IDOT contract 64U52 bid tabulation
Section ((201-3)R&(4-1,5)R)PP. Let by Illinois DOT on August 1, 2025, Winnebago, District 02. 3 bids received; low bid $3,920,847 by G. M. Sipes Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 01 AUG 2025
- Pay items
- 60
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | G. M. Sipes Construction, Inc. | $3,920,847 | Low |
| 2 | Martin & Company Excavating | $4,476,192 | +14% |
| 3 | Plote Construction, Inc. | $7,000,000 | +79% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. G. M. Sipes Construction, Inc. | 2. Martin & Company Excavating | 3. Plote Construction, Inc. |
|---|---|---|---|---|---|---|
| 1 | Constructn layout SPL (X0320050) | LS | 1 | $10,000 | $29,000 | $6,775.00 |
| 2 | Washout basin (X0326806) | LS | 1 | $1,000.00 | $6,000.00 | $20,000 |
| 3 | Geotechnical reinf (X2100104) | SY | 5,258 | $1.00 | $6.00 | $3.00 |
| 4 | Temp aggregate wedge (X4810110) | TON | 169 | $10.00 | $71.00 | $65.00 |
| 5 | Engr FLD off A SPL (X6700410) | CAL MO | 3 | $2,000.00 | $6,900.00 | $5,500.00 |
| 6 | TC-prot 701406 SPL (X7010600) | LS | 1 | $5,000.00 | $10,100 | $125,000 |
| 7 | Rem & rein sign panel (X7200075) | SF | 50 | $15.00 | $188.00 | $75.00 |
| 8 | Stab constr entrance (Z0013797) | SY | 224 | $20.00 | $51.00 | $30.00 |
| 9 | Dowel bar assembly (Z0017099) | EACH | 256 | $150.00 | $250.00 | $230.00 |
| 10 | Earth excavation (20200100) | CY | 3,495 | $1.00 | $96.30 | $200.00 |
| 11 | Rem & disp uns matl (20201200) | CY | 1,245 | $1.00 | $48.00 | $200.00 |
| 12 | Topsoil exc & plac (21101505) | CY | 1,000 | $20.00 | $56.00 | $45.00 |
| 13 | Seeding CL 2A (25000210) | ACRE | 1 | $2,000.00 | $4,000.00 | $2,000.00 |
| 14 | Seeding CL 4 (25000310) | ACRE | 0.25 | $8,000.00 | $16,000 | $8,000.00 |
| 15 | Seeding CL 4A (25000312) | ACRE | 0.75 | $3,500.00 | $7,000.00 | $3,500.00 |
| 16 | Seeding CL 5 (25000320) | ACRE | 0.75 | $3,500.00 | $7,000.00 | $3,500.00 |
| 17 | Nitrogen fert nutr (25000400) | LB | 180 | $2.00 | $5.00 | $2.00 |
| 18 | Phosphorus fert nutr (25000500) | LB | 180 | $2.00 | $5.00 | $2.00 |
| 19 | Potassium fert nutr (25000600) | LB | 180 | $2.00 | $5.00 | $2.00 |
| 20 | Mulch method 3A (25100127) | ACRE | 2 | $3,000.00 | $6,000.00 | $3,000.00 |
| 21 | Temp eros contr seed (28000250) | LB | 156 | $1.00 | $2.00 | $1.00 |
| 22 | Temp ditch checks (28000305) | LF | 26 | $30.00 | $60.00 | $30.00 |
| 23 | Perimeter eros bar (28000400) | LF | 2,217 | $5.00 | $10.00 | $5.00 |
| 24 | Temp eros contr blank (28001100) | SY | 7,542 | $0.01 | $1.00 | $0.01 |
| 25 | Agg subgrade impr 24 (30300124) | SY | 5,258 | $40.00 | $91.00 | $100.00 |
| 26 | Welded wire reinf (42000060) | SY | 5,138 | $15.00 | $15.00 | $14.00 |
| 27 | Pavement rem (44000100) | SY | 1,719 | $125.00 | $66.00 | $125.00 |
| 28 | Paved SHLD removal (44004250) | SY | 2,077 | $100.00 | $66.00 | $58.00 |
| 29 | CL B patch T4 12 (44201000) | SY | 5,138 | $395.00 | $271.00 | $710.00 |
| 30 | Dowel bars 1 1/2 (44201299) | EACH | 268 | $50.00 | $35.00 | $21.00 |
| 31 | Saw cuts (44213200) | LF | 2,461 | $10.00 | $12.00 | $40.00 |
| 32 | Tie bars 3/4 (44213204) | EACH | 1,285 | $25.00 | $30.00 | $23.00 |
| 33 | Aggregate SHLDS A 6 (48100500) | SY | 482 | $100.00 | $41.00 | $40.00 |
| 34 | Conc HDWL for P drain (60100060) | EACH | 1 | $1,000.00 | $650.00 | $2,500.00 |
| 35 | French drains (60100080) | CY | 19 | $500.00 | $240.00 | $300.00 |
| 36 | Geo fab-french drain (60100085) | SY | 170 | $1.00 | $8.00 | $12.00 |
| 37 | Pipe underdrain 6 SP (60108200) | LF | 62 | $10.00 | $111.00 | $200.00 |
| 38 | Pipe underdr T 2 6 (60108206) | LF | 310 | $10.00 | $90.00 | $135.00 |
| 39 | Delineators (63500105) | EACH | 6 | $100.00 | $150.00 | $150.00 |
| 40 | Non SPL waste disposl (66900200) | CY | 4,670 | $0.01 | $167.00 | $90.00 |
| 41 | Soil disposal analy (66900530) | EACH | 1 | $1,350.00 | $1,600.00 | $1,800.00 |
| 42 | Reg sub P-const plan (66901001) | LS | 1 | $3,400.00 | $4,000.00 | $3,350.00 |
| 43 | Reg sub F con report (66901003) | LS | 1 | $1,200.00 | $1,600.00 | $1,500.00 |
| 44 | Reg sub mon (66901006) | CAL DAY | 14 | $2,500.00 | $2,000.00 | $950.00 |
| 45 | Mobilization (67100100) | LS | 1 | $195,000 | $250,000 | $402,048 |
| 46 | Traf cont-prot 701401 (70100800) | LS | 1 | $600,000 | $135,000 | $25,000 |
| 47 | TR cont surveillance (70103815) | CAL DAY | 25 | $0.01 | $125.00 | $100.00 |
| 48 | Changeable message SN (70107025) | CAL DAY | 28 | $150.00 | $65.00 | $35.00 |
| 49 | Night work zone light (70200100) | LS | 1 | $15,000 | $166,000 | $12,500 |
| 50 | SHRT TRM pavt MK rem (70300150) | SF | 451 | $5.00 | $1.20 | $0.60 |
| 51 | Temp PVT MK L4 T4 tape (70307120) | LF | 1,196 | $4.00 | $2.25 | $1.15 |
| 52 | Temp PVT MK L6 T4 tape (70307130) | LF | 105 | $12.50 | $3.00 | $1.75 |
| 53 | Sign panel T2 (72000200) | SF | 32 | $25.00 | $52.00 | $32.00 |
| 54 | Teles STL sin support (72800100) | LF | 86 | $10.00 | $25.00 | $15.00 |
| 55 | Mod ureth PM line 4 (78009004) | LF | 4,256 | $3.30 | $4.00 | $3.30 |
| 56 | Mod ureth PM line 6 (78009006) | LF | 532 | $5.50 | $5.00 | $5.50 |
| 57 | Mod ureth PM line 12 (78009012) | LF | 347 | $11.00 | $10.00 | $11.00 |
| 58 | Raised refl pavt MKR (78100100) | EACH | 146 | $165.00 | $115.00 | $10.00 |
| 59 | Raised ref PVT MK rem (78300200) | EACH | 52 | $10.00 | $25.00 | $25.00 |
| 60 | PVT MKG rem WTR blast (78300202) | SF | 1,462 | $8.00 | $5.00 | $2.65 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of August 1, 2025. Compiled by Mirage Metrics.