IDOT contract 80B14 bid tabulation
Section 2025-1087-RS. Let by Illinois DOT on January 16, 2026, Will, District 01. 4 bids received; low bid $2,039,223 by D. Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 16 JAN 2026
- Pay items
- 55
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D. Construction, Inc. | $2,039,223 | Low |
| 2 | P. T. Ferro Construction Co. | $2,049,298 | 0.0% |
| 3 | Austin Tyler Construction, Inc. | $2,297,279 | +13% |
| 4 | Gallagher Asphalt Corporation | $2,346,694 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D. Construction, Inc. | 2. P. T. Ferro Construction Co. | 3. Austin Tyler Construction, Inc. | 4. Gallagher Asphalt Corporation |
|---|---|---|---|---|---|---|---|
| 1 | Weed cont NTV LSC RMN (X2000001) | UNIT | 1 | $2,750.00 | $1,000.00 | $1,000.00 | $1,900.00 |
| 2 | Temporary ramp SPL (X4060995) | SY | 24 | $0.01 | $50.00 | $0.01 | $0.01 |
| 3 | CC&G RMVL repl < = 10 (X4400501) | LF | 2,326 | $45.00 | $40.00 | $68.00 | $30.00 |
| 4 | CC&G RMVL repl > 10FT (X4400503) | LF | 2,326 | $40.00 | $40.00 | $58.00 | $56.00 |
| 5 | Class SI conc out SPL (X6060097) | CY | 2 | $600.00 | $0.01 | $1,170.00 | $906.15 |
| 6 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 6 | $5,000.00 | $1.00 | $0.01 | $500.00 |
| 7 | Temp info signing (X7200061) | SF | 51 | $25.00 | $18.00 | $18.00 | $19.75 |
| 8 | Det loop repl (X8860105) | LF | 1,866 | $20.85 | $18.95 | $18.95 | $19.00 |
| 9 | Drainage STR cleaned (Z0018500) | EACH | 10 | $450.00 | $425.00 | $500.00 | $423.00 |
| 10 | Earth excavation (20200100) | CY | 10 | $100.00 | $400.00 | $133.00 | $325.00 |
| 11 | Topsoil F & P 4 (21101615) | SY | 1,034 | $7.15 | $6.50 | $7.00 | $12.52 |
| 12 | Nitrogen fert nutr (25000400) | LB | 19 | $3.30 | $3.00 | $3.00 | $25.00 |
| 13 | Phosphorus fert nutr (25000500) | LB | 19 | $3.30 | $3.00 | $3.00 | $25.00 |
| 14 | Potassium fert nutr (25000600) | LB | 19 | $3.30 | $3.00 | $3.00 | $25.00 |
| 15 | Sodding salt tolerant (25200110) | SY | 1,034 | $12.65 | $11.50 | $14.00 | $18.50 |
| 16 | Supple watering (25200200) | UNIT | 10 | $132.00 | $120.00 | $250.00 | $246.00 |
| 17 | Bit matls tack CT (40600290) | LB | 36,202 | $0.01 | $0.01 | $0.01 | $1.00 |
| 18 | Long joint sealant (40600370) | LF | 11,236 | $3.22 | $6.00 | $2.70 | $3.30 |
| 19 | Mix CR JTS flangewys (40600400) | TON | 81 | $0.01 | $0.01 | $350.00 | $0.01 |
| 20 | HMA surf rem butt JT (40600982) | SY | 728 | $0.01 | $0.01 | $20.00 | $27.00 |
| 21 | HMA BC IL-9.5 N70 (40602985) | TON | 6,007 | $70.00 | $76.00 | $69.00 | $94.50 |
| 22 | P HMA SC SMA 9.5 F N80 (40605026) | TON | 5,257 | $105.00 | $120.00 | $108.00 | $128.00 |
| 23 | HMA surf rem 3 3/4 (44000164) | SY | 53,633 | $2.75 | $2.80 | $3.00 | $4.00 |
| 24 | Median removal (PD) (44003510) | SF | 10,209 | $2.75 | $0.01 | $0.01 | $3.00 |
| 25 | Welded wire reinf (44200050) | SY | 3 | $50.00 | $12.00 | $5.00 | $21.00 |
| 26 | CL D patch T1 12 (44201785) | SY | 135 | $101.00 | $0.01 | $180.00 | $120.00 |
| 27 | CL D patch T2 12 (44201789) | SY | 1,073 | $101.00 | $50.00 | $180.00 | $90.00 |
| 28 | CL D patch T3 12 (44201794) | SY | 805 | $101.00 | $50.00 | $150.00 | $70.00 |
| 29 | CL D patch T4 12 (44201796) | SY | 671 | $101.00 | $50.00 | $150.00 | $60.00 |
| 30 | Tie bars 3/4 (44213204) | EACH | 12 | $20.00 | $50.00 | $22.00 | $6.30 |
| 31 | Class SI conc outlet (60600095) | CY | 2 | $600.00 | $3,000.00 | $1,170.00 | $909.25 |
| 32 | Conc median surf 4 (60618300) | SF | 10,209 | $7.00 | $0.01 | $6.00 | $6.30 |
| 33 | Shoulder rum strip 16 (64200116) | LF | 14,453 | $0.36 | $0.60 | $1.00 | $0.45 |
| 34 | Non SPL waste disposl (66900200) | CY | 10 | $150.00 | $300.00 | $78.00 | $213.00 |
| 35 | Mobilization (67100100) | LS | 1 | $75,000 | $120,000 | $75,000 | $140,000 |
| 36 | Traf cont-prot 701421 (70100310) | LS | 1 | $86,175 | $51,100 | $5,000.00 | $6,352.00 |
| 37 | TR cont & prot 701601 (70102630) | LS | 1 | $0.01 | $51,100 | $5,000.00 | $6,352.00 |
| 38 | TR cont & prot 701701 (70102635) | LS | 1 | $0.01 | $51,100 | $5,000.00 | $6,352.00 |
| 39 | Short term pavt mking (70300100) | LF | 16,138 | $0.01 | $1.50 | $2.00 | $0.01 |
| 40 | SHRT TRM pavt MK rem (70300150) | SF | 5,379 | $0.01 | $0.01 | $2.00 | $0.01 |
| 41 | Temp PVT MK LTR & sym paint (70300211) | SF | 512 | $0.01 | $0.01 | $1.75 | $0.01 |
| 42 | Temp PVT MK line 4 - paint (70300221) | LF | 22,434 | $0.01 | $0.35 | $0.35 | $0.01 |
| 43 | Temp PVT MK line 6 - paint (70300241) | LF | 1,695 | $0.01 | $0.53 | $0.53 | $0.01 |
| 44 | Temp PVT MK line 8 - paint (70300251) | LF | 3,521 | $0.01 | $0.01 | $0.70 | $0.01 |
| 45 | Temp PVT MK line 12 - paint (70300261) | LF | 1,624 | $0.01 | $0.01 | $1.06 | $0.01 |
| 46 | Temp PVT MK line 24 - paint (70300281) | LF | 329 | $0.01 | $0.01 | $1.60 | $0.01 |
| 47 | Rem & rel sign panel asmbly TA (72400205) | EACH | 1 | $357.50 | $150.00 | $150.00 | $164.80 |
| 48 | THPL PVT MK LTR & sym (78000100) | SF | 552 | $6.60 | $6.00 | $6.50 | $6.00 |
| 49 | THPL PVT MK line 4 (78000200) | LF | 22,434 | $0.66 | $0.60 | $0.75 | $0.60 |
| 50 | THPL PVT MK line 6 (78000400) | LF | 1,695 | $1.21 | $1.10 | $1.15 | $1.10 |
| 51 | THPL PVT MK line 8 (78000500) | LF | 3,521 | $1.65 | $1.50 | $1.50 | $1.50 |
| 52 | THPL PVT MK line 12 (78000600) | LF | 1,624 | $3.30 | $3.00 | $2.50 | $3.00 |
| 53 | THPL PVT MK line 24 (78000650) | LF | 329 | $6.60 | $6.00 | $6.50 | $6.00 |
| 54 | Raised refl pavt MKR (78100100) | EACH | 132 | $55.00 | $60.00 | $75.00 | $50.00 |
| 55 | Raised ref PVT MK rem (78300200) | EACH | 132 | $10.00 | $0.01 | $59.00 | $0.01 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.