IDOT contract 68474 bid tabulation
Section 72[(7,7-1)RS-3;1RS-5]. Let by Illinois DOT on February 27, 2026, Peoria, District 04. 1 bid received; low bid $25,863,073 by R. A. Cullinan and Son, a div of UCM, Inc..
- Owner
- Illinois DOT
- Letting
- 27 FEB 2026
- Pay items
- 130
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | R. A. Cullinan and Son, a div of UCM, Inc. | $25,863,073 | Low |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. R. A. Cullinan and Son, a div of UCM, Inc. |
|---|---|---|---|---|
| 1 | Constr sta layout (XZ013798) | LS | 1 | $30,807 |
| 2 | Slotted drain removal (X0325734) | LF | 212 | $31.90 |
| 3 | MC-SF agg FR CL JF (X0600001) | TON | 126 | $3,025.00 |
| 4 | MC-SF EM asp FR CL JF (X0600002) | LB | 26,490 | $0.50 |
| 5 | Grad & shap ditch SPL (X2020114) | LF | 200 | $25.58 |
| 6 | Recoverable delineatr (X2600002) | EACH | 518 | $132.00 |
| 7 | HMA surf rem SPL (X4400196) | SY | 9,953 | $35.98 |
| 8 | Pavement patching SPL (X4420201) | SY | 925 | $742.50 |
| 9 | CL A patch T1 10 SPL (X4420551) | SY | 38 | $275.00 |
| 10 | CL A patch T2 10 SPL (X4420553) | SY | 456 | $275.00 |
| 11 | CL A patch T4 10 SPL (X4420559) | SY | 1,891 | $247.50 |
| 12 | STR refl CR CTRL TRTMT (X4430200) | LF | 34,064 | $3.05 |
| 13 | Dewatering (X5021507) | LS | 1 | $57,200 |
| 14 | Conc struct SPL (X5030225) | CY | 74.30 | $3,430.72 |
| 15 | Abandon & fill EX SS (X5509900) | LF | 530 | $192.50 |
| 16 | Conc gutter TA SPL (X6062700) | LF | 1,317 | $88.28 |
| 17 | Delineator removal (X6350120) | EACH | 141 | $47.64 |
| 18 | Linear delin panels 4 (X6350204) | EACH | 161 | $95.70 |
| 19 | Traf cont & prot SPL (X7010216) | LS | 1 | $587,479 |
| 20 | Rem X traf surv equip (X8950425) | LS | 1 | $77,000 |
| 21 | GDRL agg eros cont (Z0001002) | TON | 2,047.80 | $104.50 |
| 22 | Drill-grout #6 T-bar (Z0018911) | EACH | 3,379 | $1.10 |
| 23 | Expansion joint SPL (Z0021400) | LF | 520 | $33.00 |
| 24 | Slot DR 15"W/1.75" SL (Z0065767) | LF | 212 | $495.00 |
| 25 | Trainees (Z0076600) | HR | 10,000 | $0.80 |
| 26 | Trainees TPG (Z0076604) | HR | 10,000 | $15.00 |
| 27 | Porous gran embank (20700220) | CY | 10 | $209.00 |
| 28 | Geotech fab F/GR stab (21001000) | SY | 280 | $3.30 |
| 29 | Topsoil F & P 4 (21101615) | SY | 745 | $12.38 |
| 30 | Seeding CL 2A (25000210) | ACRE | 0.25 | $11,000 |
| 31 | Nitrogen fert nutr (25000400) | LB | 22.50 | $6.33 |
| 32 | Phosphorus fert nutr (25000500) | LB | 22.50 | $6.33 |
| 33 | Potassium fert nutr (25000600) | LB | 22.50 | $6.33 |
| 34 | Mowing (25000750) | ACRE | 83 | $104.50 |
| 35 | Mulch method 2 (25100115) | ACRE | 0.25 | $8,800.00 |
| 36 | Erosion contr blanket (25100630) | SY | 745 | $3.58 |
| 37 | Temp eros contr seed (28000250) | LB | 25 | $38.87 |
| 38 | Temp ditch checks (28000305) | LF | 28 | $73.49 |
| 39 | Perimeter eros bar (28000400) | LF | 1,577 | $6.80 |
| 40 | Inlet & pipe protect (28000500) | EACH | 8 | $356.13 |
| 41 | Stone riprap CL B3 (28100225) | TON | 65 | $115.50 |
| 42 | Sub gran mat A (31100100) | TON | 145 | $74.80 |
| 43 | Agg base cse A (35100100) | TON | 255 | $78.10 |
| 44 | HMA BC wid 9 (35600712) | SY | 444 | $166.78 |
| 45 | Preparation of base (35800100) | SY | 255 | $18.43 |
| 46 | P bit matls tack CT (40600295) | LB | 419,472 | $1.91 |
| 47 | Matl transfer device (40600405) | TON | 70,710 | $4.71 |
| 48 | HMA surf rem butt JT (40600982) | SY | 14,199 | $7.54 |
| 49 | PCC surf rem butt JT (40600985) | SY | 4,447 | $14.45 |
| 50 | Temporary ramp (40600990) | SY | 1,361 | $19.18 |
| 51 | P HMA BC IL-4.75 N50 (40603200) | TON | 263 | $201.55 |
| 52 | P HMA BC IL-9.5 N70 (40603208) | TON | 15,115 | $160.92 |
| 53 | P HMA BC SMA 12.5 N80 (40605015) | TON | 526 | $224.71 |
| 54 | P SC SMA 12.5 E N80 (40605034) | TON | 18,064 | $193.35 |
| 55 | Incidental HMA surf (40800050) | TON | 1,934 | $344.97 |
| 56 | HMA surf rem 1 (44000153) | SY | 83,176 | $5.21 |
| 57 | HMA surf rem 3 (44000161) | SY | 2,800 | $11.68 |
| 58 | HMA surf rem 3 3/4 (44000164) | SY | 1,910 | $11.32 |
| 59 | HMA surf rem 4 1/4 (44000166) | SY | 60,077 | $10.87 |
| 60 | Curb rem (44000300) | LF | 1,176 | $23.10 |
| 61 | Gutter rem (44000400) | LF | 1,461 | $23.10 |
| 62 | Welded wire reinf (44200050) | SY | 1,328 | $5.50 |
| 63 | CL A patch T2 10 (44200553) | SY | 301 | $275.00 |
| 64 | CL A patch T3 10 (44200557) | SY | 41 | $275.00 |
| 65 | CL A patch T4 10 (44200559) | SY | 1,200 | $247.50 |
| 66 | CL A patch T4 12 (44200583) | SY | 1,024 | $258.50 |
| 67 | CL B patch T2 10 (44200970) | SY | 397 | $264.00 |
| 68 | CL B patch T3 10 (44200974) | SY | 27 | $264.00 |
| 69 | CL B patch T4 10 (44200976) | SY | 1,301 | $236.50 |
| 70 | Dowel bars 1 1/2 (44201299) | EACH | 1,831 | $38.50 |
| 71 | CL D patch T1 10 (44201761) | SY | 679 | $314.95 |
| 72 | CL D patch T2 10 (44201765) | SY | 679 | $292.95 |
| 73 | CL D patch T3 10 (44201769) | SY | 679 | $270.95 |
| 74 | CL D patch T4 10 (44201771) | SY | 679 | $248.95 |
| 75 | Patch reinforcement (44213000) | SY | 4,951 | $88.00 |
| 76 | Saw cuts (44213200) | LF | 15,291 | $8.75 |
| 77 | Tie bars 3/4 (44213204) | EACH | 1,519 | $1.10 |
| 78 | Aggregate SHLDS B (48101200) | TON | 5,479 | $47.03 |
| 79 | HMA shoulders (48203100) | TON | 34,646 | $144.41 |
| 80 | PCC shoulders 10 (48300500) | SY | 280 | $247.50 |
| 81 | Conc rem (50102400) | CY | 8.30 | $2,750.00 |
| 82 | Conc struct (50300225) | CY | 32.20 | $1,760.00 |
| 83 | Reinf bars, epoxy CTD (50800205) | LB | 2,970 | $6.60 |
| 84 | Inlets adjust (60260100) | EACH | 8 | $1,265.00 |
| 85 | Fill manholes (60500105) | EACH | 3 | $1,650.00 |
| 86 | Class SI conc outlet (60600095) | CY | 12.70 | $1,815.00 |
| 87 | Conc curb TB (60600605) | LF | 285 | $90.20 |
| 88 | Pipe culv cleaned 15 (60920015) | LF | 48 | $62.70 |
| 89 | Pipe culv cleaned 24 (60920024) | LF | 245 | $71.50 |
| 90 | Pipe culv cleaned 36 (60920036) | LF | 400 | $22.00 |
| 91 | Pipe culv cleaned 42 (60920042) | LF | 364 | $24.20 |
| 92 | Pipe culv cleaned 60 (60920060) | LF | 342 | $113.30 |
| 93 | Pipe culv cleaned 72 (60920072) | LF | 414 | $168.30 |
| 94 | Misc concrete (61100605) | CY | 12.60 | $2,475.00 |
| 95 | SPBGR TY A 6FT posts (63000001) | LF | 5,442.50 | $35.31 |
| 96 | SPBGR TY A 9FT posts (63000003) | LF | 1,612.50 | $46.09 |
| 97 | Traf bar term T2 (63100045) | EACH | 7 | $2,530.00 |
| 98 | Traf bar term T6 (63100085) | EACH | 19 | $5,060.00 |
| 99 | TR bar TRM T1 SPL tan (63100167) | EACH | 24 | $4,422.00 |
| 100 | Guardrail remov (63200310) | LF | 9,769 | $9.79 |
| 101 | Shoulder rum strip 16 (64200116) | LF | 78,536 | $0.62 |
| 102 | Imp atten NRD TL3 (64300450) | EACH | 2 | $6,600.00 |
| 103 | Attenuator base (64301090) | SY | 49 | $372.93 |
| 104 | Engr field office A (67000400) | CAL MO | 15 | $5,112.04 |
| 105 | Mobilization (67100100) | LS | 1 | $1,495,900 |
| 106 | Traf cont-prot 701401 (70100205) | EACH | 2 | $255,091 |
| 107 | Traf cont-prot 701411 (70100420) | EACH | 2 | $3,278.00 |
| 108 | Traf cont-prot 701406 (70100701) | EACH | 11 | $880.00 |
| 109 | Traf cont-prot 701451 (70100820) | LS | 1 | $10,835 |
| 110 | Traf cont-prot 701456 (70100825) | LS | 1 | $6,578.00 |
| 111 | TR cont surveillance (70103815) | CAL DAY | 140 | $553.94 |
| 112 | Changeable message SN (70107025) | CAL DAY | 84 | $137.50 |
| 113 | Short term pavt mking (70300100) | LF | 14,078 | $3.18 |
| 114 | SHRT TRM pavt MK rem (70300150) | SF | 4,693 | $10.78 |
| 115 | Temp PVT MK LTR & sym paint (70300211) | SF | 1,261 | $1.10 |
| 116 | Temp PVT MK line 4 - paint (70300221) | LF | 493,588 | $0.28 |
| 117 | Temp PVT MK line 6 - paint (70300241) | LF | 44,298 | $0.28 |
| 118 | Temp PVT MK line 8 - paint (70300251) | LF | 46,820 | $0.39 |
| 119 | Temp PVT MK line 12 - paint (70300261) | LF | 6,316 | $0.61 |
| 120 | Terminal marker - DA (72501000) | EACH | 24 | $55.00 |
| 121 | Pref PL PM TD STD LTR/sym (78004600) | SF | 315 | $55.00 |
| 122 | Pref PL PM TD STD L 6 (78004630) | LF | 134,472 | $5.83 |
| 123 | Pref PL PM TD STD L 8 (78004640) | LF | 11,705 | $8.80 |
| 124 | Pref PL PM TD STD L12 (78004660) | LF | 1,579 | $15.40 |
| 125 | GRV RCSD PM LTR & sym (78011000) | SF | 315 | $8.25 |
| 126 | GRV RCSD PVT MRKG 7 (78011035) | LF | 134,472 | $0.55 |
| 127 | GRV RCSD PVT MRKG 9 (78011045) | LF | 11,705 | $0.66 |
| 128 | GRV RCSD PVT MRKG 13 (78011065) | LF | 1,579 | $4.40 |
| 129 | Raised refl pavt MKR (78100100) | EACH | 1,324 | $49.50 |
| 130 | Raised ref PVT MK rem (78300200) | EACH | 1,324 | $34.71 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of February 27, 2026. Compiled by Mirage Metrics.