IDOT contract 74650 bid tabulation

Section (15-22VB)BR. Let by Illinois DOT on September 18, 2026, Coles, District 07. 3 bids received; low bid $11,526,296 by Sangamo Construction Company.

Owner
Illinois DOT
Letting
18 SEP 2026
Pay items
128
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Sangamo Construction Company$11,526,296Low
2Samron Midwest Contracting, Inc.$11,858,707+3.0%
3William Charles Construction Company, LLC$13,075,769+13%
IDOT contract 74650: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Sangamo Construction Company2. Samron Midwest Contracting, Inc.3. William Charles Construction Company, LLC
1Seeding CL 2 SPL (X2501000)ACRE2.10$6,492.81$10,000$6,150.00
2Recoverable delineatr (X2600002)EACH38$213.95$90.00$95.00
3HMA surf rem var DP (X4401198)SY2,286$16.10$18.00$15.25
4BR deck grooving long (X5030250)SY2,254$9.42$10.00$12.50
5Bar terminators (X5080530)EACH580$22.40$25.00$32.00
6Pipe drains 12 SPL (X6012005)LF286$56.37$38.00$45.00
7Rem conc HDWL P DRNS (X6015000)EACH3$270.59$500.00$325.00
8Plug exist deck drain (X6050182)EACH8$276.25$230.00$650.00
9Remove inlet box (X6050700)EACH7$437.27$1,100.00$850.00
10Temp rumble strips SP (X7010118)EACH28$1,989.94$1,300.00$1,700.00
11Real-time TR cont cbu (X7011854)CAL MO10$1,583.61$3,700.00$1,500.00
12Real-time TR cont SU (X7011856)CAL MO160$232.26$290.00$220.00
13Real-time TR con W SGN (X7011860)CAL MO80$548.99$600.00$520.00
14Temp TRBT T1 SPL tan (X7050167)EACH2$3,695.10$4,100.00$3,500.00
15Temp raised pavt MKR (X7810400)EACH360$109.80$65.00$104.00
16Temp lighting system (X8410102)LS1$350,456$0.01$119,500
17BR approach SHLD rem (Z0001495)SY72$70.19$7.00$105.00
18Approach slab rem (Z0004552)SY214$65.48$90.00$90.00
19HMA surface RM (deck) (Z0004556)SY752$16.38$50.00$25.00
20Deck slab rep (FD-T2) (Z0016002)SY200$912.28$1,225.00$1,450.00
21Deck slab rep (part) (Z0016200)SY150$567.75$650.00$750.00
22Diamond grind BR sec (Z0029090)SY2,374$13.00$12.00$19.00
23RR prot liability ins (Z0048665)LS1$16,892$42,000$75,000
24Tree remov 6-15 (20100110)UNIT52$128.15$42.00$110.00
25Tree remov over 15 (20100210)UNIT18$185.11$120.00$140.00
26Earth excavation (20200100)CY1,244$77.45$27.00$100.00
27Topsoil exc & plac (21101505)CY1,066$48.39$21.00$90.00
28Erosion contr blanket (25100630)SY168$2.38$0.50$2.25
29Temp eros contr seed (28000250)LB210$4.15$2.00$10.00
30Temp ditch checks (28000305)LF40$30.97$23.00$25.00
31Inlet & pipe protect (28000500)EACH8$301.93$210.00$300.00
32Sub gran mat B (31101000)TON899$56.53$60.00$60.00
33Agg base cse B (35101400)TON7,698$40.03$45.00$52.00
34Agg base cse B (35101500)CY850$128.22$115.00$108.00
35Bit matls tack CT (40600290)LB2,346$7.93$9.00$7.51
36Long joint sealant (40600370)LF858$29.03$50.00$27.50
37P HMA BC IL-9.5FG N90 (40603219)TON146$403.78$450.00$382.46
38P HMA SC IL-9.5 D N90 (40604164)TON370$366.76$400.00$347.40
39Welded wire reinf (42000060)SY5,098$13.13$8.00$16.00
40PVT con PCC BR app SL (42000080)SY346$264.40$250.00$350.00
41PCC PVT 10 3/4 jointd (42000516)SY5,098$109.71$120.00$140.00
42Pavement rem (44000100)SY305$50.65$40.00$48.00
43Paved SHLD removal (44004250)SY7,362$18.82$13.00$25.00
44Aggregate SHLDS B (48101200)TON47$82.77$52.00$95.00
45Agg wedge SHLD type B (48102100)TON15$83.98$85.00$210.00
46HMA shoulders 6 (48203021)SY666$99.96$105.00$94.68
47HMA shoulders (48203100)TON214$329.59$355.00$312.19
48PCC shoulders 10 (48300500)SY9,190$100.52$120.00$108.00
49Rem exist struct N1 (50100300)EACH1$167,839$453,000$150,000
50Rem exist struct N2 (50100400)EACH1$167,839$453,000$150,000
51Conc rem (50102400)CY67.60$1,430.63$2,000.00$2,500.00
52Slope wall remov (50104650)SY1,660$13.45$21.30$26.00
53Protective shield (50157300)SY1,338$1.00$0.01$25.00
54Structure excavation (50200100)CY630$104.57$43.00$85.00
55Conc struct (50300225)CY322.60$1,899.03$1,550.00$1,800.00
56Conc sup-STR (50300255)CY652$1,767.81$1,700.00$1,850.00
57Protective coat (50300300)SY2,852$3.38$2.00$3.50
58Conc supstr app slab (50301350)CY234.20$709.64$620.00$675.00
59F & E struct steel (50500105)LS1$1,232,609$1,445,000$1,400,000
60Stud shear connectors (50500505)EACH15,102$4.43$4.75$5.50
61Reinf bars, epoxy CTD (50800205)LB300,110$1.85$1.80$2.30
62Slope wall 4 (51100100)SY1,760$180.44$146.00$225.00
63Fur STL pile HP10X42 (51201400)LF1,910$99.03$140.00$110.00
64Driving piles (51202305)LF1,910$0.02$0.01$1.00
65Test pile ST HP10X42 (51203400)EACH4$9,123.37$0.01$11,500
66Pile shoes (51204650)EACH30$163.72$156.00$175.00
67Name plates (51500100)EACH2$1,164.89$950.00$1,200.00
68Elast bearing assy T1 (52100010)EACH48$1,924.88$1,820.00$3,600.00
69Anchor bolts 1 (52100520)EACH120$152.43$130.00$125.00
70Temp soil reten systm (52200020)SF360$1.00$0.01$165.00
71P cul CL A 1 15 (542A0220)LF66$99.82$112.00$75.00
72P cul CL A 1 24 (542A0229)LF1,149$108.11$83.00$80.00
73PRC flar end sec 12 (54213657)EACH4$1,353.77$1,150.00$1,750.00
74PRC flar end sec 24 (54213669)EACH1$2,347.98$1,550.00$2,800.00
75Inlet box 542531 (54246405)EACH3$21,205$18,750$18,000
76Granular backfill STR (58600101)CY368$89.45$120.00$115.00
77Concrete sealer (58700300)SF1,460$2.62$1.50$4.00
78Geocomposite wall DR (59100100)SY176$26.74$16.00$55.00
79Conc HDWL for P drain (60100060)EACH1$296.69$1,000.00$550.00
80Pipe underdrain 4 SP (60108100)LF90$17.66$23.00$30.00
81P undr for struct 4 (60146304)LF264$28.66$32.00$38.00
82Man TA 4 dia T1F OL (60218300)EACH2$7,887.22$4,200.00$7,000.00
83Inlets TA T8G (60236200)EACH4$2,110.88$2,300.00$2,800.00
84Inl recon new T1F CL (60263000)EACH1$7,205.46$2,300.00$3,100.00
85Conc curb TB (60600605)LF2,304$54.86$35.00$85.00
86Conc thrust blocks (61000050)EACH4$852.18$1,000.00$1,750.00
87TY F inlet box 610001 (61000225)EACH7$5,097.28$6,770.00$6,500.00
88SPBGR TY A 6FT posts (63000001)LF3,950$41.53$43.00$37.00
89Traf bar term T2 (63100045)EACH2$1,794.76$2,000.00$1,700.00
90Traf bar term T6 (63100085)EACH6$6,220.74$6,400.00$5,500.00
91TR bar TRM T1 SPL tan (63100167)EACH4$4,434.12$4,850.00$4,200.00
92Guardrail remov (63200310)LF3,542$5.80$6.00$5.00
93Rem RE-E SPBGR TY A (63301210)LF100$36.95$40.50$35.00
94Mod glar SCR sys temp (63800920)LF4,474$14.03$13.00$13.00
95Shoulder rum strip 16 (64200116)LF5,526$1.76$1.00$2.25
96Non SPL waste disposl (66900200)CY1,725$105.25$74.50$75.00
97SPL wast GRD wat disp (66900400)GAL15,000$2.55$2.50$2.50
98Soil disposal analy (66900530)EACH1$1,583.61$1,750.00$1,925.00
99Reg sub P-const plan (66901001)LS1$3,167.23$3,500.00$2,400.00
100Reg sub F con report (66901003)LS1$1,055.74$1,150.00$2,600.00
101Reg sub mon (66901006)CAL DAY16$1,583.61$1,750.00$1,200.00
102Mobilization (67100100)LS1$680,051$710,000$875,000
103Traf cont-prot 701316 (70100100)EACH2$18,713$15,000$25,000
104Traf cont-prot 701401 (70100205)EACH2$23,998$135,000$35,000
105Traf cont-prot 701402 (70100207)EACH1$41,577$0.01$38,000
106Traf cont-prot 701416 (70100410)EACH2$119,344$75,000$225,000
107Traf cont-prot 701201 (70100450)LS1$23,462$0.01$25,000
108Traf cont-prot 701406 (70100700)LS1$1.00$0.01$65,000
109Temp BR traf signals (70106500)EACH2$34,840$0.01$45,000
110Pavt MK blkout tape 8 (70107008)LF1,000$3.43$4.50$3.25
111Short term pavt mking (70300100)LF1,192$0.01$1.50$2.00
112SHRT TRM pavt MK rem (70300150)SF13,198$3.06$0.80$5.00
113Temp PVT MK line 6 - paint (70300241)LF20,410$0.46$0.50$0.42
114Temp PVT MK L4 T4 tape (70307120)LF38,400$1.95$2.00$1.85
115Temp conc barrier (70400100)LF5,125$41.81$39.00$35.50
116Pin temp conc barrier (70400125)EACH870$31.44$17.00$25.00
117Rel temp conc barrier (70400200)LF438$9.01$4.00$16.00
118Temp SPBGR TY A (70500100)LF175$33.78$35.00$32.00
119Temp TR bar term T6 (70500665)EACH2$4,637.14$1,700.00$4,000.00
120Imp attn temp NRN TL3 (70600251)EACH1$9,874.54$4,500.00$4,200.00
121Imp attn rel NRN TL3 (70600352)EACH1$1,491.72$2,000.00$500.00
122Terminal marker - DA (72501000)EACH8$52.79$58.00$50.00
123Pref PL PM TD STD L 6 (78004630)LF20,410$5.93$6.00$6.44
124GRV RCSD PVT MRKG 7 (78011035)LF20,410$1.36$1.50$0.49
125Raised refl pavt MKR (78100100)EACH22$477.77$515.00$130.29
126Grdrail ref type A (78200005)EACH43$10.56$10.00$10.00
127Raised ref PVT MK rem (78300200)EACH22$12.22$125.00$215.00
128PVT MKG rem WTR blast (78300202)SF5,035$1.71$1.75$1.58
IDOT contract 74650: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of September 18, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy