
| 75 | CB TA 4 dia T1F OL (60200105) | EACH | 1 | $4,900.00 | $8,700.00 |
| 76 | CB TA 4 dia T8G (60200805) | EACH | 1 | $4,900.00 | $7,500.00 |
| 77 | CB TA 5 dia T1F OL (60203805) | EACH | 1 | $6,600.00 | $13,000 |
| 78 | Man TA 4 dia T1F OL (60218300) | EACH | 1 | $5,200.00 | $10,600 |
| 79 | Man TA 5 dia T1F CL (60221100) | EACH | 1 | $6,200.00 | $15,500 |
| 80 | Man TA 6 dia T1F OL (60223700) | EACH | 1 | $9,800.00 | $22,400 |
| 81 | Man TA 7 dia T1F OL (60224445) | EACH | 1 | $18,000 | $32,700 |
| 82 | Man TA 7 dia T1F CL (60224446) | EACH | 2 | $18,000 | $42,700 |
| 83 | FR & lids adjust (60300305) | EACH | 4 | $1,000.00 | $1,300.00 |
| 84 | Remov manholes (60500040) | EACH | 3 | $1,500.00 | $1,800.00 |
| 85 | Remov catch bas (60500050) | EACH | 1 | $1,500.00 | $3,400.00 |
| 86 | Comb CC&G TB6.12 (60603800) | LF | 9 | $150.00 | $123.00 |
| 87 | Non SPL waste disposl (66900200) | CY | 200 | $100.00 | $138.00 |
| 88 | Soil disposal analy (66900530) | EACH | 1 | $1,925.00 | $2,400.00 |
| 89 | Reg sub P-const plan (66901001) | LS | 1 | $2,475.00 | $3,300.00 |
| 90 | Reg sub F con report (66901003) | LS | 1 | $2,475.00 | $2,800.00 |
| 91 | Reg sub mon (66901006) | CAL DAY | 3 | $1,045.00 | $1,200.00 |
| 92 | Mobilization (67100100) | LS | 1 | $244,800 | $359,000 |
| 93 | Changeable message SN (70107025) | CAL DAY | 180 | $50.00 | $49.00 |
| 94 | SHRT TRM pavt MK rem (70300150) | SF | 5,900 | $0.50 | $1.20 |
| 95 | Temp PVT MK L4 T4 tape (70307120) | LF | 25,996 | $2.00 | $1.40 |
| 96 | Temp PVT MK L12 T4 tape (70307160) | LF | 565 | $5.00 | $4.40 |
| 97 | Temp PVT MK L24 T4 tape (70307210) | LF | 28 | $10.00 | $8.80 |
| 98 | Temp conc barrier (70400100) | LF | 1,050 | $30.00 | $96.00 |
| 99 | Pin temp conc barrier (70400125) | EACH | 107 | $20.00 | $34.00 |
| 100 | Rel temp conc barrier (70400200) | LF | 2,412.50 | $15.00 | $24.00 |
| 101 | Imp attn temp FRN TL2 (70600255) | EACH | 6 | $10,000 | $5,400.00 |
| 102 | Imp attn rel FRN TL2 (70600322) | EACH | 14 | $2,000.00 | $2,700.00 |
| 103 | THPL PVT MK line 4 (78000200) | LF | 3,764 | $2.48 | $1.30 |
| 104 | THPL PVT MK line 24 (78000650) | LF | 275 | $11.88 | $7.40 |
| 105 | Pref PL PM TD STD L 7 (78004635) | LF | 240 | $15.24 | $11.40 |
| 106 | Mod ureth PM line 4 (78009004) | LF | 958 | $5.50 | $2.70 |
| 107 | GRV RCSD PVT MRKG 5 (78011025) | LF | 958 | $3.14 | $2.40 |
| 108 | GRV RCSD PVT MRKG 8 (78011040) | LF | 240 | $9.24 | $3.70 |
| 109 | PVT MKG rem WTR blast (78300202) | SF | 10,418 | $4.00 | $1.60 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 13, 2025. Compiled by Mirage Metrics.