IDOT contract 70D66 bid tabulation
Section (92-9)BR. Let by Illinois DOT on September 19, 2025, Vermilion, District 05. 3 bids received; low bid $7,049,795 by Stark Excavating, Inc..
- Owner
- Illinois DOT
- Letting
- 19 SEP 2025
- Pay items
- 102
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Stark Excavating, Inc. | $7,049,795 | Low |
| 2 | Sangamo Construction Company | $7,835,888 | +11% |
| 3 | William Charles Construction Company, LLC | $8,781,093 | +25% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Stark Excavating, Inc. | 2. Sangamo Construction Company | 3. William Charles Construction Company, LLC |
|---|---|---|---|---|---|---|
| 1 | BR deck grooving long (X5030250) | SY | 1,209 | $11.00 | $15.46 | $11.00 |
| 2 | Bar terminators (X5080530) | EACH | 1,052 | $22.00 | $24.56 | $35.00 |
| 3 | Fence removal (X6640104) | LF | 174 | $15.00 | $7.38 | $20.00 |
| 4 | Real-time TR cont cbu (X7011854) | CAL MO | 18 | $1,325.00 | $1,320.25 | $1,250.00 |
| 5 | Real-time TR con W SGN (X7011860) | CAL MO | 144 | $235.00 | $237.65 | $225.00 |
| 6 | Real-time TR mon SU (X7011862) | CAL MO | 288 | $95.00 | $95.06 | $90.00 |
| 7 | Width restrict sign (X7200201) | LS | 1 | $3,250.00 | $3,432.66 | $3,250.00 |
| 8 | Approach slab rem (Z0004552) | SY | 542 | $60.00 | $71.30 | $50.00 |
| 9 | Construction layout (Z0013798) | LS | 1 | $40,000 | $56,274 | $70,000 |
| 10 | Sed cont silt curtain (Z0023201) | EACH | 1 | $5,000.00 | $3,427.46 | $8,500.00 |
| 11 | Diamond grind BR sec (Z0029090) | SY | 1,829 | $18.00 | $15.70 | $30.00 |
| 12 | Permnt bench marks (Z0038700) | EACH | 2 | $450.00 | $146.92 | $1,500.00 |
| 13 | Pipe underdrain remov (Z0040530) | LF | 1,477 | $15.00 | $10.94 | $17.50 |
| 14 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 | $0.80 |
| 15 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 | $15.00 |
| 16 | Tree remov 6-15 (20100110) | UNIT | 391 | $42.00 | $62.84 | $50.00 |
| 17 | Tree remov over 15 (20100210) | UNIT | 184 | $60.00 | $78.16 | $50.00 |
| 18 | Earth excavation (20200100) | CY | 385 | $110.00 | $135.25 | $125.00 |
| 19 | Channel excavation (20300100) | CY | 2,499 | $33.00 | $58.94 | $55.00 |
| 20 | Seeding CL 2A (25000210) | ACRE | 1 | $2,600.00 | $4,911.34 | $4,650.00 |
| 21 | Nitrogen fert nutr (25000400) | LB | 90 | $3.00 | $1.74 | $1.65 |
| 22 | Phosphorus fert nutr (25000500) | LB | 90 | $3.00 | $1.74 | $1.65 |
| 23 | Potassium fert nutr (25000600) | LB | 90 | $3.00 | $1.74 | $1.65 |
| 24 | Erosion contr blanket (25100630) | SY | 3,795 | $1.90 | $2.06 | $2.00 |
| 25 | Temp eros contr seed (28000250) | LB | 200 | $4.75 | $4.09 | $5.00 |
| 26 | Temp ditch checks (28000305) | LF | 96 | $14.00 | $20.20 | $12.00 |
| 27 | Perimeter eros bar (28000400) | LF | 807 | $5.25 | $6.71 | $4.00 |
| 28 | Inlet filters (28000510) | EACH | 5 | $300.00 | $479.96 | $400.00 |
| 29 | Temp eros contr blank (28001100) | SY | 3,795 | $1.90 | $3.14 | $3.50 |
| 30 | Stone riprap CL A4 (28100107) | SY | 71 | $130.00 | $90.88 | $120.00 |
| 31 | Stone riprap CL A5 (28100109) | SY | 3,673 | $140.00 | $103.98 | $125.00 |
| 32 | Filter fabric (28200200) | SY | 3,744 | $4.75 | $5.22 | $3.00 |
| 33 | Sub gran mat C 7 (31102400) | SY | 1,085 | $31.00 | $38.61 | $25.00 |
| 34 | HMA SC IL-9.5 D N70 (40604062) | TON | 403 | $400.00 | $401.09 | $400.00 |
| 35 | PVT con PCC BR app SL (42000080) | SY | 463 | $275.00 | $277.48 | $225.00 |
| 36 | Pavement rem (44000100) | SY | 318 | $53.00 | $52.19 | $60.00 |
| 37 | HMA surf rem 3 (44000161) | SY | 2,748 | $38.00 | $38.97 | $40.00 |
| 38 | Paved SHLD removal (44004250) | SY | 870 | $22.00 | $34.07 | $48.00 |
| 39 | Aggregate SHLDS B 6 (48101500) | SY | 1,338 | $35.00 | $22.94 | $30.00 |
| 40 | Agg wedge SHLD type B (48102100) | TON | 21 | $365.00 | $87.80 | $90.00 |
| 41 | HMA shoulders 8 (48203029) | SY | 1,009 | $160.00 | $161.55 | $155.00 |
| 42 | Rem exist struct N1 (50100300) | EACH | 1 | $295,000 | $170,983 | $200,000 |
| 43 | Rem exist struct N2 (50100400) | EACH | 1 | $295,000 | $170,983 | $200,000 |
| 44 | Structure excavation (50200100) | CY | 520 | $45.00 | $68.80 | $80.00 |
| 45 | Cofferdam excavation (50200300) | CY | 675 | $0.01 | $76.95 | $110.00 |
| 46 | Rock exc struct (50200400) | CY | 60 | $115.00 | $132.59 | $225.00 |
| 47 | Cofferdam typ 1 loc 1 (50201101) | EACH | 1 | $0.01 | $117,836 | $195,000 |
| 48 | Cofferdam typ 1 loc 2 (50201102) | EACH | 1 | $0.01 | $89,112 | $195,000 |
| 49 | Cofferdam typ 1 loc 3 (50201103) | EACH | 1 | $0.01 | $117,836 | $195,000 |
| 50 | Cofferdam typ 1 loc 4 (50201104) | EACH | 1 | $0.01 | $89,112 | $195,000 |
| 51 | Floor drains (50300100) | EACH | 40 | $495.00 | $538.49 | $500.00 |
| 52 | Conc struct (50300225) | CY | 439.60 | $1,265.00 | $1,375.90 | $1,600.00 |
| 53 | Conc sup-STR (50300255) | CY | 473.90 | $1,800.00 | $2,505.18 | $2,200.00 |
| 54 | Protective coat (50300300) | SY | 2,402 | $4.00 | $3.54 | $4.00 |
| 55 | Conc supstr app slab (50301350) | CY | 236.80 | $695.00 | $705.23 | $700.00 |
| 56 | F & E struct steel (50500105) | LS | 1 | $1,255,000 | $1,299,545 | $1,300,000 |
| 57 | Stud shear connectors (50500505) | EACH | 10,404 | $5.00 | $5.22 | $3.50 |
| 58 | Reinf bars, epoxy CTD (50800205) | LB | 280,560 | $1.70 | $1.62 | $1.75 |
| 59 | Bar splicers (50800515) | EACH | 2,024 | $38.00 | $47.35 | $35.00 |
| 60 | Fur STL pile HP12X63 (51201610) | LF | 904 | $95.00 | $237.56 | $225.00 |
| 61 | Fur STL pile HP14X73 (51201800) | LF | 710 | $65.00 | $77.61 | $75.00 |
| 62 | Driving piles (51202305) | LF | 904 | $0.01 | $0.03 | $1.00 |
| 63 | Test pile ST HP12X63 (51203610) | EACH | 2 | $48,850 | $5,057.32 | $15,000 |
| 64 | Drill & set piles (IS) (51265001) | CF | 491 | $135.00 | $24.00 | $150.00 |
| 65 | Drill & set piles (IR) (51265002) | CF | 547 | $170.00 | $69.00 | $200.00 |
| 66 | Name plates (51500100) | EACH | 2 | $1,250.00 | $1,174.60 | $750.00 |
| 67 | Anchor bolts 1 (52100520) | EACH | 96 | $110.00 | $115.69 | $130.00 |
| 68 | Temp SHT piling (52200010) | SF | 4,464 | $0.01 | $1.00 | $55.00 |
| 69 | Granular backfill STR (58600101) | CY | 276 | $75.00 | $91.27 | $105.00 |
| 70 | Geocomposite wall DR (59100100) | SY | 134 | $50.00 | $30.27 | $80.00 |
| 71 | Conc HDWL for P drain (60100060) | EACH | 6 | $585.00 | $301.84 | $750.00 |
| 72 | Pipe underdrain 4 SP (60108100) | LF | 108 | $50.00 | $9.69 | $35.00 |
| 73 | Pipe underdr T 3 (60108501) | LF | 1,477 | $18.50 | $46.66 | $20.00 |
| 74 | P undr for struct 4 (60146304) | LF | 382 | $40.00 | $27.42 | $25.00 |
| 75 | SPBGR TY A 6FT posts (63000001) | LF | 1,200 | $34.00 | $33.80 | $32.00 |
| 76 | Traf bar term T6 (63100085) | EACH | 4 | $5,200.00 | $5,342.53 | $4,600.00 |
| 77 | TR bar TRM T1 SPL tan (63100167) | EACH | 4 | $3,750.00 | $3,802.33 | $3,600.00 |
| 78 | Guardrail remov (63200310) | LF | 1,581 | $7.25 | $6.34 | $6.00 |
| 79 | Shoulder rum strip 16 (64200116) | LF | 3,060 | $4.50 | $1.90 | $9.00 |
| 80 | Wov W fence 4 (66500105) | LF | 174 | $68.00 | $68.65 | $65.00 |
| 81 | Engr field office B (67000500) | CAL MO | 18 | $2,100.00 | $3,063.97 | $3,500.00 |
| 82 | Mobilization (67100100) | LS | 1 | $421,250 | $462,317 | $528,000 |
| 83 | Traf cont-prot 701401 (70100205) | EACH | 2 | $5,800.00 | $36,207 | $10,000 |
| 84 | Traf cont-prot 701402 (70100207) | EACH | 2 | $21,125 | $46,342 | $50,000 |
| 85 | TR cont surveillance (70103815) | CAL DAY | 72 | $0.01 | $1.19 | $1,000.00 |
| 86 | Temp rumble strips (70106700) | EACH | 16 | $1,650.00 | $1,742.73 | $1,650.00 |
| 87 | Changeable message SN (70107025) | CAL DAY | 28 | $135.00 | $132.03 | $125.00 |
| 88 | SHRT TRM pavt MK rem (70300150) | SF | 4,555 | $2.00 | $2.01 | $1.90 |
| 89 | Temp PVT MK line 4 - paint (70300221) | LF | 7,201 | $0.75 | $0.74 | $0.70 |
| 90 | Temp PVT MK L4 T4 tape (70307120) | LF | 13,665 | $1.45 | $1.48 | $1.40 |
| 91 | Temp conc barrier (70400100) | LF | 937.50 | $48.00 | $56.52 | $50.50 |
| 92 | Pin temp conc barrier (70400125) | EACH | 87 | $48.00 | $86.81 | $40.00 |
| 93 | Rel temp conc barrier (70400200) | LF | 912.50 | $8.00 | $8.72 | $11.25 |
| 94 | Imp attn temp NRN TL3 (70600251) | EACH | 2 | $8,000.00 | $4,674.58 | $6,500.00 |
| 95 | Imp attn rel NRN TL3 (70600352) | EACH | 2 | $3,150.00 | $1,444.56 | $2,600.00 |
| 96 | Terminal marker - DA (72501000) | EACH | 4 | $50.00 | $52.81 | $50.00 |
| 97 | THPL PVT MK line 6 (78000400) | LF | 6,181 | $2.10 | $2.11 | $2.00 |
| 98 | Polyurea PM T2 LN 6 (78008330) | LF | 1,020 | $15.50 | $15.84 | $15.00 |
| 99 | GRV RCSD PVT MRKG 7 (78011035) | LF | 7,201 | $2.10 | $2.11 | $2.00 |
| 100 | Grdrail ref type A (78200005) | EACH | 20 | $10.00 | $10.56 | $10.00 |
| 101 | Barr wall ref type C (78200011) | EACH | 70 | $15.00 | $17.70 | $30.00 |
| 102 | PVT MKG rem grinding (78300201) | SF | 1,118 | $2.35 | $2.38 | $2.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of September 19, 2025. Compiled by Mirage Metrics.