IDOT contract 85767 bid tabulation
East Moline, section 22-00159-00-PV. Let by Illinois DOT on January 17, 2025, Rock Island, District 02. 5 bids received; low bid $835,827 by McCarthy Improvement Company.
- Owner
- Illinois DOT
- Letting
- 17 JAN 2025
- Pay items
- 52
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | McCarthy Improvement Company | $835,827 | Low |
| 2 | Valley Construction Co. | $867,531 | +4.0% |
| 3 | Phoenix Corporation of the Quad Cities | $968,399 | +16% |
| 4 | Centennial Contractors of the Quad Cities, Inc. | $1,034,880 | +24% |
| 5 | Langman Construction, Inc. | $1,097,500 | +31% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. McCarthy Improvement Company | 2. Valley Construction Co. | 3. Phoenix Corporation of the Quad Cities | 4. Centennial Contractors of the Quad Cities, Inc. | 5. Langman Construction, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | T-acer miy mor 2 (A2000316) | EACH | 17 | $1,083.00 | $490.00 | $1,050.00 | $925.00 | $1,000.00 |
| 2 | T-ginkgo bil AG 2 (A2004512) | EACH | 12 | $1,083.00 | $490.00 | $1,250.00 | $1,060.00 | $1,000.00 |
| 3 | T-nyssa sylvat 2 (A2005516) | EACH | 15 | $1,300.00 | $500.00 | $1,125.00 | $1,020.00 | $1,200.00 |
| 4 | T-zelkova ser GV 2 (A3005238) | EACH | 12 | $1,300.00 | $500.00 | $1,050.00 | $960.00 | $1,200.00 |
| 5 | Wayfinding sign SP (X0327880) | LS | 1 | $7,750.00 | $18,325 | $13,700 | $15,640 | $10,000 |
| 6 | Conc paver pavement (X0327978) | SY | 127 | $162.50 | $184.00 | $575.00 | $405.00 | $270.00 |
| 7 | Trash receptacles (X0327997) | EACH | 3 | $3,150.00 | $3,500.00 | $4,050.00 | $3,450.00 | $5,000.00 |
| 8 | R R FL beacon A comp (X1400326) | EACH | 4 | $11,015 | $10,172 | $13,200 | $11,698 | $11,500 |
| 9 | Cable SPL (X1400381) | LF | 830 | $18.00 | $16.50 | $27.50 | $19.00 | $0.01 |
| 10 | Seeding CL 2A SPL (X2501020) | ACRE | 2 | $7,580.00 | $5,750.00 | $9,550.00 | $8,250.00 | $7,000.00 |
| 11 | Inlets SPL N1 (X6024242) | EACH | 1 | $6,590.00 | $7,150.00 | $9,825.00 | $5,000.00 | $5,000.00 |
| 12 | Inlets SPL N2 (X6024244) | EACH | 2 | $6,690.00 | $4,000.00 | $6,750.00 | $5,000.00 | $5,500.00 |
| 13 | Comb CC&G TB SPL aep (X6060068) | LF | 170 | $50.90 | $100.00 | $80.00 | $60.00 | $55.00 |
| 14 | Traf cont & prot SPL (X7010216) | LS | 1 | $14,946 | $13,800 | $17,300 | $14,000 | $85,800 |
| 15 | Benches (Z0003850) | EACH | 6 | $161.50 | $4,750.00 | $5,800.00 | $4,800.00 | $6,000.00 |
| 16 | Construction layout (Z0013798) | LS | 1 | $7,580.00 | $11,850 | $21,100 | $8,500.00 | $3,000.00 |
| 17 | Trench backfill (20800150) | CY | 42 | $66.50 | $34.00 | $91.00 | $55.00 | $71.00 |
| 18 | Topsoil exc & plac (21101505) | CY | 760 | $12.20 | $27.00 | $35.50 | $50.00 | $22.00 |
| 19 | Topsoil F & P 12 (21101645) | SY | 674 | $13.00 | $22.00 | $16.50 | $26.00 | $12.00 |
| 20 | Temp eros contr seed (28000250) | LB | 1,530 | $2.15 | $2.00 | $3.00 | $2.25 | $2.00 |
| 21 | Perimeter eros bar (28000400) | LF | 1,962 | $2.15 | $2.25 | $5.00 | $2.50 | $2.00 |
| 22 | Inlet & pipe protect (28000500) | EACH | 3 | $153.00 | $195.00 | $325.00 | $250.00 | $150.00 |
| 23 | Sub gran mat B 4 (31101200) | SY | 3,897 | $10.90 | $13.00 | $13.00 | $10.00 | $18.60 |
| 24 | Preparation of base (35800100) | SY | 122 | $9.00 | $7.00 | $10.50 | $10.00 | $10.00 |
| 25 | Agg base repair (35800200) | TON | 3 | $369.00 | $125.00 | $86.00 | $50.00 | $65.00 |
| 26 | Protective coat (42001300) | SY | 4,446 | $1.20 | $3.00 | $3.75 | $0.50 | $0.01 |
| 27 | PCC driveway pavt 8 (42300400) | SY | 549 | $56.00 | $90.00 | $111.50 | $90.00 | $95.00 |
| 28 | PC conc sidewalk 4 (42400100) | SF | 9,053 | $9.04 | $8.50 | $6.50 | $12.00 | $11.50 |
| 29 | PC conc sidewalk 5 (42400200) | SF | 25,926 | $8.80 | $8.75 | $7.50 | $13.00 | $12.00 |
| 30 | Detectable warnings (42400800) | SF | 362 | $36.50 | $24.50 | $33.50 | $50.00 | $60.00 |
| 31 | Drive pavement rem (44000200) | SY | 543 | $15.50 | $15.00 | $13.25 | $20.00 | $15.00 |
| 32 | Curb rem (44000300) | LF | 160 | $40.00 | $16.50 | $28.00 | $15.00 | $5.00 |
| 33 | Sidewalk rem (44000600) | SF | 1,014 | $4.50 | $1.50 | $3.50 | $2.50 | $2.00 |
| 34 | CL B patch T4 7 (44200926) | SY | 152 | $193.00 | $135.00 | $124.00 | $120.00 | $208.00 |
| 35 | Storm sew CL A 1 12 (550A0050) | LF | 52 | $97.50 | $172.00 | $98.00 | $100.00 | $132.00 |
| 36 | Man TA 4 dia T1F CL (60218400) | EACH | 1 | $5,050.00 | $5,200.00 | $5,850.00 | $4,500.00 | $4,000.00 |
| 37 | Man adjust (60255500) | EACH | 3 | $979.00 | $1,250.00 | $1,175.00 | $1,000.00 | $700.00 |
| 38 | Valve box adj (60266600) | EACH | 8 | $630.00 | $850.00 | $550.00 | $250.00 | $300.00 |
| 39 | Conc curb TB (60600605) | LF | 36 | $55.00 | $65.50 | $92.50 | $60.00 | $55.00 |
| 40 | Comb CC&G TB6.18 aep (60604500) | LF | 26 | $71.50 | $83.00 | $109.00 | $60.00 | $120.00 |
| 41 | Non SPL waste disposl (66900200) | CY | 51 | $65.00 | $35.50 | $120.00 | $45.00 | $40.00 |
| 42 | Soil disposal analy (66900530) | EACH | 2 | $1,565.00 | $1,800.00 | $2,250.00 | $1,668.00 | $1,000.00 |
| 43 | Reg sub P-const plan (66901001) | LS | 1 | $3,760.00 | $2,350.00 | $3,000.00 | $4,025.00 | $1,000.00 |
| 44 | Reg sub F con report (66901003) | LS | 1 | $950.00 | $2,400.00 | $3,000.00 | $1,050.00 | $1,000.00 |
| 45 | Mobilization (67100100) | LS | 1 | $46,122 | $50,000 | $22,300 | $25,000 | $60,000 |
| 46 | Sign panel T1 (72000100) | SF | 236 | $30.30 | $28.00 | $35.00 | $30.00 | $26.00 |
| 47 | Reloc sin pan assy TA (72400500) | EACH | 2 | $543.00 | $500.00 | $625.00 | $575.00 | $500.00 |
| 48 | Teles STL sin support (72800100) | LF | 334 | $30.30 | $28.00 | $35.00 | $28.00 | $24.00 |
| 49 | Epoxy PVT MK LTR-sym (78005100) | SF | 96 | $15.20 | $14.00 | $17.50 | $18.00 | $14.00 |
| 50 | Epoxy PVT MK line 12 (78005150) | LF | 1,828 | $6.95 | $6.40 | $8.00 | $4.00 | $6.40 |
| 51 | Epoxy PVT MK line 24 (78005180) | LF | 353 | $13.90 | $12.85 | $16.00 | $6.00 | $12.85 |
| 52 | PVT MKG rem WTR blast (78300202) | SF | 881 | $8.05 | $7.45 | $9.50 | $8.00 | $7.45 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 17, 2025. Compiled by Mirage Metrics.