IDOT contract 70E30 bid tabulation
Section D5. Let by Illinois DOT on June 13, 2025, Edgar, District 05. 3 bids received; low bid $1,111,995 by McCarthy Improvement Company.
- Owner
- Illinois DOT
- Letting
- 13 JUN 2025
- Pay items
- 31
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | McCarthy Improvement Company | $1,111,995 | Low |
| 2 | Feutz Contractors, Inc. | $1,188,828 | +7.0% |
| 3 | Kieffer Bros. Construction Co., Inc. | $1,439,754 | +29% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. McCarthy Improvement Company | 2. Feutz Contractors, Inc. | 3. Kieffer Bros. Construction Co., Inc. |
|---|---|---|---|---|---|---|
| 1 | Construction layout (Z0013798) | LS | 1 | $20,000 | $8,800.00 | $48,495 |
| 2 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 | $15.00 |
| 3 | Earth excavation (20200100) | CY | 985 | $43.00 | $55.00 | $44.00 |
| 4 | Trench backfill (20800150) | CY | 194 | $75.00 | $48.00 | $77.00 |
| 5 | Sub gran mat A 4 (31100300) | SY | 5,582 | $12.00 | $12.25 | $14.00 |
| 6 | Welded wire reinf (42000060) | SY | 992 | $14.00 | $19.00 | $17.00 |
| 7 | PCC PVT 10 jointed (42000501) | SY | 4,590 | $105.00 | $113.00 | $134.50 |
| 8 | PCC PVT 12 (42000540) | SY | 992 | $130.00 | $132.00 | $162.87 |
| 9 | Pavement rem (44000100) | SY | 5,582 | $20.00 | $23.75 | $52.15 |
| 10 | Conc rem (50102400) | CY | 0.20 | $15,000 | $6,000.00 | $2,186.25 |
| 11 | Storm sew CL B 1 12 (550B0050) | LF | 78 | $70.00 | $91.00 | $60.18 |
| 12 | Storm sew CL B 1 15 (550B0070) | LF | 119 | $78.00 | $110.00 | $72.27 |
| 13 | Storm sewer rem 6 (55100200) | LF | 360 | $18.00 | $18.00 | $11.13 |
| 14 | Storm sewer rem 8 (55100300) | LF | 480 | $12.00 | $18.00 | $13.78 |
| 15 | Storm sewer rem 12 (55100500) | LF | 30 | $15.00 | $18.00 | $34.45 |
| 16 | Storm sewer rem 14 (55100600) | LF | 60 | $14.00 | $18.00 | $45.58 |
| 17 | Storm sewer rem 18 (55100900) | LF | 71 | $6.00 | $22.00 | $45.58 |
| 18 | Water valves adjust (56109210) | EACH | 2 | $250.00 | $1,300.00 | $225.25 |
| 19 | Contr low-streng matl (59300100) | CY | 100 | $180.00 | $200.00 | $284.08 |
| 20 | Pipe drains 6 (60100915) | LF | 445 | $80.00 | $65.00 | $23.11 |
| 21 | Pipe drains 8 (60100925) | LF | 368 | $65.00 | $69.00 | $33.66 |
| 22 | Man TA 4 dia T1F OL (60218300) | EACH | 1 | $4,800.00 | $5,800.00 | $5,572.96 |
| 23 | Man TA 4 dia T1F CL (60218400) | EACH | 1 | $4,800.00 | $5,800.00 | $5,572.96 |
| 24 | Inlets TA T1F OL (60234200) | EACH | 2 | $2,800.00 | $2,800.00 | $1,527.84 |
| 25 | Inlets TB T1F OL (60240210) | EACH | 1 | $3,500.00 | $4,100.00 | $2,291.57 |
| 26 | Inlets TB T1F CL (60240215) | EACH | 2 | $3,500.00 | $4,000.00 | $2,291.57 |
| 27 | Remov inlets (60500060) | EACH | 3 | $750.00 | $1,190.00 | $477.00 |
| 28 | Engr field office B (67000500) | CAL MO | 6 | $3,000.00 | $3,800.00 | $2,157.10 |
| 29 | Mobilization (67100100) | LS | 1 | $65,000 | $63,850 | $38,319 |
| 30 | Paint PVT MK line 4 (78001110) | LF | 425 | $7.00 | $7.00 | $7.58 |
| 31 | Paint PVT MK line 6 (78001130) | LF | 50 | $10.50 | $10.50 | $11.37 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 13, 2025. Compiled by Mirage Metrics.