IDOT contract 62Y05 bid tabulation
Section (111-BI)BDR,BJR. Let by Illinois DOT on January 16, 2026, Mchenry, District 01. 4 bids received; low bid $740,984 by Martam Construction Incorporated.
- Owner
- Illinois DOT
- Letting
- 16 JAN 2026
- Pay items
- 50
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Martam Construction Incorporated | $740,984 | Low |
| 2 | Lorig Construction Company | $771,565 | +4.0% |
| 3 | Areatha Construction Co., Inc. | $892,051 | +20% |
| 4 | Alliance Contractors, Inc. | $912,447 | +23% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Martam Construction Incorporated | 2. Lorig Construction Company | 3. Areatha Construction Co., Inc. | 4. Alliance Contractors, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Temp LGHT SNGL LN STG (X0326276) | LS | 1 | $36,000 | $20,000 | $33,105 | $33,105 |
| 2 | BR deck grooving long (X5030250) | SY | 445 | $13.00 | $15.00 | $19.00 | $26.75 |
| 3 | Rep traf B term T1 SP (X6310301) | EACH | 3 | $2,400.00 | $3,400.00 | $2,110.25 | $2,110.24 |
| 4 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 12 | $3,600.00 | $3,200.00 | $3,000.00 | $250.00 |
| 5 | Traf cont & prot SPL (X7010216) | LS | 1 | $83,500 | $110,000 | $15,500 | $39,150 |
| 6 | Temp info signing (X7200061) | SF | 412 | $20.00 | $21.00 | $16.00 | $15.00 |
| 7 | RRPM reflector removl (X7830050) | EACH | 8 | $10.00 | $10.00 | $50.00 | $6.00 |
| 8 | RRPM reflector replac (X7830052) | EACH | 8 | $25.00 | $40.00 | $50.00 | $50.00 |
| 9 | Temp TR signal timing (X8900104) | EACH | 1 | $2,500.00 | $1,400.00 | $2,485.00 | $2,485.00 |
| 10 | BR DK LTX C oly 2 3/4 (Z0006016) | SY | 816 | $155.00 | $160.00 | $255.05 | $186.00 |
| 11 | BR deck scar 3/4 (Z0012130) | SY | 816 | $65.00 | $105.00 | $137.25 | $152.00 |
| 12 | STR rep con DP = < 5 (Z0012754) | SF | 132 | $240.00 | $425.00 | $215.70 | $140.00 |
| 13 | Construction layout (Z0013798) | LS | 1 | $4,000.00 | $10,000 | $6,000.00 | $7,500.00 |
| 14 | Debris removal (Z0015550) | CY | 16 | $128.00 | $350.00 | $649.30 | $400.00 |
| 15 | Diamond grind BR sec (Z0029090) | SY | 742 | $15.00 | $16.00 | $15.55 | $20.25 |
| 16 | Seeding CL 2A (25000210) | ACRE | 0.25 | $10,000 | $10,000 | $9,000.00 | $9,000.00 |
| 17 | Nitrogen fert nutr (25000400) | LB | 23 | $6.00 | $5.00 | $5.00 | $5.00 |
| 18 | Phosphorus fert nutr (25000500) | LB | 23 | $6.00 | $5.00 | $5.00 | $5.00 |
| 19 | Potassium fert nutr (25000600) | LB | 23 | $6.00 | $5.00 | $5.00 | $5.00 |
| 20 | Erosion contr blanket (25100630) | SY | 392 | $6.00 | $5.00 | $5.00 | $5.00 |
| 21 | Temp eros contr seed (28000250) | LB | 9 | $12.00 | $10.00 | $10.00 | $10.00 |
| 22 | Perimeter eros bar (28000400) | LF | 690 | $5.00 | $4.50 | $4.50 | $4.50 |
| 23 | Bit matls tack CT (40600290) | LB | 146 | $1.00 | $0.10 | $0.10 | $0.01 |
| 24 | Long joint sealant (40600370) | LF | 210 | $38.00 | $35.00 | $35.00 | $25.00 |
| 25 | HMA surf rem butt JT (40600982) | SY | 324 | $2.00 | $1.00 | $1.00 | $25.00 |
| 26 | HMA SC IL-9.5 D N70 (40604062) | TON | 19 | $1,300.00 | $1,150.00 | $1,100.00 | $775.00 |
| 27 | Conc rem (50102400) | CY | 12 | $2,400.00 | $3,500.00 | $3,127.00 | $8,175.00 |
| 28 | Conc sup-STR (50300255) | CY | 11.20 | $3,200.00 | $3,800.00 | $5,556.45 | $13,050 |
| 29 | Protective coat (50300300) | SY | 946 | $2.00 | $1.75 | $3.95 | $3.75 |
| 30 | Reinf bars, epoxy CTD (50800205) | LB | 2,450 | $4.00 | $5.00 | $5.20 | $2.95 |
| 31 | Bar splicers (50800515) | EACH | 32 | $63.00 | $82.00 | $72.75 | $70.00 |
| 32 | Pref JT strip seal (52000110) | LF | 118 | $265.00 | $257.00 | $560.30 | $220.00 |
| 33 | Concrete sealer (58700300) | SF | 130 | $5.00 | $22.00 | $4.50 | $7.50 |
| 34 | SPBGR TY A 6FT posts (63000001) | LF | 637.50 | $32.00 | $29.00 | $29.65 | $29.66 |
| 35 | Traf bar term T6B (63100089) | EACH | 1 | $5,200.00 | $6,000.00 | $4,866.00 | $4,866.00 |
| 36 | Guardrail remov (63200310) | LF | 638 | $8.00 | $6.00 | $6.65 | $6.66 |
| 37 | Mobilization (67100100) | LS | 1 | $44,000 | $37,000 | $53,508 | $54,000 |
| 38 | Temp BR traf signals (70106500) | EACH | 1 | $66,000 | $10,000 | $64,367 | $64,367 |
| 39 | Temp rumble strips (70106700) | EACH | 12 | $90.00 | $75.00 | $665.00 | $75.00 |
| 40 | Changeable message SN (70107025) | CAL DAY | 168 | $30.00 | $25.00 | $35.00 | $25.00 |
| 41 | SHRT TRM pavt MK rem (70300150) | SF | 826 | $0.50 | $0.40 | $1.00 | $0.40 |
| 42 | Temp PVT MK line 4 - paint (70300221) | LF | 1,908 | $0.50 | $0.40 | $0.80 | $0.40 |
| 43 | Temp PVT MK L4 T4 tape (70307120) | LF | 2,205 | $1.30 | $1.25 | $1.30 | $1.18 |
| 44 | Temp PVT MK L24 T4 tape (70307210) | LF | 49 | $8.00 | $7.50 | $7.60 | $7.20 |
| 45 | THPL PVT MK line 4 (78000200) | LF | 1,532 | $4.80 | $3.50 | $3.50 | $2.20 |
| 46 | Mod ureth PM line 4 (78009004) | LF | 376 | $15.00 | $15.00 | $15.00 | $8.00 |
| 47 | Raised refl pavt MKR (78100100) | EACH | 3 | $1,600.00 | $1,700.00 | $1,500.00 | $400.00 |
| 48 | Grdrail ref type A (78200005) | EACH | 15 | $15.00 | $12.00 | $12.00 | $12.00 |
| 49 | Raised ref PVT MK rem (78300200) | EACH | 3 | $30.00 | $50.00 | $20.00 | $50.00 |
| 50 | PVT MKG rem WTR blast (78300202) | SF | 1,259 | $3.00 | $2.50 | $2.85 | $2.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.