IDOT contract 80B34 bid tabulation
Section 2025-2004-RS. Let by Illinois DOT on January 16, 2026, Will, District 01. 6 bids received; low bid $977,777 by Gallagher Asphalt Corporation.
- Owner
- Illinois DOT
- Letting
- 16 JAN 2026
- Pay items
- 84
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Gallagher Asphalt Corporation | $977,777 | Low |
| 2 | D. Construction, Inc. | $999,189 | +2.0% |
| 3 | P. T. Ferro Construction Co. | $1,069,082 | +9.0% |
| 4 | Builders Paving, LLC | $1,083,067 | +11% |
| 5 | Austin Tyler Construction, Inc. | $1,087,776 | +11% |
| 6 | K-Five Construction Corporation | $1,234,982 | +26% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Gallagher Asphalt Corporation | 2. D. Construction, Inc. | 3. P. T. Ferro Construction Co. | 4. Builders Paving, LLC | 5. Austin Tyler Construction, Inc. | 6. K-Five Construction Corporation |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Constructn layout SPL (X0320050) | LS | 1 | $6,218.00 | $7,500.00 | $25,000 | $6,000.00 | $3,750.00 | $2,428.89 |
| 2 | Ped signal post 10 FT (X1400367) | EACH | 1 | $1,300.00 | $1,428.88 | $1,298.98 | $1,300.00 | $1,300.00 | $1,397.07 |
| 3 | CC&G RMVL repl < = 10 (X4400501) | LF | 8 | $106.25 | $100.00 | $200.00 | $145.00 | $1,160.00 | $155.17 |
| 4 | CC&G RMVL repl > 10FT (X4400503) | LF | 2,565 | $43.50 | $45.00 | $70.00 | $66.00 | $58.00 | $68.17 |
| 5 | FR & lids adjust SPL (X6030310) | EACH | 1 | $1,400.00 | $1,000.00 | $2,000.00 | $2,550.00 | $1,500.00 | $2,500.00 |
| 6 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 6 | $500.00 | $5,000.00 | $2,000.00 | $3,100.00 | $3,000.00 | $3,000.00 |
| 7 | Temp info signing (X7200061) | SF | 115 | $13.00 | $30.00 | $15.00 | $12.50 | $35.00 | $16.13 |
| 8 | Accessible ped signal (X8760200) | EACH | 2 | $4,000.00 | $4,358.54 | $3,962.31 | $4,000.00 | $3,965.00 | $4,261.50 |
| 9 | Conc FDN TY A 12D (X8780012) | LF | 4 | $475.00 | $506.64 | $460.58 | $465.00 | $465.00 | $495.36 |
| 10 | Det loop repl (X8860105) | LF | 2,197 | $21.60 | $23.19 | $21.08 | $21.10 | $22.00 | $22.00 |
| 11 | Drainage STR cleaned (Z0018500) | EACH | 2 | $625.00 | $1,650.00 | $1,875.00 | $1,875.00 | $500.00 | $1,075.51 |
| 12 | RE-optimize TR sig sys 1 (Z0033044) | EACH | 1 | $900.00 | $950.40 | $864.00 | $870.00 | $865.00 | $864.00 |
| 13 | Earth excavation (20200100) | CY | 150 | $92.00 | $60.00 | $60.00 | $75.00 | $55.00 | $129.76 |
| 14 | Geotech fab F/GR stab (21001000) | SY | 221 | $2.75 | $5.00 | $3.50 | $3.10 | $9.00 | $2.00 |
| 15 | Topsoil F & P 4 (21101615) | SY | 67 | $8.50 | $55.00 | $30.00 | $30.00 | $5.00 | $8.60 |
| 16 | Sodding salt tolerant (25200110) | SY | 67 | $33.00 | $55.00 | $45.00 | $86.00 | $120.00 | $34.42 |
| 17 | Supple watering (25200200) | UNIT | 0.67 | $200.00 | $270.60 | $1,000.00 | $60.00 | $500.00 | $215.10 |
| 18 | Agg subgrade improve (30300001) | CY | 19 | $130.00 | $100.00 | $100.00 | $58.00 | $120.00 | $60.00 |
| 19 | Agg subgrade impr 12 (30300112) | SY | 221 | $40.00 | $25.00 | $26.00 | $46.00 | $43.00 | $59.30 |
| 20 | Bit matls tack CT (40600290) | LB | 15,124 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 21 | Long joint sealant (40600370) | LF | 8,642 | $3.20 | $3.18 | $3.50 | $3.00 | $3.10 | $3.12 |
| 22 | Mix CR JTS flangewys (40600400) | TON | 34 | $50.00 | $0.01 | $0.01 | $650.00 | $300.00 | $400.00 |
| 23 | HMA surf rem butt JT (40600982) | SY | 149 | $0.01 | $0.01 | $0.01 | $20.00 | $20.00 | $44.93 |
| 24 | P HMA BC IL-4.75 N50 (40603200) | TON | 919 | $110.00 | $102.00 | $105.00 | $95.00 | $96.50 | $129.73 |
| 25 | HMA SC IL-9.5 D N50 (40604060) | TON | 47 | $169.00 | $105.00 | $175.00 | $250.00 | $200.00 | $179.71 |
| 26 | P HMA SC SMA 9.5 F N80 (40605026) | TON | 2,183 | $121.00 | $115.00 | $120.00 | $123.00 | $115.00 | $133.84 |
| 27 | Protective coat (42001300) | SY | 788 | $1.00 | $1.00 | $0.01 | $0.10 | $1.00 | $0.01 |
| 28 | PC conc sidewalk 5 (42400200) | SF | 1,464 | $9.50 | $9.00 | $13.00 | $12.10 | $12.20 | $14.95 |
| 29 | PC conc sidewalk 7 (42400400) | SF | 528 | $13.00 | $12.00 | $17.00 | $13.10 | $15.00 | $16.19 |
| 30 | Detectable warnings (42400800) | SF | 175 | $21.00 | $40.00 | $20.00 | $45.00 | $43.00 | $43.30 |
| 31 | Pavement rem (44000100) | SY | 202 | $30.00 | $20.00 | $25.00 | $27.00 | $68.00 | $33.00 |
| 32 | HMA surf rem 2 (44000157) | SY | 411 | $9.00 | $3.00 | $11.00 | $13.00 | $18.00 | $4.89 |
| 33 | HMA surf rem 2 1/2 (44000159) | SY | 22,269 | $3.00 | $2.30 | $3.00 | $4.30 | $2.05 | $4.91 |
| 34 | Sidewalk rem (44000600) | SF | 1,464 | $4.00 | $3.00 | $2.50 | $4.10 | $3.55 | $3.49 |
| 35 | CL D patch T2 10 (44201765) | SY | 10 | $197.00 | $170.00 | $150.00 | $200.00 | $140.00 | $130.00 |
| 36 | CL D patch T3 10 (44201769) | SY | 17 | $150.00 | $170.00 | $125.00 | $140.00 | $135.00 | $130.00 |
| 37 | CL D patch T4 10 (44201771) | SY | 216 | $80.00 | $112.00 | $90.00 | $95.00 | $125.00 | $128.00 |
| 38 | HMA shoulders 8 (48203029) | SY | 247 | $75.00 | $47.00 | $60.00 | $67.00 | $57.00 | $94.12 |
| 39 | FR & lids adjust (60300305) | EACH | 4 | $575.00 | $900.00 | $500.00 | $820.00 | $400.00 | $1,043.42 |
| 40 | Pipe culv cleaned 12 (60920012) | LF | 90 | $31.00 | $13.20 | $12.00 | $12.00 | $50.00 | $26.89 |
| 41 | Non SPL waste disposl (66900200) | CY | 145 | $65.00 | $90.00 | $85.00 | $95.00 | $200.00 | $85.00 |
| 42 | Soil disposal analy (66900530) | EACH | 2 | $1,500.00 | $1,522.50 | $1,450.00 | $965.00 | $965.00 | $1,435.40 |
| 43 | Reg sub P-const plan (66901001) | LS | 1 | $3,200.00 | $3,255.00 | $3,100.00 | $5,000.00 | $5,000.00 | $3,422.87 |
| 44 | Reg sub F con report (66901003) | LS | 1 | $1,250.00 | $1,260.00 | $1,200.00 | $500.00 | $500.00 | $1,324.98 |
| 45 | Reg sub mon (66901006) | CAL DAY | 4 | $700.00 | $714.00 | $680.00 | $715.00 | $715.00 | $750.82 |
| 46 | Mobilization (67100100) | LS | 1 | $58,000 | $39,000 | $60,000 | $35,000 | $55,000 | $71,250 |
| 47 | Traf cont-prot 701306 (70100460) | LS | 1 | $1.00 | $0.01 | $1,025.00 | $1.00 | $1.00 | $1,217.14 |
| 48 | Traf cont-prot 701336 (70100600) | LS | 1 | $750.00 | $0.01 | $1,025.00 | $700.00 | $1.00 | $1,217.14 |
| 49 | TR cont & prot 701501 (70102620) | LS | 1 | $12,000 | $0.01 | $1,025.00 | $900.00 | $1.00 | $1,217.14 |
| 50 | TR cont & prot 701502 (70102622) | LS | 1 | $2,000.00 | $0.01 | $1,025.00 | $2,400.00 | $1.00 | $1,217.14 |
| 51 | TR cont & prot 701606 (70102625) | LS | 1 | $4,000.00 | $57,725 | $1,025.00 | $1.00 | $8,500.00 | $1,217.14 |
| 52 | TR cont & prot 701611 (70102634) | LS | 1 | $2,000.00 | $0.01 | $1,025.00 | $3,900.00 | $1.00 | $1,217.14 |
| 53 | TR cont & prot 701701 (70102635) | LS | 1 | $1.00 | $0.01 | $1,025.00 | $1.00 | $1.00 | $1,217.14 |
| 54 | TR cont & prot 701801 (70102640) | LS | 1 | $900.00 | $0.01 | $1,025.00 | $900.00 | $320.00 | $1,217.14 |
| 55 | Short term pavt mking (70300100) | LF | 17,342 | $0.01 | $0.01 | $0.01 | $0.01 | $1.50 | $1.50 |
| 56 | SHRT TRM pavt MK rem (70300150) | SF | 1,446 | $0.01 | $0.01 | $0.01 | $0.01 | $2.50 | $1.00 |
| 57 | Temp PVT MK LTR & sym paint (70300211) | SF | 1,000 | $0.01 | $0.01 | $1.75 | $0.01 | $2.00 | $0.01 |
| 58 | Temp PVT MK line 4 - paint (70300221) | LF | 20,249 | $0.01 | $0.01 | $0.35 | $0.01 | $0.35 | $0.01 |
| 59 | Temp PVT MK line 6 - paint (70300241) | LF | 4,292 | $0.01 | $0.01 | $0.53 | $0.01 | $0.33 | $0.01 |
| 60 | Temp PVT MK line 8 - paint (70300251) | LF | 512 | $0.01 | $0.01 | $0.70 | $0.01 | $0.33 | $0.01 |
| 61 | Temp PVT MK line 12 - paint (70300261) | LF | 2,692 | $0.01 | $0.01 | $1.06 | $0.01 | $1.00 | $0.01 |
| 62 | Temp PVT MK line 24 - paint (70300281) | LF | 598 | $0.01 | $0.01 | $1.60 | $0.01 | $2.00 | $0.01 |
| 63 | Temp PVT MK L4 T4 tape (70307120) | LF | 4,335 | $0.01 | $0.01 | $0.01 | $1.00 | $2.60 | $0.01 |
| 64 | THPL PVT MK LTR & sym (78000100) | SF | 500 | $6.00 | $6.33 | $5.75 | $5.75 | $5.75 | $5.75 |
| 65 | THPL PVT MK line 4 (78000200) | LF | 10,125 | $0.75 | $0.83 | $0.75 | $0.75 | $0.75 | $0.75 |
| 66 | THPL PVT MK line 6 (78000400) | LF | 2,146 | $0.90 | $0.94 | $0.85 | $0.85 | $0.85 | $0.85 |
| 67 | THPL PVT MK line 8 (78000500) | LF | 256 | $2.00 | $2.15 | $1.95 | $1.95 | $1.95 | $1.95 |
| 68 | THPL PVT MK line 12 (78000600) | LF | 1,346 | $3.00 | $3.08 | $2.80 | $2.80 | $2.80 | $2.80 |
| 69 | THPL PVT MK line 24 (78000650) | LF | 299 | $6.00 | $6.33 | $5.75 | $5.75 | $5.75 | $5.75 |
| 70 | Raised refl pavt MKR (78100100) | EACH | 135 | $59.00 | $60.50 | $65.00 | $55.00 | $45.00 | $55.00 |
| 71 | Raised ref PVT MK rem (78300200) | EACH | 135 | $0.01 | $10.00 | $0.01 | $19.00 | $10.00 | $10.00 |
| 72 | Undrgrd C galvs 2 (81028200) | LF | 279 | $48.00 | $51.66 | $46.96 | $47.00 | $47.00 | $50.51 |
| 73 | HD handhole (81400200) | EACH | 5 | $5,700.00 | $6,200.16 | $5,636.51 | $5,700.00 | $5,650.00 | $6,062.12 |
| 74 | Main EX TR sig instal (85000200) | EACH | 2 | $1,950.00 | $2,022.49 | $1,838.63 | $1,900.00 | $1,840.00 | $1,977.46 |
| 75 | Elcbl C signal 14 2C (87301215) | LF | 452 | $4.50 | $4.75 | $4.32 | $4.35 | $4.35 | $4.65 |
| 76 | Elcbl C signal 14 3C (87301225) | LF | 460 | $4.60 | $4.95 | $4.50 | $4.50 | $4.50 | $4.84 |
| 77 | Elcbl C lead 14 1PR (87301305) | LF | 848 | $4.60 | $4.95 | $4.50 | $4.50 | $4.80 | $4.84 |
| 78 | Elcbl C egrdc 6 1C (87301900) | LF | 35 | $5.40 | $5.53 | $5.03 | $5.10 | $5.05 | $5.41 |
| 79 | Drill EX handhole (87900200) | EACH | 6 | $450.00 | $485.06 | $440.96 | $450.00 | $440.00 | $474.26 |
| 80 | Ped SH LED 1F BM CDT (88102717) | EACH | 2 | $670.00 | $686.38 | $623.98 | $625.00 | $625.00 | $671.10 |
| 81 | Det loop T1 (88600100) | LF | 590 | $21.50 | $23.19 | $21.08 | $21.20 | $21.20 | $22.67 |
| 82 | Mod EX contr (89502200) | EACH | 1 | $1,250.00 | $1,299.16 | $1,181.05 | $1,250.00 | $1,200.00 | $1,270.23 |
| 83 | Rebuild EX handhole (89502376) | EACH | 1 | $2,600.00 | $2,733.90 | $2,485.36 | $2,500.00 | $2,500.00 | $2,673.03 |
| 84 | Remov EX handhole (89502380) | EACH | 5 | $1,350.00 | $1,433.09 | $1,302.81 | $1,320.00 | $1,305.00 | $1,401.18 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.