IDOT contract 62Y14 bid tabulation
Section (1976-165-WRS)BDR,BJR. Let by Illinois DOT on January 16, 2026, Cook, District 01. 4 bids received; low bid $742,733 by D. Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 16 JAN 2026
- Pay items
- 72
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D. Construction, Inc. | $742,733 | Low |
| 2 | MYS, Incorporated | $905,721 | +22% |
| 3 | Lorig Construction Company | $914,997 | +23% |
| 4 | Areatha Construction Co., Inc. | $957,295 | +29% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D. Construction, Inc. | 2. MYS, Incorporated | 3. Lorig Construction Company | 4. Areatha Construction Co., Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Acrylic coating (X0325748) | SY | 20 | $176.00 | $113.10 | $100.00 | $300.00 |
| 2 | Fiber wrap (X0325749) | SF | 180 | $110.00 | $169.65 | $100.00 | $185.00 |
| 3 | Tree remov acres SPL (X2010350) | ACRE | 0.40 | $35,200 | $36,194 | $32,000 | $32,000 |
| 4 | Prun safety/equip CLR (X2100002) | UNIT | 7 | $1,265.00 | $1,300.70 | $500.00 | $1,150.00 |
| 5 | Eros cont blanket SPL (X2511630) | SY | 1,936 | $2.20 | $2.26 | $2.00 | $2.00 |
| 6 | Clean/paint bearings (X5060700) | EACH | 20 | $2,750.00 | $2,827.62 | $2,500.00 | $2,500.00 |
| 7 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 6 | $5,000.00 | $4,677.00 | $3,800.00 | $2,500.00 |
| 8 | Traf cont & prot SPL (X7010216) | LS | 1 | $35,000 | $31,054 | $125,000 | $17,000 |
| 9 | Temp info signing (X7200061) | SF | 64 | $30.00 | $22.62 | $25.00 | $20.00 |
| 10 | Temp TR signal timing (X8900104) | EACH | 4 | $1,375.00 | $848.29 | $750.00 | $1,250.00 |
| 11 | Jack & rem EX bearing (Z0001899) | EACH | 4 | $6,000.00 | $10,369 | $8,000.00 | $10,324 |
| 12 | BR DK LTX C oly 2 3/4 (Z0006016) | SY | 559 | $149.00 | $223.11 | $180.00 | $269.30 |
| 13 | Cleaning bridge seats (Z0010400) | SF | 517 | $5.50 | $5.66 | $5.00 | $2.90 |
| 14 | BR deck scar 3/4 (Z0012130) | SY | 559 | $75.00 | $114.10 | $100.00 | $166.15 |
| 15 | STR rep con DP = < 5 (Z0012754) | SF | 46 | $280.00 | $282.77 | $550.00 | $338.55 |
| 16 | Deck slab rep (FD-T2) (Z0016002) | SY | 3 | $2,000.00 | $2,092.44 | $3,800.00 | $3,746.30 |
| 17 | Diamond grind BR sec (Z0029090) | SY | 559 | $19.04 | $25.29 | $18.00 | $20.00 |
| 18 | P P conc I-BM repair (Z0043800) | SF | 2 | $1,000.00 | $791.73 | $500.00 | $350.00 |
| 19 | Earth excavation (20200100) | CY | 5 | $250.00 | $111.33 | $110.00 | $139.20 |
| 20 | Topsoil F & P var DP (21101600) | SY | 52 | $26.40 | $27.14 | $25.00 | $24.00 |
| 21 | Seeding CL 1B (25000115) | ACRE | 0.40 | $4,620.00 | $4,750.41 | $4,200.00 | $4,200.00 |
| 22 | Nitrogen fert nutr (25000400) | LB | 45 | $3.30 | $3.39 | $3.00 | $3.00 |
| 23 | Potassium fert nutr (25000600) | LB | 45 | $3.30 | $3.39 | $3.00 | $3.00 |
| 24 | Bit matls tack CT (40600290) | LB | 566 | $0.01 | $1.46 | $0.01 | $0.10 |
| 25 | Long joint sealant (40600370) | LF | 284 | $37.63 | $17.51 | $53.00 | $35.00 |
| 26 | HMA surf rem butt JT (40600982) | SY | 444 | $20.00 | $27.00 | $27.00 | $1.00 |
| 27 | HMA SC IL-9.5 D N70 (40604062) | TON | 130 | $130.00 | $310.77 | $255.00 | $250.00 |
| 28 | Bit matls PR CT (40800025) | LB | 222 | $0.01 | $1.46 | $0.01 | $0.10 |
| 29 | Incidental HMA surf (40800050) | TON | 30 | $140.00 | $437.89 | $400.00 | $600.00 |
| 30 | Protective coat (42001300) | SY | 16 | $1.00 | $47.94 | $16.00 | $12.85 |
| 31 | HMA surf rem 1/4 (44000150) | SY | 719 | $5.00 | $14.59 | $17.00 | $22.00 |
| 32 | Comb curb gutter rem (44000500) | LF | 388 | $12.00 | $29.95 | $20.00 | $18.65 |
| 33 | Sidewalk rem (44000600) | SF | 890 | $5.00 | $3.64 | $8.00 | $5.25 |
| 34 | Saw cuts (44213200) | LF | 285 | $5.00 | $2.54 | $7.00 | $4.00 |
| 35 | Relief joint 3 (45000120) | LF | 147 | $100.00 | $96.14 | $70.00 | $102.10 |
| 36 | Conc rem (50102400) | CY | 15.30 | $3,000.00 | $2,679.23 | $2,800.00 | $1,848.20 |
| 37 | Conc struct (50300225) | CY | 0.90 | $3,250.00 | $5,938.01 | $12,000 | $17,085 |
| 38 | Conc sup-STR (50300255) | CY | 16.40 | $3,250.00 | $2,411.14 | $2,600.00 | $3,357.65 |
| 39 | Protective coat (50300300) | SY | 589 | $1.00 | $6.19 | $2.25 | $4.80 |
| 40 | Reinf bars, epoxy CTD (50800205) | LB | 980 | $5.00 | $7.52 | $6.00 | $6.50 |
| 41 | Bar splicers (50800515) | EACH | 12 | $100.00 | $97.83 | $85.00 | $58.15 |
| 42 | Pref JT strip seal (52000110) | LF | 171 | $250.00 | $295.34 | $290.00 | $413.10 |
| 43 | Elast bearing assy T1 (52100010) | EACH | 4 | $3,200.00 | $5,473.31 | $2,500.00 | $2,019.45 |
| 44 | Anchor bolts 1 (52100520) | EACH | 8 | $180.00 | $261.30 | $300.00 | $346.60 |
| 45 | Concrete sealer (58700300) | SF | 2,276 | $3.30 | $2.26 | $3.00 | $1.85 |
| 46 | Man adjust (60255500) | EACH | 1 | $1,000.00 | $1,047.50 | $2,300.00 | $950.00 |
| 47 | Inlets adjust (60260100) | EACH | 8 | $900.00 | $507.94 | $1,300.00 | $950.00 |
| 48 | Comb CC&G TY B-6.24 (60605000) | LF | 388 | $45.00 | $81.23 | $90.00 | $115.35 |
| 49 | Traf bar term T6 (63100085) | EACH | 3 | $5,802.50 | $5,966.29 | $5,000.00 | $5,275.00 |
| 50 | Guardrail remov (63200310) | LF | 113 | $9.90 | $10.18 | $24.00 | $9.00 |
| 51 | Non SPL waste disposl (66900200) | CY | 20 | $150.00 | $159.41 | $100.00 | $161.80 |
| 52 | Soil disposal analy (66900530) | EACH | 1 | $1,815.00 | $1,640.02 | $1,450.00 | $1,450.00 |
| 53 | Reg sub P-const plan (66901001) | LS | 1 | $2,475.00 | $3,506.25 | $3,100.00 | $3,100.00 |
| 54 | Reg sub F con report (66901003) | LS | 1 | $2,475.00 | $1,357.26 | $1,200.00 | $1,200.00 |
| 55 | Reg sub mon (66901006) | CAL DAY | 35 | $0.01 | $769.11 | $250.00 | $680.00 |
| 56 | Mobilization (67100100) | LS | 1 | $42,041 | $36,379 | $50,000 | $57,300 |
| 57 | Pavt MK blkout tape 4 (70107004) | LF | 4,617 | $3.00 | $2.26 | $1.00 | $1.90 |
| 58 | Pavt MK blkout tape 6 (70107006) | LF | 221 | $3.00 | $3.39 | $2.00 | $2.00 |
| 59 | Pavt MK blkout tpe 12 (70107012) | LF | 73 | $6.00 | $6.96 | $4.00 | $4.00 |
| 60 | Pavt MK blkout tpe 24 (70107024) | LF | 39 | $12.00 | $13.86 | $15.00 | $15.00 |
| 61 | Changeable message SN (70107025) | CAL DAY | 28 | $100.00 | $39.59 | $50.00 | $40.00 |
| 62 | SHRT TRM pavt MK rem (70300150) | SF | 20 | $5.00 | $7.35 | $10.00 | $10.00 |
| 63 | Temp PVT MK L6 T4 tape (70307130) | LF | 40 | $5.00 | $6.79 | $15.00 | $15.00 |
| 64 | THPL PVT MK line 4 (78000200) | LF | 920 | $5.12 | $5.37 | $1.00 | $1.00 |
| 65 | THPL PVT MK line 6 (78000400) | LF | 10 | $5.50 | $8.09 | $1.50 | $1.35 |
| 66 | THPL PVT MK line 12 (78000600) | LF | 30 | $7.04 | $16.12 | $3.00 | $2.90 |
| 67 | THPL PVT MK line 24 (78000650) | LF | 15 | $12.10 | $32.23 | $6.00 | $5.80 |
| 68 | Mod ureth PM line 4 (78009004) | LF | 650 | $7.76 | $9.05 | $1.00 | $1.00 |
| 69 | Mod ureth PM line 12 (78009012) | LF | 10 | $28.60 | $28.28 | $13.00 | $12.25 |
| 70 | Raised refl pavt MKR (78100100) | EACH | 24 | $231.00 | $248.83 | $50.00 | $49.10 |
| 71 | Raised ref PVT MK rem (78300200) | EACH | 24 | $20.00 | $62.21 | $25.00 | $25.00 |
| 72 | PVT MKG rem WTR blast (78300202) | SF | 62 | $41.80 | $0.11 | $15.00 | $15.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.