IDOT contract 66M57 bid tabulation
Section (128)RS-5. Let by Illinois DOT on March 7, 2025, Dekalb, District 03. 4 bids received; low bid $2,734,986 by Curran Contracting Company.
- Owner
- Illinois DOT
- Letting
- 07 MAR 2025
- Pay items
- 63
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Curran Contracting Company | $2,734,986 | Low |
| 2 | Peter Baker & Son Co. | $2,890,298 | +6.0% |
| 3 | Plote Construction, Inc. | $3,091,121 | +13% |
| 4 | Rock Road Companies, Inc. | $3,297,470 | +21% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Curran Contracting Company | 2. Peter Baker & Son Co. | 3. Plote Construction, Inc. | 4. Rock Road Companies, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Box culvert removal (X1200050) | LF | 53 | $100.00 | $100.00 | $78.50 | $250.00 |
| 2 | Furnished excav SPL (X2040805) | CY | 5 | $0.01 | $887.00 | $75.00 | $101.00 |
| 3 | HMA surf rem var DP (X4401198) | SY | 4,216 | $5.40 | $6.40 | $7.50 | $6.49 |
| 4 | Linear delin panels 4 (X6350204) | EACH | 29 | $55.00 | $58.60 | $58.10 | $65.65 |
| 5 | Linear delin panels 6 (X6350206) | EACH | 4 | $65.00 | $58.03 | $68.00 | $95.95 |
| 6 | Temp info signing (X7200061) | SF | 84 | $25.00 | $25.00 | $25.00 | $12.12 |
| 7 | RR prot liability ins (Z0048665) | LS | 1 | $4,000.00 | $5,000.00 | $6,000.00 | $12,759 |
| 8 | Trainees (Z0076600) | HR | 1,000 | $0.80 | $0.80 | $0.80 | $0.80 |
| 9 | Trainees TPG (Z0076604) | HR | 1,000 | $15.00 | $15.00 | $15.00 | $15.00 |
| 10 | Nitrogen fert nutr (20101400) | LB | 33 | $2.00 | $5.00 | $2.00 | $2.02 |
| 11 | Phosphorus fert nutr (20101500) | LB | 33 | $2.00 | $5.00 | $2.00 | $2.02 |
| 12 | Potassium fert nutr (20101600) | LB | 33 | $2.00 | $5.00 | $2.00 | $2.02 |
| 13 | Earth excavation (20200100) | CY | 300 | $45.00 | $5.90 | $28.00 | $63.00 |
| 14 | Trench backfill (20800150) | CY | 18 | $40.00 | $40.00 | $61.10 | $50.00 |
| 15 | Grading & shap ditch (21400100) | LF | 2,630 | $7.15 | $14.60 | $8.55 | $18.45 |
| 16 | Seeding CL 2A (25000210) | ACRE | 0.40 | $2,700.00 | $8,000.00 | $2,700.00 | $2,727.00 |
| 17 | Erosion contr blanket (25100630) | SY | 1,753 | $2.00 | $2.00 | $2.00 | $2.02 |
| 18 | Stone dump rip CL A4 (28100707) | SY | 6 | $170.00 | $400.00 | $165.00 | $350.00 |
| 19 | Filter fabric (28200200) | SY | 6 | $1.00 | $22.00 | $84.70 | $20.00 |
| 20 | Sub gran mat A (31100100) | TON | 9 | $80.00 | $80.00 | $59.30 | $50.00 |
| 21 | Agg surf course TY B (40200800) | TON | 148 | $50.00 | $46.85 | $45.00 | $51.88 |
| 22 | Bit matls tack CT (40600290) | LB | 86,504 | $1.00 | $0.01 | $0.01 | $0.75 |
| 23 | Long joint sealant (40600370) | LF | 37,709 | $2.45 | $3.19 | $2.32 | $2.50 |
| 24 | Mix CR JTS flangewys (40600400) | TON | 37 | $350.00 | $55.00 | $600.00 | $236.14 |
| 25 | Matl transfer device (40600405) | TON | 21,368 | $2.20 | $1.85 | $3.25 | $2.25 |
| 26 | Temporary ramp (40600990) | SY | 988 | $10.00 | $3.40 | $1.00 | $18.88 |
| 27 | HMA BC IL-19.0 N70 (40603085) | TON | 6,845 | $62.00 | $70.25 | $80.00 | $76.94 |
| 28 | P HMA BC IL-4.75 N50 (40603200) | TON | 3,965 | $82.00 | $93.50 | $115.00 | $117.85 |
| 29 | HMA SC IL-9.5 D N70 (40604062) | TON | 10,558 | $66.00 | $76.15 | $84.00 | $82.87 |
| 30 | Incidental HMA surf (40800050) | TON | 468 | $120.00 | $153.55 | $170.00 | $158.21 |
| 31 | HMA surf rem 1 1/2 (44000155) | SY | 308 | $2.65 | $13.52 | $2.10 | $7.74 |
| 32 | HMA surf rem 2 1/2 (44000159) | SY | 70,534 | $2.25 | $2.30 | $1.85 | $3.06 |
| 33 | HMA surf rem 3 3/4 (44000164) | SY | 54,324 | $2.65 | $3.29 | $3.00 | $3.89 |
| 34 | CL D patch T3 12 (44201794) | SY | 32 | $340.00 | $398.00 | $475.00 | $379.55 |
| 35 | Agg wedge SHLD type B (48102100) | TON | 2,933 | $15.00 | $37.30 | $39.00 | $31.96 |
| 36 | P cul CL A 1 eqrs 18 (542A5473) | LF | 72 | $200.00 | $200.00 | $300.00 | $300.00 |
| 37 | PRCF end S EL eqrs 18 (54214713) | EACH | 4 | $5,000.00 | $5,000.00 | $3,600.00 | $3,000.00 |
| 38 | Contr low-streng matl (59300100) | CY | 1.20 | $1,000.00 | $2,694.00 | $952.60 | $2,000.00 |
| 39 | Box cul to BE cleaned (60905305) | LF | 156 | $59.00 | $55.00 | $55.00 | $195.00 |
| 40 | Delineators (63500105) | EACH | 34 | $100.00 | $68.00 | $58.60 | $65.65 |
| 41 | Shoulder rum strip 8 (64200108) | LF | 32,594 | $0.45 | $0.50 | $0.50 | $0.73 |
| 42 | Non SPL waste disposl (66900200) | CY | 126 | $60.00 | $79.00 | $61.00 | $139.70 |
| 43 | Soil disposal analy (66900530) | EACH | 3 | $1,500.00 | $1,125.00 | $1,125.00 | $1,225.00 |
| 44 | Reg sub P-const plan (66901001) | LS | 1 | $2,900.00 | $4,100.00 | $4,100.00 | $3,500.00 |
| 45 | Reg sub F con report (66901003) | LS | 1 | $900.00 | $500.00 | $500.00 | $900.00 |
| 46 | Reg sub mon (66901006) | CAL DAY | 3 | $700.00 | $700.00 | $700.00 | $890.00 |
| 47 | Engr field office A (67000400) | CAL MO | 5 | $2,500.00 | $3,500.00 | $3,500.00 | $2,184.09 |
| 48 | Mobilization (67100100) | LS | 1 | $236,000 | $145,817 | $133,000 | $92,267 |
| 49 | Traf cont-prot 701201 (70100450) | LS | 1 | $100.00 | $11,700 | $20,400 | $1.01 |
| 50 | Traf cont-prot 701306 (70100460) | LS | 1 | $10,700 | $100.00 | $100.00 | $12,928 |
| 51 | Short term pavt mking (70300100) | LF | 11,143 | $0.50 | $0.46 | $1.25 | $0.86 |
| 52 | SHRT TRM pavt MK rem (70300150) | SF | 1,240 | $2.50 | $5.40 | $3.70 | $2.52 |
| 53 | Pref PL PM TD STD LTR/sym (78004600) | SF | 122 | $50.00 | $20.00 | $20.00 | $50.50 |
| 54 | Pref PL PM TD STD L 8 (78004640) | LF | 194 | $10.00 | $10.00 | $10.00 | $10.10 |
| 55 | Pref PL PM TD STD L24 (78004720) | LF | 146 | $50.00 | $20.00 | $20.00 | $50.50 |
| 56 | Epoxy PVT MK line 12 (78005150) | LF | 148 | $15.00 | $18.00 | $18.00 | $15.15 |
| 57 | Mod ureth PM line 4 (78009004) | LF | 202,473 | $0.50 | $0.49 | $0.49 | $0.50 |
| 58 | Mod ureth PM line 6 (78009006) | LF | 19,186 | $1.00 | $0.55 | $0.55 | $1.01 |
| 59 | GRV RCSD PM LTR & sym (78011000) | SF | 122 | $45.00 | $5.00 | $5.00 | $45.45 |
| 60 | GRV RCSD PVT MRKG 8 (78011040) | LF | 194 | $7.50 | $2.00 | $2.00 | $7.57 |
| 61 | GRV RCSD PVT MRKG 25 (78011125) | LF | 146 | $45.00 | $5.00 | $5.00 | $45.45 |
| 62 | Raised refl pavt MKR (78100100) | EACH | 470 | $42.50 | $34.00 | $34.00 | $42.92 |
| 63 | Raised ref PVT MK rem (78300200) | EACH | 470 | $13.50 | $1.00 | $0.50 | $13.28 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of March 7, 2025. Compiled by Mirage Metrics.