IDOT contract 66M84 bid tabulation
Section (22X)CR-2546. Let by Illinois DOT on June 12, 2026, Lasalle, District 03. 4 bids received; low bid $443,941 by D. Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 12 JUN 2026
- Pay items
- 81
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D. Construction, Inc. | $443,941 | Low |
| 2 | Gillan Construction LLC | $531,831 | +20% |
| 3 | Phoenix Corporation of the Quad Cities | $567,528 | +28% |
| 4 | Alliance Contractors, Inc. | $640,129 | +44% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D. Construction, Inc. | 2. Gillan Construction LLC | 3. Phoenix Corporation of the Quad Cities | 4. Alliance Contractors, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Linear delin panels 4 (X6350204) | EACH | 2 | $61.60 | $55.00 | $50.00 | $250.00 |
| 2 | Temp info signing (X7200061) | SF | 64 | $30.00 | $27.50 | $25.00 | $20.00 |
| 3 | Construction layout (Z0013798) | LS | 1 | $10,000 | $6,000.00 | $12,000 | $15,000 |
| 4 | Temp pavement (Z0062456) | SY | 82 | $150.00 | $125.00 | $165.00 | $168.00 |
| 5 | Earth excavation (20200100) | CY | 195 | $40.00 | $39.00 | $85.00 | $20.00 |
| 6 | Rem & disp uns matl (20201200) | CY | 75 | $40.00 | $50.00 | $55.00 | $30.00 |
| 7 | Trench backfill (20800150) | CY | 56 | $60.00 | $80.00 | $60.00 | $75.00 |
| 8 | Topsoil F & P 4 (21101615) | SY | 437 | $25.00 | $12.00 | $11.00 | $17.80 |
| 9 | Seeding CL 2A (25000210) | ACRE | 0.25 | $4,400.00 | $8,800.00 | $15,000 | $18,500 |
| 10 | Nitrogen fert nutr (25000400) | LB | 8.60 | $3.30 | $11.00 | $20.00 | $5.00 |
| 11 | Phosphorus fert nutr (25000500) | LB | 8.60 | $3.30 | $11.00 | $20.00 | $5.00 |
| 12 | Potassium fert nutr (25000600) | LB | 8.60 | $3.30 | $11.00 | $20.00 | $5.00 |
| 13 | Erosion contr blanket (25100630) | SY | 461 | $4.40 | $4.40 | $8.00 | $3.85 |
| 14 | Temp ditch checks (28000305) | LF | 66 | $11.00 | $15.00 | $23.00 | $14.80 |
| 15 | Perimeter eros bar (28000400) | LF | 141 | $5.50 | $5.50 | $10.00 | $12.85 |
| 16 | Stone riprap CL A4 (28100107) | SY | 43 | $90.00 | $87.00 | $112.00 | $175.00 |
| 17 | Filter fabric (28200200) | SY | 96 | $10.00 | $4.50 | $4.00 | $1.00 |
| 18 | Aggregate ditch (28300400) | TON | 13 | $60.00 | $75.00 | $110.00 | $100.00 |
| 19 | Sub gran mat B 4 (31101200) | SY | 58 | $20.00 | $30.00 | $25.00 | $8.00 |
| 20 | Bit matls tack CT (40600290) | LB | 287 | $0.01 | $10.00 | $2.00 | $0.01 |
| 21 | Long joint sealant (40600370) | LF | 239 | $47.49 | $45.00 | $2.20 | $2.30 |
| 22 | HMA BC IL-19.0 N50 (40603080) | TON | 82 | $125.00 | $75.00 | $250.00 | $342.00 |
| 23 | HMA SC IL-9.5 D N50 (40604060) | TON | 63 | $125.00 | $629.00 | $350.00 | $352.00 |
| 24 | HMA pavt FD 10 (40701881) | SY | 54 | $40.00 | $370.00 | $300.00 | $196.00 |
| 25 | Pavement rem (44000100) | SY | 54 | $140.00 | $30.00 | $32.00 | $30.00 |
| 26 | HMA surf rem 1 3/4 (44000156) | SY | 730 | $8.00 | $17.50 | $21.00 | $40.50 |
| 27 | Gutter rem (44000400) | LF | 10 | $50.00 | $77.00 | $40.00 | $30.00 |
| 28 | Aggregate SHLDS A 6 (48100500) | SY | 5 | $200.00 | $100.00 | $69.00 | $20.00 |
| 29 | HMA shoulders 8 (48203029) | SY | 270 | $56.00 | $155.00 | $135.00 | $155.00 |
| 30 | Rem exist struct (50100100) | EACH | 1 | $10,000 | $7,000.00 | $13,500 | $28,850 |
| 31 | Structure excavation (50200100) | CY | 100 | $50.00 | $55.00 | $41.00 | $30.00 |
| 32 | Reinforcement bars (50800105) | LB | 1,790 | $3.00 | $2.25 | $7.00 | $2.50 |
| 33 | Reinf bars, epoxy CTD (50800205) | LB | 200 | $5.00 | $2.50 | $8.00 | $3.00 |
| 34 | Temp soil reten systm (52200020) | SF | 205 | $45.00 | $195.00 | $170.00 | $176.00 |
| 35 | Seg conc block wall (52200800) | SF | 30 | $150.00 | $250.00 | $100.00 | $190.00 |
| 36 | Conc STR retain wall (52200900) | CY | 23 | $1,600.00 | $1,400.00 | $2,000.00 | $3,075.00 |
| 37 | P cul CL A 1 eqrs 42 (542A5497) | LF | 80 | $202.00 | $445.00 | $320.00 | $206.00 |
| 38 | TRVRS pipe GRT con ES (54260315) | LF | 67 | $160.00 | $105.00 | $190.00 | $156.00 |
| 39 | Conc ES 542011 42 1:4 (54263442) | EACH | 2 | $13,290 | $10,750 | $11,600 | $37,000 |
| 40 | Storm sewer rem 12 (55100500) | LF | 8 | $20.00 | $40.00 | $46.00 | $10.00 |
| 41 | Granular backfill STR (58600101) | CY | 15 | $100.00 | $80.00 | $98.00 | $100.00 |
| 42 | Geocomposite wall DR (59100100) | SY | 21 | $50.00 | $30.00 | $35.00 | $25.00 |
| 43 | Conc HDWL for P drain (60100060) | EACH | 1 | $1,000.00 | $325.00 | $1,000.00 | $1,450.00 |
| 44 | Pipe drains 15 (60100955) | LF | 3 | $200.00 | $300.00 | $240.00 | $500.00 |
| 45 | Man adjust (60255500) | EACH | 1 | $1,000.00 | $800.00 | $1,250.00 | $500.00 |
| 46 | Concrete gutter TY A (60602500) | LF | 18 | $100.00 | $130.00 | $81.00 | $370.00 |
| 47 | Paved ditch TA-30 (60616110) | LF | 9 | $200.00 | $130.00 | $107.00 | $395.00 |
| 48 | SPBGR TY A 6FT posts (63000001) | LF | 87.50 | $52.94 | $44.00 | $40.00 | $38.00 |
| 49 | LSG OV cul 18'9" span (63000360) | LF | 43.75 | $51.17 | $44.00 | $40.00 | $46.00 |
| 50 | TR bar TRM T1 SPL tan (63100167) | EACH | 2 | $4,193.20 | $7,150.00 | $4,500.00 | $4,630.00 |
| 51 | Guardrail remov (63200310) | LF | 389 | $9.06 | $10.00 | $8.75 | $9.00 |
| 52 | Perm surv MKRS T1 (66700205) | EACH | 1 | $1,000.00 | $500.00 | $750.00 | $1,000.00 |
| 53 | Non SPL waste disposl (66900200) | CY | 123 | $85.00 | $140.00 | $160.00 | $105.00 |
| 54 | Soil disposal analy (66900530) | EACH | 1 | $1,750.00 | $2,035.00 | $1,500.00 | $900.00 |
| 55 | Reg sub P-const plan (66901001) | LS | 1 | $2,250.00 | $2,475.00 | $3,700.00 | $4,200.00 |
| 56 | Reg sub F con report (66901003) | LS | 1 | $2,250.00 | $2,530.00 | $1,000.00 | $500.00 |
| 57 | Reg sub mon (66901006) | CAL DAY | 4 | $1,000.00 | $1,897.00 | $1,300.00 | $1,750.00 |
| 58 | Engr field office A (67000400) | CAL MO | 2 | $5,000.00 | $3,500.00 | $2,500.00 | $500.00 |
| 59 | Mobilization (67100100) | LS | 1 | $25,080 | $27,500 | $62,000 | $40,600 |
| 60 | Traf cont-prot 701321 (70100405) | EACH | 1 | $17,500 | $14,825 | $13,478 | $2,150.00 |
| 61 | TR cont & prot 701501 (70102620) | LS | 1 | $0.01 | $1,100.00 | $1,000.00 | $1,250.00 |
| 62 | TR cont surveillance (70103815) | CAL DAY | 5 | $500.00 | $500.00 | $500.00 | $1,500.00 |
| 63 | Temp BR traf signals (70106500) | EACH | 1 | $45,000 | $19,800 | $18,000 | $23,000 |
| 64 | Short term pavt mking (70300100) | LF | 159 | $0.01 | $1.10 | $1.00 | $5.00 |
| 65 | SHRT TRM pavt MK rem (70300150) | SF | 661 | $0.01 | $3.30 | $3.00 | $0.75 |
| 66 | Temp PVT MK L4 T4 tape (70307120) | LF | 18 | $5.00 | $6.60 | $6.00 | $10.00 |
| 67 | Temp PVT MK L24 T4 tape (70307210) | LF | 14 | $10.00 | $26.40 | $24.00 | $12.00 |
| 68 | Temp conc barrier (70400100) | LF | 200 | $40.00 | $48.00 | $43.50 | $61.35 |
| 69 | Pin temp conc barrier (70400125) | EACH | 30 | $20.00 | $40.00 | $50.00 | $118.00 |
| 70 | Rel temp conc barrier (70400200) | LF | 175 | $20.00 | $15.00 | $13.00 | $29.70 |
| 71 | Imp attn temp NRN TL3 (70600251) | EACH | 2 | $6,500.00 | $3,850.00 | $3,500.00 | $4,200.00 |
| 72 | Imp attn rel NRN TL3 (70600352) | EACH | 2 | $2,000.00 | $825.00 | $750.00 | $1,300.00 |
| 73 | Rem & rel sign panel asmbly TB (72400210) | EACH | 1 | $357.50 | $385.00 | $350.00 | $1,000.00 |
| 74 | Terminal marker - DA (72501000) | EACH | 2 | $33.00 | $55.00 | $50.00 | $50.00 |
| 75 | Metal post TY A (72900100) | LF | 15 | $14.30 | $27.50 | $25.00 | $20.00 |
| 76 | Mod ureth PM line 4 (78009004) | LF | 1,898 | $3.85 | $4.40 | $4.00 | $2.96 |
| 77 | Mod ureth PM line 6 (78009006) | LF | 316 | $5.50 | $13.20 | $12.00 | $5.00 |
| 78 | Raised refl pavt MKR (78100100) | EACH | 8 | $495.00 | $330.00 | $300.00 | $550.00 |
| 79 | Grdrail ref type A (78200005) | EACH | 4 | $13.20 | $27.50 | $25.00 | $25.00 |
| 80 | Raised ref PVT MK rem (78300200) | EACH | 8 | $20.00 | $25.00 | $65.00 | $50.00 |
| 81 | PVT MKG rem WTR blast (78300202) | SF | 304 | $11.00 | $9.90 | $10.00 | $15.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 12, 2026. Compiled by Mirage Metrics.