IDOT contract 78A09 bid tabulation
Section 127CR-1. Let by Illinois DOT on January 16, 2026, Franklin, District 09. 3 bids received; low bid $957,763 by Samron Midwest Contracting, Inc..
- Owner
- Illinois DOT
- Letting
- 16 JAN 2026
- Pay items
- 75
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Samron Midwest Contracting, Inc. | $957,763 | Low |
| 2 | Guinzy Construction,Inc. | $1,069,096 | +12% |
| 3 | Sierra Bravo Contractors, LLC | $1,294,688 | +35% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Samron Midwest Contracting, Inc. | 2. Guinzy Construction,Inc. | 3. Sierra Bravo Contractors, LLC |
|---|---|---|---|---|---|---|
| 1 | Concrete slab removal (X5012504) | SY | 75 | $5.00 | $49.62 | $61.17 |
| 2 | Prcast conc JCN CHMBR (X5040150) | EACH | 2 | $30,000 | $59,403 | $41,592 |
| 3 | Pro SS conn to EX man (X5510011) | EACH | 1 | $1,500.00 | $5,778.96 | $5,079.33 |
| 4 | Memb WTRPRF sys B STR (X5810103) | SY | 227 | $20.00 | $60.06 | $46.96 |
| 5 | Traf cont & prot SPL (X7010216) | LS | 1 | $93,000 | $53,116 | $33,549 |
| 6 | Detour signing (X7200203) | LS | 1 | $15,000 | $123,180 | $26,250 |
| 7 | Construction layout (Z0013798) | LS | 1 | $12,000 | $30,355 | $18,375 |
| 8 | Earth excavation (20200100) | CY | 68 | $20.00 | $42.47 | $58.45 |
| 9 | Furnished excavation (20400800) | CY | 18 | $80.00 | $150.29 | $97.48 |
| 10 | Porous gran embank (20700220) | CY | 272 | $50.00 | $93.19 | $83.62 |
| 11 | Trench backfill (20800150) | CY | 35 | $60.00 | $102.58 | $82.41 |
| 12 | Seeding CL 2 (25000200) | ACRE | 0.10 | $11,500 | $21,866 | $29,400 |
| 13 | Seeding CL 7 (25000350) | ACRE | 0.10 | $0.01 | $21,866 | $787.50 |
| 14 | Nitrogen fert nutr (25000400) | LB | 7.50 | $2.00 | $2.43 | $1.73 |
| 15 | Phosphorus fert nutr (25000500) | LB | 7.50 | $2.00 | $2.43 | $1.73 |
| 16 | Potassium fert nutr (25000600) | LB | 7.50 | $2.00 | $2.43 | $1.73 |
| 17 | Agr ground limestone (25000700) | TON | 0.20 | $2,650.00 | $212.48 | $367.50 |
| 18 | Erosion contr blanket (25100630) | SY | 459 | $1.00 | $2.63 | $3.68 |
| 19 | Temp eros contr seed (28000250) | LB | 8.30 | $0.01 | $27.41 | $24.63 |
| 20 | Perimeter eros bar (28000400) | LF | 265 | $6.00 | $14.10 | $6.58 |
| 21 | Inlet filters (28000510) | EACH | 9 | $200.00 | $78.67 | $347.72 |
| 22 | Stone riprap CL A1 (28100101) | SY | 36 | $0.01 | $136.62 | $33.64 |
| 23 | Stone riprap CL A4 (28100107) | SY | 36 | $60.00 | $96.98 | $82.82 |
| 24 | Filter fabric (28200200) | SY | 44 | $4.00 | $1.40 | $7.61 |
| 25 | Agg subgrade impr 12 (30300112) | SY | 90 | $22.00 | $91.18 | $41.05 |
| 26 | Welded wire reinf (42000060) | SY | 71 | $10.00 | $1.36 | $28.00 |
| 27 | PCC PVT 9 (42000400) | SY | 71 | $230.00 | $289.58 | $271.62 |
| 28 | PCC driveway pavt 6 (42300200) | SY | 48 | $130.00 | $231.78 | $311.80 |
| 29 | PCC driveway pavt 7 (42300300) | SY | 135 | $90.00 | $143.37 | $214.28 |
| 30 | PC conc sidewalk 5 (42400200) | SF | 1,045 | $13.00 | $18.50 | $18.08 |
| 31 | Pavement rem (44000100) | SY | 99 | $6.00 | $93.39 | $48.05 |
| 32 | HMA surf rem 4 (44000165) | SY | 88 | $17.00 | $165.57 | $36.04 |
| 33 | Drive pavement rem (44000200) | SY | 112 | $23.00 | $63.94 | $56.63 |
| 34 | Curb rem (44000300) | LF | 38 | $20.00 | $37.32 | $35.61 |
| 35 | Comb curb gutter rem (44000500) | LF | 312 | $25.00 | $23.16 | $20.33 |
| 36 | Sidewalk rem (44000600) | SF | 833 | $0.50 | $5.30 | $9.52 |
| 37 | CL C patch T3 9 (44201345) | SY | 43 | $170.00 | $362.79 | $606.53 |
| 38 | Rem exist struct (50100100) | EACH | 1 | $175,000 | $21,278 | $19,029 |
| 39 | Reinforcement bars (50800105) | LB | 4,240 | $2.00 | $4.25 | $3.16 |
| 40 | Temp soil reten systm (52200020) | SF | 2,397 | $0.01 | $10.93 | $106.04 |
| 41 | Box cul end sec C1 (54001001) | EACH | 1 | $35,000 | $14,716 | $26,795 |
| 42 | Conc box cul (54003000) | CY | 15 | $2,300.00 | $1,808.47 | $3,519.36 |
| 43 | PCBC 8X3 (54010803) | LF | 120 | $1,000.00 | $866.12 | $1,211.86 |
| 44 | PCBC 11X2 (54011102) | LF | 28 | $3,700.00 | $1,379.12 | $1,490.31 |
| 45 | Concrete collar (54248510) | CY | 2 | $270.00 | $411.26 | $2,969.08 |
| 46 | Storm sew CL A 1 12 (550A0050) | LF | 103 | $100.00 | $105.53 | $151.17 |
| 47 | Storm sew CL A 1 15 (550A0070) | LF | 28 | $200.00 | $143.66 | $201.60 |
| 48 | Storm sew CL A 1 24 (550A0120) | LF | 17 | $300.00 | $265.17 | $295.41 |
| 49 | Storm sewer rem 8 (55100300) | LF | 9 | $150.00 | $209.14 | $101.20 |
| 50 | Storm sewer rem 12 (55100500) | LF | 51 | $0.01 | $36.91 | $53.58 |
| 51 | Storm sewer rem 24 (55101200) | LF | 27 | $20.00 | $69.71 | $67.47 |
| 52 | Geocomposite wall DR (59100100) | SY | 227 | $10.00 | $12.72 | $25.65 |
| 53 | CB TA 4 dia T11F&G (60201105) | EACH | 2 | $3,700.00 | $6,303.43 | $12,903 |
| 54 | CB TA 4 dia T15F&L (60201305) | EACH | 2 | $4,000.00 | $5,654.75 | $12,903 |
| 55 | Man TA 4 dia T1F CL (60218400) | EACH | 1 | $5,000.00 | $5,266.21 | $6,283.06 |
| 56 | Inlets TB T11F&G (60240310) | EACH | 2 | $3,000.00 | $3,361.47 | $3,702.38 |
| 57 | Remov manholes (60500040) | EACH | 1 | $2,000.00 | $1,201.13 | $1,242.49 |
| 58 | Remov inlets (60500060) | EACH | 2 | $100.00 | $1,201.13 | $1,242.46 |
| 59 | Conc curb TB (60600605) | LF | 69 | $47.00 | $123.74 | $184.90 |
| 60 | Comb CC&G TB6.18 (60604400) | LF | 312 | $60.00 | $64.79 | $102.23 |
| 61 | Non SPL waste disposl (66900200) | CY | 292 | $60.00 | $110.84 | $63.18 |
| 62 | Soil disposal analy (66900530) | EACH | 1 | $2,200.00 | $1,942.69 | $1,260.00 |
| 63 | Reg sub P-const plan (66901001) | LS | 1 | $2,800.00 | $2,792.61 | $1,890.00 |
| 64 | Reg sub F con report (66901003) | LS | 1 | $3,000.00 | $2,914.03 | $1,890.00 |
| 65 | Reg sub mon (66901006) | CAL DAY | 5 | $1,500.00 | $1,487.37 | $1,260.00 |
| 66 | Engr field office A (67000400) | CAL MO | 6 | $1,000.00 | $384.49 | $2,804.23 |
| 67 | Mobilization (67100100) | LS | 1 | $56,000 | $59,100 | $77,461 |
| 68 | Changeable message SN (70107025) | CAL DAY | 28 | $100.00 | $108.41 | $125.12 |
| 69 | SHRT TRM pavt MK rem (70300150) | SF | 415 | $2.00 | $12.14 | $10.35 |
| 70 | Temp PVT MK L4 T4 tape (70307120) | LF | 1,245 | $3.00 | $1.74 | $6.25 |
| 71 | Temp conc barrier (70400100) | LF | 255 | $0.01 | $170.80 | $186.88 |
| 72 | Imp attn temp NRN TL2 (70600241) | EACH | 2 | $6,000.00 | $4,598.16 | $9,782.63 |
| 73 | Remov sin pan assy TB (72400200) | EACH | 1 | $200.00 | $908.27 | $2,057.76 |
| 74 | Paint PVT MK line 4 (78001110) | LF | 830 | $5.00 | $4.98 | $3.41 |
| 75 | PVT MKG rem grinding (78300201) | SF | 277 | $5.00 | $18.21 | $4.46 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.