Section 2025-2106-RS. Let by Illinois DOT on April 24, 2026, Cook, District 01. 5 bids received; low bid $4,164,775 by K-Five Construction Corporation.
- Owner
- Illinois DOT
- Letting
- 24 APR 2026
- Pay items
- 122
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | K-Five Construction Corporation | $4,164,775 | Low |
| 2 | Gallagher Asphalt Corporation | $4,239,696 | +2.0% |
| 3 | P. T. Ferro Construction Co. | $4,531,713 | +9.0% |
| 4 | Builders Paving, LLC | $4,573,898 | +10% |
| 5 | Austin Tyler Construction, Inc. | $5,419,276 | +30% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. K-Five Construction Corporation | 2. Gallagher Asphalt Corporation | 3. P. T. Ferro Construction Co. | 4. Builders Paving, LLC | 5. Austin Tyler Construction, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Tree care (K0026700) | EACH | 23 | $100.00 | $1,300.00 | $100.00 | $1,200.00 | $177.37 |
| 2 | Weed control teasel (K0029624) | GAL | 0.50 | $900.00 | $955.37 | $900.00 | $380.00 | $4,434.17 |
| 3 | Mulch placement 4 (K0036120) | SY | 250 | $4.00 | $4.25 | $4.00 | $12.00 | $11.09 |
| 4 | Constructn layout SPL (X0320050) | LS | 1 | $2,500.00 | $1,300.00 | $20,000 | $9,500.00 | $11,085 |
| 5 | Weed cont basal TRTMT (X0325222) | GAL | 12 | $900.00 | $955.37 | $900.00 | $460.00 | $1,457.73 |
| 6 | Weed CTRL NTV LSCP EN (X0327120) | ACRE | 5.90 | $900.00 | $955.37 | $900.00 | $1,500.00 | $2,294.68 |
| 7 | Ped signal post 10 FT (X1400367) | EACH | 1 | $1,316.21 | $1,397.19 | $1,316.21 | $1,400.00 | $1,459.07 |
| 8 | Tree remov acres SPL (X2010350) | ACRE | 5.36 | $6,000.00 | $6,500.00 | $6,000.00 | $6,500.00 | $21,949 |
| 9 | Selective clearing (X2010516) | UNIT | 19.70 | $350.00 | $360.00 | $350.00 | $370.00 | $543.19 |
| 10 | Grading & shap SHLDRS (X2020110) | UNIT | 120 | $136.00 | $340.00 | $0.01 | $135.00 | $176.24 |
| 11 | Prun safety/equip CLR (X2100002) | UNIT | 4 | $500.00 | $540.00 | $500.00 | $550.00 | $1,607.39 |
| 12 | Temporary ramp SPL (X4060995) | SY | 560 | $0.01 | $30.00 | $0.01 | $38.00 | $16.63 |
| 13 | CC&G RMVL repl < = 10 (X4400501) | LF | 100 | $75.00 | $85.00 | $90.00 | $83.00 | $92.71 |
| 14 | CC&G RMVL repl > 10FT (X4400503) | LF | 435 | $65.00 | $58.00 | $70.00 | $74.00 | $58.71 |
| 15 | SS cleaned 12 (X5537800) | LF | 375 | $1.00 | $1.00 | $1.00 | $4.00 | $11.09 |
| 16 | FR & lids adjust SPL (X6030310) | EACH | 5 | $2,000.00 | $830.00 | $1,500.00 | $2,700.00 | $1,676.59 |
| 17 | Vert adj of guardrail (X6330900) | LF | 125 | $18.00 | $19.00 | $18.00 | $20.00 | $19.95 |
| 18 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 12 | $3,500.00 | $500.00 | $2,500.00 | $4,000.00 | $3,325.63 |
| 19 | Temp info signing (X7200061) | SF | 104 | $28.85 | $26.00 | $25.00 | $27.00 | $19.95 |
| 20 | Accessible ped signal (X8760200) | EACH | 2 | $3,954.65 | $4,000.00 | $3,954.65 | $4,200.00 | $4,383.89 |
| 21 | Conc FDN TY A 12D (X8780012) | LF | 4 | $405.16 | $430.00 | $405.16 | $420.00 | $449.14 |
| 22 | Det loop repl (X8860105) | LF | 35 | $27.44 | $29.00 | $27.44 | $30.00 | $30.42 |
| 23 | Construction layout (Z0013798) | LS | 1 | $20,700 | $8,000.00 | $50,000 | $20,000 | $11,085 |
| 24 | Drainage STR cleaned (Z0018500) | EACH | 25 | $350.00 | $370.00 | $350.00 | $350.00 | $415.70 |
| 25 | RE-optimize TR sig sys 1 (Z0033044) | EACH | 4 | $792.00 | $800.00 | $792.00 | $800.00 | $877.97 |
| 26 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 | $0.80 | $0.80 | $0.80 |
| 27 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 |
| 28 | Tree remov 6-15 (20100110) | UNIT | 161 | $20.00 | $21.00 | $20.00 | $21.00 | $46.56 |
| 29 | Tree remov over 15 (20100210) | UNIT | 69 | $25.00 | $27.00 | $25.00 | $26.00 | $69.84 |
| 30 | Tree prun over 10 (20101350) | EACH | 5 | $150.00 | $160.00 | $150.00 | $170.00 | $399.08 |
| 31 | Earth excavation (20200100) | CY | 4,325 | $50.00 | $120.00 | $52.00 | $89.00 | $52.88 |
| 32 | Rem & disp uns matl (20201200) | CY | 255 | $76.93 | $50.00 | $62.00 | $50.00 | $51.92 |
| 33 | Geotech fab F/GR stab (21001000) | SY | 775 | $3.25 | $1.00 | $3.50 | $3.00 | $5.54 |
| 34 | Topsoil F & P 4 (21101615) | SY | 290 | $6.00 | $6.00 | $6.00 | $4.00 | $13.86 |
| 35 | Grading & shap ditch (21400100) | LF | 250 | $31.16 | $5.40 | $35.00 | $18.00 | $45.34 |
| 36 | Seeding CL 2A (25000210) | ACRE | 0.25 | $3,800.00 | $4,000.00 | $3,800.00 | $2,800.00 | $4,877.58 |
| 37 | Interseed CL 1B (25003115) | ACRE | 0.50 | $3,000.00 | $3,100.00 | $3,000.00 | $2,600.00 | $4,301.14 |
| 38 | Interseed CL 4A (25003312) | ACRE | 5.90 | $3,500.00 | $3,700.00 | $3,500.00 | $1,000.00 | $3,458.65 |
| 39 | Erosion contr blanket (25100630) | SY | 150 | $5.00 | $5.30 | $5.00 | $11.00 | $2.44 |
| 40 | Sodding salt tolerant (25200110) | SY | 290 | $11.00 | $11.60 | $11.00 | $25.00 | $32.15 |
| 41 | Perimeter eros bar (28000400) | LF | 450 | $3.00 | $3.10 | $3.00 | $5.50 | $4.99 |
| 42 | Agg subgrade improve (30300001) | CY | 255 | $69.65 | $50.00 | $100.00 | $40.00 | $68.55 |
| 43 | Agg subgrade impr 12 (30300112) | SY | 7,710 | $35.36 | $26.00 | $23.00 | $34.00 | $40.18 |
| 44 | Bit matls PR CT (40600275) | LB | 17,350 | $0.01 | $0.01 | $0.01 | $0.01 | $0.39 |
| 45 | Bit matls tack CT (40600290) | LB | 42,700 | $0.01 | $1.10 | $0.01 | $0.01 | $0.39 |
| 46 | Long joint sealant (40600370) | LF | 30,550 | $3.00 | $3.50 | $3.40 | $3.70 | $3.90 |
| 47 | Mix CR JTS flangewys (40600400) | TON | 95 | $50.00 | $200.00 | $100.00 | $830.00 | $341.40 |
| 48 | HMA surf rem butt JT (40600982) | SY | 405 | $0.01 | $31.00 | $0.01 | $18.00 | $23.30 |
| 49 | HMA BC IL-9.5 N70 (40602985) | TON | 6,620 | $82.00 | $100.00 | $97.00 | $83.00 | $91.08 |
| 50 | HMA SC IL-9.5 D N70 (40604062) | TON | 6,200 | $82.00 | $105.00 | $98.00 | $84.00 | $92.15 |
| 51 | Protective coat (42001300) | SY | 260 | $3.00 | $0.01 | $0.01 | $5.00 | $5.54 |
| 52 | PC conc sidewalk 5 (42400200) | SF | 905 | $15.00 | $8.00 | $14.00 | $17.00 | $13.24 |
| 53 | Detectable warnings (42400800) | SF | 100 | $55.00 | $30.00 | $25.00 | $55.00 | $44.34 |
| 54 | HMA surf rem 1 3/4 (44000156) | SY | 4,170 | $2.40 | $4.50 | $3.00 | $7.00 | $4.09 |
| 55 | HMA surf rem 3 3/4 (44000164) | SY | 59,090 | $5.00 | $5.00 | $5.50 | $8.40 | $5.50 |
| 56 | Sidewalk rem (44000600) | SF | 700 | $5.00 | $3.90 | $4.00 | $3.00 | $2.75 |
| 57 | CL D patch T2 14 (44201815) | SY | 100 | $45.00 | $200.00 | $175.00 | $46.00 | $187.42 |
| 58 | CL D patch T3 14 (44201819) | SY | 235 | $45.00 | $155.00 | $155.00 | $46.00 | $182.03 |
| 59 | CL D patch T4 14 (44201821) | SY | 1,000 | $45.00 | $130.00 | $100.00 | $46.00 | $174.08 |
| 60 | CL D patch T2 17 (44201851) | SY | 100 | $55.00 | $225.00 | $215.00 | $55.00 | $227.14 |
| 61 | CL D patch T3 17 (44201855) | SY | 150 | $55.00 | $165.00 | $190.00 | $55.00 | $221.39 |
| 62 | CL D patch T4 17 (44201857) | SY | 200 | $55.00 | $140.00 | $155.00 | $55.00 | $216.36 |
| 63 | JT CR RT PCC pav/SHLD (45200100) | LF | 5,975 | $0.15 | $0.15 | $0.15 | $0.25 | $2.44 |
| 64 | JT or crack filling (45200300) | LB | 1,710 | $6.92 | $7.00 | $6.92 | $7.00 | $3.59 |
| 65 | Aggregate SHLDS B (48101200) | TON | 785 | $50.00 | $50.00 | $39.00 | $50.00 | $47.84 |
| 66 | HMA shoulders 8 (48203029) | SY | 7,710 | $40.00 | $44.00 | $46.00 | $43.00 | $42.30 |
| 67 | Man adjust (60255500) | EACH | 3 | $1,200.00 | $340.00 | $650.00 | $700.00 | $438.55 |
| 68 | FR & grates adjust (60300105) | EACH | 7 | $1,200.00 | $360.00 | $500.00 | $700.00 | $438.55 |
| 69 | SPBGR TY A 6FT posts (63000001) | LF | 1,525 | $33.00 | $35.00 | $33.00 | $34.00 | $36.58 |
| 70 | TR bar TRM T1 SPL tan (63100167) | EACH | 19 | $3,720.00 | $3,900.00 | $3,720.00 | $4,000.00 | $4,123.78 |
| 71 | Guardrail remov (63200310) | LF | 2,475 | $6.00 | $6.30 | $6.00 | $7.00 | $6.65 |
| 72 | Rem RE-E SPBGR TY A (63301210) | LF | 125 | $24.00 | $25.00 | $24.00 | $25.00 | $26.61 |
| 73 | Non SPL waste disposl (66900200) | CY | 4,325 | $90.70 | $0.01 | $83.00 | $93.00 | $122.88 |
| 74 | Soil disposal analy (66900530) | EACH | 10 | $1,450.00 | $1,500.00 | $1,450.00 | $945.00 | $1,047.57 |
| 75 | Reg sub P-const plan (66901001) | LS | 1 | $3,100.00 | $3,200.00 | $3,100.00 | $6,900.00 | $7,648.94 |
| 76 | Reg sub F con report (66901003) | LS | 1 | $1,200.00 | $1,200.00 | $1,200.00 | $500.00 | $554.27 |
| 77 | Reg sub mon (66901006) | CAL DAY | 30 | $680.00 | $720.00 | $680.00 | $715.00 | $792.61 |
| 78 | Mobilization (67100100) | LS | 1 | $249,000 | $190,000 | $265,000 | $270,000 | $290,000 |
| 79 | Traf cont-prot 701201 (70100450) | LS | 1 | $2,800.00 | $2,000.00 | $2,000.00 | $2,500.00 | $1.11 |
| 80 | Traf cont-prot 701306 (70100460) | LS | 1 | $100.00 | $100.00 | $300,000 | $228.65 | $1.11 |
| 81 | Traf cont-prot 701326 (70100500) | LS | 1 | $100.00 | $100.00 | $100.00 | $200.00 | $1.11 |
| 82 | TR cont & prot 701501 (70102620) | LS | 1 | $270,625 | $9,000.00 | $9,000.00 | $55,000 | $22,171 |
| 83 | TR cont & prot 701502 (70102622) | LS | 1 | $100.00 | $100.00 | $100.00 | $200.00 | $1.11 |
| 84 | TR cont & prot 701701 (70102635) | LS | 1 | $2,000.00 | $2,000.00 | $2,000.00 | $2,500.00 | $1.11 |
| 85 | TR cont & prot 701801 (70102640) | LS | 1 | $2,000.00 | $2,000.00 | $2,000.00 | $2,500.00 | $16,628 |
| 86 | TR cont surveillance (70103815) | CAL DAY | 10 | $250.00 | $260.00 | $250.00 | $250.00 | $166.28 |
| 87 | Short term pavt mking (70300100) | LF | 261,680 | $0.01 | $0.01 | $0.01 | $0.01 | $1.11 |
| 88 | SHRT TRM pavt MK rem (70300150) | SF | 21,810 | $0.01 | $0.01 | $0.01 | $0.01 | $1.11 |
| 89 | Temp PVT MK LTR & sym paint (70300211) | SF | 2,850 | $0.01 | $0.01 | $0.01 | $0.01 | $1.83 |
| 90 | Temp PVT MK line 4 - paint (70300221) | LF | 196,260 | $0.01 | $0.01 | $0.01 | $0.01 | $0.31 |
| 91 | Temp PVT MK line 6 - paint (70300241) | LF | 18,240 | $0.01 | $0.01 | $0.01 | $0.01 | $0.45 |
| 92 | Temp PVT MK line 8 - paint (70300251) | LF | 2,835 | $0.01 | $0.01 | $0.01 | $0.01 | $0.61 |
| 93 | Temp PVT MK line 12 - paint (70300261) | LF | 9,150 | $0.01 | $0.01 | $0.01 | $0.01 | $0.91 |
| 94 | Temp PVT MK line 24 - paint (70300281) | LF | 1,665 | $0.01 | $0.01 | $0.01 | $0.01 | $1.83 |
| 95 | Temp PVT MK L4 T4 tape (70307120) | LF | 65,420 | $0.01 | $0.01 | $0.01 | $0.01 | $2.22 |
| 96 | Terminal marker - DA (72501000) | EACH | 19 | $50.00 | $70.00 | $50.00 | $60.00 | $55.43 |
| 97 | THPL PVT MK LTR & sym (78000100) | SF | 950 | $5.00 | $5.30 | $5.00 | $5.00 | $5.82 |
| 98 | THPL PVT MK line 4 (78000200) | LF | 65,420 | $0.55 | $0.60 | $0.55 | $0.55 | $0.78 |
| 99 | THPL PVT MK line 6 (78000400) | LF | 6,080 | $1.00 | $1.05 | $1.00 | $1.00 | $1.33 |
| 100 | THPL PVT MK line 8 (78000500) | LF | 945 | $1.50 | $1.55 | $1.50 | $1.50 | $1.61 |
| 101 | THPL PVT MK line 12 (78000600) | LF | 3,050 | $2.50 | $2.60 | $2.50 | $2.50 | $2.49 |
| 102 | THPL PVT MK line 24 (78000650) | LF | 555 | $5.00 | $5.30 | $5.00 | $5.00 | $5.82 |
| 103 | Mod ureth PM LTR-sym (78009000) | SF | 185 | $8.00 | $8.40 | $8.00 | $8.00 | $6.65 |
| 104 | Mod ureth PM line 4 (78009004) | LF | 3,700 | $0.72 | $0.75 | $0.72 | $0.72 | $1.00 |
| 105 | Mod ureth PM line 6 (78009006) | LF | 1,125 | $1.20 | $1.25 | $1.20 | $1.20 | $1.61 |
| 106 | Mod ureth PM line 12 (78009012) | LF | 495 | $4.00 | $4.20 | $4.00 | $4.00 | $3.05 |
| 107 | Mod ureth PM line 24 (78009024) | LF | 85 | $8.00 | $8.40 | $8.00 | $8.00 | $6.65 |
| 108 | Raised refl pavt MKR (78100100) | EACH | 950 | $40.00 | $42.00 | $40.00 | $40.00 | $46.28 |
| 109 | Grdrail ref type A (78200005) | EACH | 40 | $15.00 | $15.50 | $15.00 | $17.00 | $16.63 |
| 110 | Raised ref PVT MK rem (78300200) | EACH | 950 | $15.00 | $0.01 | $0.01 | $22.00 | $16.63 |
| 111 | Undrgrd C galvs 2 (81028200) | LF | 568 | $49.27 | $52.00 | $49.27 | $50.00 | $54.62 |
| 112 | HD handhole (81400200) | EACH | 9 | $5,734.19 | $6,000.00 | $5,734.19 | $5,800.00 | $6,356.59 |
| 113 | Main EX TR sig instal (85000200) | EACH | 4 | $3,926.63 | $4,100.00 | $3,926.63 | $4,000.00 | $4,352.83 |
| 114 | Elcbl C signal 14 2C (87301215) | LF | 205 | $8.86 | $9.00 | $8.86 | $9.00 | $9.82 |
| 115 | Elcbl C signal 14 3C (87301225) | LF | 70 | $9.07 | $9.20 | $9.07 | $9.50 | $10.05 |
| 116 | Elcbl C lead 14 1PR (87301305) | LF | 1,469 | $9.05 | $9.20 | $9.05 | $9.50 | $10.03 |
| 117 | Elcbl C egrdc 6 1C (87301900) | LF | 55 | $9.71 | $10.00 | $9.71 | $10.00 | $10.76 |
| 118 | Drill EX handhole (87900200) | EACH | 10 | $425.32 | $450.00 | $425.32 | $450.00 | $471.48 |
| 119 | Det loop T1 (88600100) | LF | 2,857 | $27.44 | $29.00 | $27.44 | $30.00 | $30.42 |
| 120 | Rem elcbl FR con (89502300) | LF | 1,720 | $0.14 | $0.15 | $0.14 | $0.50 | $0.16 |
| 121 | Remov EX TS equip (89502375) | EACH | 4 | $138.01 | $145.00 | $138.01 | $160.00 | $152.99 |
| 122 | Remov EX handhole (89502380) | EACH | 9 | $1,299.98 | $1,350.00 | $1,299.98 | $1,400.00 | $1,441.08 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 24, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.