IDOT contract 62Y28 bid tabulation
Section 2025-1076-I. Let by Illinois DOT on April 24, 2026, Cook, District 01. 2 bids received; low bid $9,649,148 by Meade Inc..
- Owner
- Illinois DOT
- Letting
- 24 APR 2026
- Pay items
- 47
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Meade Inc. | $9,649,148 | Low |
| 2 | John Burns Construction Company | $13,924,157 | +44% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Meade Inc. | 2. John Burns Construction Company |
|---|---|---|---|---|---|
| 1 | Network switch (X0323619) | EACH | 70 | $12,423 | $10,500 |
| 2 | RMV EX net SW sal (X0323620) | EACH | 15 | $650.93 | $1,000.00 |
| 3 | Network rack (X0323621) | EACH | 1 | $5,728.71 | $30,000 |
| 4 | CNTRLR, linux, atc (X0325489) | EACH | 70 | $13,068 | $15,200 |
| 5 | Cellular modem (X0325922) | EACH | 70 | $6,633.12 | $7,700.00 |
| 6 | ATMS sys integration (X0327117) | LS | 1 | $333,900 | $500,000 |
| 7 | Conduit riser gal STL (X0327752) | EACH | 17 | $2,859.96 | $3,000.00 |
| 8 | Term fiber in cabinet (X1400217) | EACH | 288 | $69.25 | $100.00 |
| 9 | Detecn intgrtn device (X1400413) | EACH | 70 | $4,960.28 | $4,700.00 |
| 10 | Detection controller (X1400414) | EACH | 70 | $5,960.28 | $5,900.00 |
| 11 | Clearing & grubbing (X2010512) | SY | 1,500 | $6.30 | $5.00 |
| 12 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 24 | $8,400.00 | $5,000.00 |
| 13 | Main EX traffic surv (X7010007) | LS | 1 | $127,416 | $2,000,000 |
| 14 | Traf cont & prot SPL (X7010216) | LS | 1 | $26,250 | $100,000 |
| 15 | TR C-prot expressways (X7011015) | LS | 1 | $340,305 | $522,000 |
| 16 | Temp info signing (X7200061) | SF | 200 | $31.50 | $16.00 |
| 17 | Aerial cable removal (X8180064) | LF | 8,562 | $3.25 | $5.00 |
| 18 | Wood pole 90FT CL3 (X8302093) | EACH | 143 | $13,220 | $14,000 |
| 19 | Wood pole 60 CL 4 (X8302160) | EACH | 163 | $7,015.74 | $13,000 |
| 20 | Focc 96F SNGL mode (X8710023) | LF | 4,723 | $8.38 | $4.00 |
| 21 | Foc aer 96F SNGL mode (X8710059) | LF | 71,950 | $13.26 | $11.00 |
| 22 | FO interct center 48P (X8710094) | EACH | 6 | $2,859.31 | $2,200.00 |
| 23 | Foc splice - mainline (X8710306) | EACH | 5 | $6,457.42 | $6,000.00 |
| 24 | Fib opt utilit marker (X8710318) | EACH | 15 | $691.55 | $2,600.00 |
| 25 | RR prot liability ins (Z0048665) | LS | 1 | $6,300.00 | $40,000 |
| 26 | Trainees (Z0076600) | HR | 1,000 | $0.80 | $0.80 |
| 27 | Trainees TPG (Z0076604) | HR | 1,000 | $15.00 | $15.00 |
| 28 | Tree remov 6-15 (20100110) | UNIT | 150 | $50.40 | $100.00 |
| 29 | Tree remov over 15 (20100210) | UNIT | 150 | $75.60 | $150.00 |
| 30 | Rock excavation (20200200) | CY | 30 | $630.00 | $1.00 |
| 31 | Topsoil F & P 4 (21101615) | SY | 5,000 | $14.33 | $10.00 |
| 32 | Seeding CL 2A (25000210) | ACRE | 1 | $7,350.00 | $10,000 |
| 33 | Nitrogen fert nutr (25000400) | LB | 90 | $4.20 | $5.00 |
| 34 | Potassium fert nutr (25000600) | LB | 90 | $4.20 | $5.00 |
| 35 | Erosion contr blanket (25100630) | SY | 500 | $2.10 | $5.00 |
| 36 | Non SPL waste disposl (66900200) | CY | 535 | $52.50 | $55.00 |
| 37 | Soil disposal analy (66900530) | EACH | 6 | $1,732.50 | $1,520.00 |
| 38 | Reg sub P-const plan (66901001) | LS | 1 | $4,147.50 | $2,700.00 |
| 39 | Reg sub F con report (66901003) | LS | 1 | $630.00 | $2,100.00 |
| 40 | Reg sub mon (66901006) | CAL DAY | 60 | $735.00 | $998.00 |
| 41 | Mobilization (67100100) | LS | 1 | $578,936 | $835,000 |
| 42 | Undrgrd C galvs 2 (81028200) | LF | 1,430 | $78.34 | $250.00 |
| 43 | Con at ST 2 galvs (81100600) | LF | 4,455 | $70.82 | $150.00 |
| 44 | Jun BX SS as 24X24X8 (81300945) | EACH | 20 | $4,197.46 | $6,000.00 |
| 45 | Reloc EX wood poles (84400405) | EACH | 10 | $5,207.42 | $10,000 |
| 46 | Drill EX handhole (87900200) | EACH | 3 | $2,603.71 | $3,200.00 |
| 47 | Rem elcbl FR con (89502300) | LF | 5,000 | $2.60 | $12.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 24, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.