IDOT contract 68510 bid tabulation

Section (37-24HVB)BR. Let by Illinois DOT on August 1, 2025, Henry, District 04. 2 bids received; low bid $15,796,785 by IHC Construction Companies, L.L.C..

Owner
Illinois DOT
Letting
01 AUG 2025
Pay items
142
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1IHC Construction Companies, L.L.C.$15,796,785Low
2Civil Constructors, Inc. d/b/a/ Helm Civil$16,500,000+4.0%
IDOT contract 68510: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. IHC Construction Companies, L.L.C.2. Civil Constructors, Inc. d/b/a/ Helm Civil
1Wick drains (X0325833)LF19,656$8.00$4.00
2Explor trench SPL (X2130010)LF325$80.00$11.00
3Eros cont blanket SPL (X2511630)SY15,420$2.00$2.00
4Recoverable delineatr (X2600002)EACH6$360.00$125.00
5Temp pavt removal (X4400110)SY6,687$25.00$18.25
6HMA surf rem SPL (X4400196)SY224$51.85$70.00
7HMA surf rem var DP (X4401198)SY4,435$12.00$12.00
8BR deck grooving long (X5030250)SY2,609$5.00$11.00
9Bar terminators (X5080530)EACH1,052$60.00$33.80
10Storm sew connection (X5510010)EACH1$7,500.00$1,100.00
11Connect EX pipe undr (X6010001)EACH2$1,000.00$450.00
12Rem rep C HDWL P undr (X6015015)EACH2$2,000.00$790.00
13Median inlet box rem (X6050702)EACH2$1,500.00$450.00
14Delineator removal (X6350120)EACH6$28.55$45.00
15Traf cont & prot SPL (X7010216)LS1$550,000$6,000.00
16Temp con bar T S SPL (X7040305)EACH1$2,000.00$1,275.00
17RRPM reflector removl (X7830050)EACH138$10.00$10.00
18RRPM reflector replac (X7830052)EACH138$56.00$20.00
19Temp lighting system (X8410102)LS1$179,345$179,345
20GDRL agg eros cont (Z0001002)TON389$125.00$85.00
21Approach slab rem (Z0004552)SY410$80.00$120.00
22Construction layout (Z0013798)LS1$30,000$180,000
23Diamond grind BR sec (Z0029090)SY2,497$8.50$12.00
24Pipe underdrain remov (Z0040530)LF83$15.00$7.50
25Sand drainage blanket (Z0056100)CY937$135.00$85.00
26Temp pavement (Z0062456)SY7,787$61.30$64.00
27Settlement platforms (Z0065100)EACH2$750.00$2,500.00
28Slot DR 18" W/var SL (Z0065765)LF401$350.00$399.00
29Trainees (Z0076600)HR2,000$0.80$0.80
30Trainees TPG (Z0076604)HR2,000$15.00$15.00
31Undr connect to STR (Z0076870)EACH2$1,750.00$450.00
32Tree remov acres (20100500)ACRE0.31$20,500$25,500
33Earth excavation (20200100)CY1,991$40.00$20.00
34Rem & disp uns matl (20201200)CY124$75.00$31.00
35Furnished excavation (20400800)CY19,337$85.00$92.00
36Topsoil F & P 4 (21101615)SY15,072$15.00$4.00
37Seeding CL 3 (25000300)ACRE3.18$4,540.00$4,540.00
38Nitrogen fert nutr (25000400)LB287$2.00$2.00
39Phosphorus fert nutr (25000500)LB287$2.00$2.00
40Potassium fert nutr (25000600)LB287$2.00$2.00
41Mowing (25000750)ACRE12.74$150.00$150.00
42Mulch method 2 (25100115)ACRE3.18$1,000.00$1,000.00
43Temp eros contr seed (28000250)LB318$5.00$4.00
44Temp ditch checks (28000305)LF940$10.00$27.00
45Perimeter eros bar (28000400)LF2,433$3.35$3.00
46Inlet & pipe protect (28000500)EACH2$250.00$450.00
47Stone riprap CL A4 (28100107)SY259$110.00$84.00
48Filter fabric (28200200)SY404$5.50$3.00
49Agg subgrade impr 12 (30300112)SY9,360$35.00$29.00
50HMA base cse 11 (35501328)SY1,039$89.40$129.00
51Bit matls PR CT (40600275)LB17,801$1.20$0.01
52P bit matls tack CT (40600295)LB23,990$1.40$0.01
53Matl transfer device (40600405)TON5,673$14.90$0.01
54HMA surf rem butt JT (40600982)SY212$38.50$45.00
55P HMA BC IL-9.5 N70 (40603208)TON689$156.50$209.00
56P HMA SC IL-9.5 E N70 (40604172)TON947$157.40$250.00
57Welded wire reinf (42000060)SY453$30.00$21.00
58PVT con PCC BR app SL (42000080)SY453$500.00$310.00
59Pavement rem (44000100)SY527$45.00$85.00
60HMA surf rem 3 (44000161)SY1,624$7.80$32.00
61Paved SHLD removal (44004250)SY1,882$30.00$14.00
62Aggregate SHLDS B (48101200)TON97$60.00$79.00
63Rem exist struct N1 (50100300)EACH1$726,000$510,000
64Rem exist struct N2 (50100400)EACH1$826,000$510,000
65Protective shield (50157300)SY713$1.00$240.00
66Structure excavation (50200100)CY1,036.20$55.00$60.00
67Conc struct (50300225)CY223.10$1,750.00$1,700.00
68Conc sup-STR (50300255)CY682$2,220.00$1,900.00
69Protective coat (50300300)SY2,642$5.00$3.20
70Conc supstr app slab (50301350)CY277.30$850.00$830.00
71F&E PP con beams IL72 (50401350)LF2,299$900.00$1,650.00
72Reinf bars, epoxy CTD (50800205)LB271,500$1.65$2.80
73Slope wall 4 (51100100)SY1,574$200.00$620.00
74Fur M S pile 16X0.375 (51200963)LF2,111$150.00$190.00
75Driving piles (51202305)LF2,111$1.00$0.10
76Test pile met shells (51203200)EACH4$30,000$15,000
77Pile shoes (51204650)EACH36$375.00$620.00
78Name plates (51500100)EACH2$1,000.00$1,500.00
79P cul CL A 2 36 (542A1081)LF288$250.00$170.50
80P cul CL D 1 18 temp (5421D018)LF586$90.00$82.00
81PRC flar end sec 36 (54213681)EACH2$5,500.00$2,875.00
82FL inlt BX med 542546 (54244405)EACH1$8,500.00$5,150.00
83Inlet box 542521 (54245005)EACH1$8,500.00$5,200.00
84SLP MT ES WG 18",1:6 (54260718)EACH4$2,900.00$2,300.00
85Granular backfill STR (58600101)CY782$98.30$110.00
86Geocomposite wall DR (59100100)SY334$15.00$52.00
87Conc HDWL for P drain (60100060)EACH4$250.00$625.00
88Pipe underdrain 4 SP (60108100)LF83$85.00$25.00
89P undr for struct 4 (60146304)LF392$45.00$73.00
90SPBGR TY A 6FT posts (63000001)LF1,725$35.40$33.75
91Traf bar term T2 (63100045)EACH1$2,283.89$1,500.00
92Traf bar term T5 (63100070)EACH2$1,827.12$2,350.00
93Traf bar term T6 (63100085)EACH4$3,654.23$2,600.00
94TR bar TRM T1 SPL tan (63100167)EACH2$3,026.16$3,400.00
95Guardrail remov (63200310)LF2,233$9.14$4.00
96Mod glar SCR sys temp (63800920)LF7,588$9.00$12.00
97Shoulder rum strip 16 (64200116)LF15,387$8.10$1.20
98Fur erect row markers (66600105)EACH4$560.00$1,200.00
99Perm surv MKRS T1 (66700205)EACH2$3,000.00$230.00
100Reg sub P-const plan (66901001)LS1$3,000.00$3,000.00
101Reg sub F con report (66901003)LS1$1,000.00$1,000.00
102Reg sub mon (66901006)CAL DAY10$1,000.00$1,000.00
103Engr field office A (67000400)CAL MO28$3,500.00$4,000.00
104Engr field lab (67000600)CAL MO28$1,000.00$4,500.00
105Mobilization (67100100)LS1$900,000$989,555
106Traf cont-prot 701416 (70100410)EACH2$42,000$42,000
107Traf cont-prot 701411 (70100420)EACH2$1,500.00$1,500.00
108Traf cont-prot 701406 (70100700)LS1$100.00$100.00
109Traf cont-prot 701401 (70100800)LS1$75,600$75,600
110Traf cont-prot 701456 (70100825)LS1$100.00$100.00
111TR cont surveillance (70103815)CAL DAY270$1,500.00$300.00
112Temp rumble strips (70106700)EACH12$1,500.00$1,500.00
113Pavt MK blkout tape 7 (70107007)LF2,370$3.00$3.00
114Pavt MK blkout tape 9 (70107009)LF914$3.90$3.90
115Pavt MK blkout tpe 12 (70107012)LF33$6.00$6.00
116Changeable message SN (70107025)CAL DAY56$100.00$100.00
117SHRT TRM pavt MK rem (70300150)SF28,129$0.90$0.90
118Temp PVT MK line 6 - paint (70300241)LF3,018$1.00$1.00
119Temp PVT MK line 8 - paint (70300251)LF291$2.00$2.00
120Temp PVT MK L6 T4 tape (70307130)LF47,290$1.90$1.90
121Temp PVT MK L8 T4 tape (70307140)LF2,621$2.55$2.55
122Temp PVT MK L12 T4 tape (70307160)LF637$3.80$3.80
123Temp conc barrier (70400100)LF7,275$75.00$42.00
124Pin temp conc barrier (70400125)EACH33$40.00$30.00
125Rel temp conc barrier (70400200)LF4,038$35.00$8.00
126Temp SPBGR TY A (70500100)LF75$43.39$33.75
127Temp TR bar term T1 (70500615)EACH1$3,425.84$3,400.00
128Temp TR bar term T6B (70500672)EACH1$4,567.78$2,750.00
129Imp attn temp FRN TL3 (70600260)EACH3$7,800.00$7,800.00
130Imp attn rel FRN TL3 (70600332)EACH4$100.00$100.00
131Rem & rel sign panel asmbly TB (72400210)EACH1$400.00$400.00
132Terminal marker - DA (72501000)EACH3$51.39$40.00
133Wood sin support (73000100)LF17$20.00$20.00
134Pref PL PM TD STD L 6 (78004630)LF18,204$10.25$5.50
135Pref PL PM TD STD L 8 (78004640)LF681$13.65$7.25
136GRV RCSD PVT MRKG 7 (78011035)LF18,204$2.25$0.75
137GRV RCSD PVT MRKG 9 (78011045)LF681$3.00$1.00
138Raised refl pavt MKR (78100100)EACH27$335.00$300.00
139Grdrail ref type A (78200005)EACH36$28.55$25.00
140Raised ref PVT MK rem (78300200)EACH25$150.00$75.00
141PVT MKG rem WTR blast (78300202)SF9,976$1.50$1.50
142Reloc EX LT unit (84400105)EACH2$3,875.00$3,875.00
IDOT contract 68510: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of August 1, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy