IDOT contract 64M10 bid tabulation
Section 112CR. Let by Illinois DOT on January 17, 2025, Lee, District 02. 4 bids received; low bid $746,263 by Martin & Company Excavating.
- Owner
- Illinois DOT
- Letting
- 17 JAN 2025
- Pay items
- 67
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Martin & Company Excavating | $746,263 | Low |
| 2 | Phoenix Corporation of the Quad Cities | $795,223 | +7.0% |
| 3 | McCarthy Improvement Company | $853,500 | +14% |
| 4 | Civil Constructors, Inc. d/b/a/ Helm Civil | $892,570 | +20% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Martin & Company Excavating | 2. Phoenix Corporation of the Quad Cities | 3. McCarthy Improvement Company | 4. Civil Constructors, Inc. d/b/a/ Helm Civil |
|---|---|---|---|---|---|---|---|
| 1 | PCC surface rem (CM) (X4406801) | SY | 126 | $44.00 | $21.00 | $18.00 | $18.00 |
| 2 | Memb WTRPRF sys B STR (X5810103) | SY | 96 | $36.00 | $33.50 | $50.00 | $44.84 |
| 3 | Traf cont & prot SPL (X7010216) | LS | 1 | $23,000 | $35,000 | $66,000 | $19,250 |
| 4 | Construction layout (Z0013798) | LS | 1 | $5,700.00 | $7,900.00 | $5,150.00 | $3,800.00 |
| 5 | Rock fill - foundatn (Z0054517) | TON | 280 | $48.00 | $104.00 | $54.00 | $45.00 |
| 6 | Earth excavation (20200100) | CY | 1,848 | $32.00 | $20.00 | $23.50 | $39.00 |
| 7 | Porous gran embank (20700220) | CY | 444 | $38.00 | $46.50 | $83.00 | $58.00 |
| 8 | Topsoil F & P 4 (21101615) | SY | 4,794 | $4.66 | $3.50 | $4.00 | $7.00 |
| 9 | Seeding CL 2A (25000210) | ACRE | 1 | $3,800.00 | $3,315.00 | $3,315.00 | $3,315.00 |
| 10 | Seeding CL 4 (25000310) | ACRE | 0.25 | $1,400.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 11 | Mowing (25000750) | ACRE | 1 | $1,600.00 | $1,200.00 | $1,200.00 | $1,200.00 |
| 12 | Mulch method 3 (25100125) | ACRE | 0.75 | $3,700.00 | $3,315.00 | $3,315.00 | $3,315.00 |
| 13 | Erosion contr blanket (25100630) | SY | 2,145 | $2.00 | $1.50 | $1.50 | $1.50 |
| 14 | Turf reinf mat (25100900) | SY | 34 | $14.00 | $10.00 | $10.00 | $10.00 |
| 15 | Temp eros contr seed (28000250) | LB | 214 | $0.10 | $3.00 | $3.50 | $12.00 |
| 16 | Temp ditch checks (28000305) | LF | 180 | $12.00 | $15.50 | $12.00 | $17.00 |
| 17 | Inlet & pipe protect (28000500) | EACH | 1 | $175.00 | $255.00 | $309.00 | $450.00 |
| 18 | Stone riprap CL A4 (28100107) | SY | 134 | $55.00 | $84.50 | $90.00 | $75.00 |
| 19 | Stone riprap CL A5 (28100109) | SY | 221 | $60.00 | $102.50 | $114.00 | $110.00 |
| 20 | Filter fabric (28200200) | SY | 355 | $5.00 | $2.00 | $2.50 | $5.00 |
| 21 | Agg subgrade impr 12 (30300112) | SY | 599 | $15.62 | $17.50 | $20.00 | $25.00 |
| 22 | Agg surf cse B (40200900) | CY | 79 | $30.00 | $57.00 | $126.00 | $85.00 |
| 23 | Bit matls PR CT (40600275) | LB | 1,209 | $0.10 | $0.50 | $0.50 | $0.50 |
| 24 | Bit matls tack CT (40600290) | LB | 3,192 | $0.10 | $0.60 | $0.60 | $0.50 |
| 25 | Long joint sealant (40600370) | LF | 750 | $11.00 | $10.50 | $10.50 | $10.50 |
| 26 | Temporary ramp (40600990) | SY | 81 | $5.00 | $22.00 | $22.00 | $22.00 |
| 27 | HMA BC IL-9.5 N50 (40602978) | TON | 218 | $92.00 | $108.00 | $108.00 | $108.00 |
| 28 | HMA SC IL-9.5 C N50 (40604050) | TON | 603 | $92.00 | $118.00 | $118.00 | $118.00 |
| 29 | Welded wire reinf (42000060) | SY | 126 | $18.00 | $24.00 | $7.80 | $21.00 |
| 30 | HMA surf rem 2 (44000157) | SY | 3,456 | $5.00 | $7.20 | $6.20 | $6.20 |
| 31 | HMA surf rem 3 (44000161) | SY | 1,920 | $6.00 | $6.90 | $6.90 | $6.90 |
| 32 | Paved SHLD removal (44004250) | SY | 123 | $13.00 | $14.50 | $18.40 | $33.00 |
| 33 | CL B patch T4 17 (44201053) | SY | 126 | $195.00 | $194.00 | $260.00 | $250.00 |
| 34 | Dowel bars 1 (44201297) | EACH | 40 | $22.00 | $37.00 | $22.50 | $28.00 |
| 35 | Saw cuts (44213200) | LF | 95 | $20.00 | $12.00 | $11.50 | $5.00 |
| 36 | Tie bars 3/4 (44213204) | EACH | 16 | $20.00 | $28.00 | $33.50 | $20.00 |
| 37 | Aggregate SHLDS B 6 (48101500) | SY | 501 | $9.11 | $19.00 | $16.50 | $14.00 |
| 38 | HMA shoulders 5 (48203017) | SY | 456 | $36.68 | $30.00 | $30.00 | $30.00 |
| 39 | Rem exist struct (50100100) | EACH | 1 | $14,900 | $30,000 | $13,000 | $45,000 |
| 40 | Rem/disp uns matl-STR (50200450) | CY | 160 | $44.00 | $29.00 | $33.00 | $45.00 |
| 41 | Name plates (51500100) | EACH | 1 | $1,150.00 | $1,100.00 | $900.00 | $1,300.00 |
| 42 | Box cul end sec C1 (54001001) | EACH | 2 | $73,105 | $67,500 | $56,500 | $66,000 |
| 43 | PCBC 10X7 (54011007) | LF | 48 | $1,710.00 | $1,625.00 | $1,870.00 | $2,200.00 |
| 44 | TRVRS pipe GRT con ES (54260315) | LF | 362 | $102.00 | $109.00 | $91.00 | $84.00 |
| 45 | Geocomposite wall DR (59100100) | SY | 96 | $24.00 | $30.00 | $46.50 | $38.19 |
| 46 | Conc HDWL for P drain (60100060) | EACH | 2 | $450.00 | $300.00 | $1,100.00 | $880.00 |
| 47 | French drains (60100080) | CY | 5 | $165.00 | $175.00 | $280.00 | $430.00 |
| 48 | Pipe drains 6 (60100915) | LF | 20 | $30.00 | $23.00 | $25.00 | $50.00 |
| 49 | Pipe drains 8 (60100925) | LF | 20 | $35.00 | $24.00 | $30.00 | $50.00 |
| 50 | Pipe drains 10 (60100935) | LF | 20 | $40.00 | $26.00 | $37.00 | $50.00 |
| 51 | Pipe drains 12 (60100945) | LF | 20 | $50.00 | $32.00 | $38.00 | $50.00 |
| 52 | Pipe underdr T 2 4 (60108204) | LF | 60 | $32.00 | $36.00 | $23.00 | $67.00 |
| 53 | Explor trench 52 (61100500) | LF | 200 | $24.00 | $9.00 | $18.25 | $30.00 |
| 54 | Storm sew prot A 8 (61101009) | LF | 50 | $75.00 | $33.00 | $70.00 | $80.00 |
| 55 | Storm sew prot A 10 (61101011) | LF | 50 | $90.00 | $39.00 | $75.00 | $80.00 |
| 56 | Storm sew prot A 12 (61101013) | LF | 50 | $100.00 | $46.00 | $77.00 | $80.00 |
| 57 | FLD tile jun vault 3D (61133200) | EACH | 2 | $2,100.00 | $1,850.00 | $4,900.00 | $3,500.00 |
| 58 | Delineators (63500105) | EACH | 6 | $100.00 | $56.00 | $90.00 | $65.00 |
| 59 | Fur erect row markers (66600105) | EACH | 11 | $220.00 | $350.00 | $220.00 | $330.00 |
| 60 | Perm surv MKRS T2 (66700305) | EACH | 1 | $2,800.00 | $2,250.00 | $2,500.00 | $3,500.00 |
| 61 | Engr field office A (67000400) | CAL MO | 3 | $2,500.00 | $2,600.00 | $7,400.00 | $2,700.00 |
| 62 | Mobilization (67100100) | LS | 1 | $36,000 | $41,400 | $50,999 | $53,554 |
| 63 | TR cont surveillance (70103815) | CAL DAY | 10 | $550.00 | $0.01 | $700.00 | $500.00 |
| 64 | Changeable message SN (70107025) | CAL DAY | 28 | $50.00 | $150.00 | $45.00 | $45.00 |
| 65 | Short term pavt mking (70300100) | LF | 232 | $0.50 | $2.50 | $2.00 | $2.00 |
| 66 | SHRT TRM pavt MK rem (70300150) | SF | 77 | $5.00 | $13.75 | $4.00 | $4.00 |
| 67 | Paint PVT MK line 4 (78001110) | LF | 5,198 | $0.85 | $1.65 | $1.04 | $0.75 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 17, 2025. Compiled by Mirage Metrics.