IDOT contract 85786 bid tabulation
Project Number: Hhn6-619 / /, section 18-00237-00-BR. Let by Illinois DOT on January 16, 2026, Whiteside, District 02. 3 bids received; low bid $2,834,678 by Martin & Company Excavating.
- Owner
- Illinois DOT
- Letting
- 16 JAN 2026
- Pay items
- 73
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Martin & Company Excavating | $2,834,678 | Low |
| 2 | Civil Constructors, Inc. d/b/a/ Helm Civil | $3,327,889 | +17% |
| 3 | Brandt Construction Co. | $3,895,254 | +37% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Martin & Company Excavating | 2. Civil Constructors, Inc. d/b/a/ Helm Civil | 3. Brandt Construction Co. |
|---|---|---|---|---|---|---|
| 1 | Outlet SPL (X0324058) | EACH | 2 | $1,310.00 | $2,500.00 | $4,100.00 |
| 2 | Earth excavation SPL (X2020410) | CY | 7,914 | $18.30 | $20.00 | $16.00 |
| 3 | Seeding CL 1A SPL (X2500920) | ACRE | 0.25 | $2,200.00 | $2,000.00 | $2,250.00 |
| 4 | Seeding CL 2A SPL (X2501020) | ACRE | 3.50 | $2,200.00 | $2,000.00 | $2,250.00 |
| 5 | Conc wearing surf VD (X5030301) | SY | 712 | $122.00 | $105.00 | $305.00 |
| 6 | Traf cont & prot SPL (X7010216) | LS | 1 | $9,000.00 | $7,450.00 | $8,500.00 |
| 7 | Construction layout (Z0013798) | LS | 1 | $7,500.00 | $40,000 | $65,000 |
| 8 | Trainees (Z0076600) | HR | 1,000 | $0.80 | $0.80 | $0.80 |
| 9 | Trainees TPG (Z0076604) | HR | 1,000 | $15.00 | $15.00 | $15.00 |
| 10 | Tree remov 6-15 (20100110) | UNIT | 110 | $22.00 | $22.00 | $80.00 |
| 11 | Tree remov over 15 (20100210) | UNIT | 18 | $24.00 | $24.00 | $120.00 |
| 12 | Tree remov acres (20100500) | ACRE | 2.79 | $8,500.00 | $8,500.00 | $12,000 |
| 13 | Rem & disp uns matl (20201200) | CY | 50 | $28.00 | $85.00 | $35.00 |
| 14 | Channel excavation (20300100) | CY | 18,201 | $17.99 | $20.00 | $22.00 |
| 15 | Trench backfill (20800150) | CY | 60 | $42.00 | $45.00 | $65.00 |
| 16 | Seeding CL 4 (25000310) | ACRE | 2 | $2,200.00 | $2,000.00 | $2,250.00 |
| 17 | Erosion contr blanket (25100630) | SY | 26,077 | $1.80 | $1.60 | $1.80 |
| 18 | Temp eros contr seed (28000250) | LB | 546 | $1.00 | $1.00 | $1.15 |
| 19 | Temp ditch checks (28000305) | LF | 24 | $20.00 | $15.00 | $17.00 |
| 20 | Perimeter eros bar (28000400) | LF | 4,508 | $2.70 | $2.25 | $2.55 |
| 21 | Inlet & pipe protect (28000500) | EACH | 5 | $220.00 | $200.00 | $225.00 |
| 22 | Stone riprap CL A5 (28100109) | SY | 879 | $66.00 | $96.00 | $102.00 |
| 23 | Filter fabric (28200200) | SY | 879 | $4.00 | $3.50 | $4.00 |
| 24 | Agg subgrade improve (30300011) | TON | 4,211 | $26.30 | $25.00 | $39.00 |
| 25 | Sub gran mat B 6 (31101400) | SY | 688 | $8.60 | $13.00 | $30.00 |
| 26 | Sub gran mat C 6 (31102300) | SY | 688 | $8.60 | $11.00 | $33.00 |
| 27 | Agg base cse B (35101400) | TON | 151 | $26.00 | $46.00 | $49.00 |
| 28 | Agg surf course TY B (40200800) | TON | 297 | $26.00 | $25.00 | $49.00 |
| 29 | Bit matls PR CT (40600275) | LB | 12,247 | $0.90 | $0.60 | $1.00 |
| 30 | Bit matls tack CT (40600290) | LB | 1,226 | $0.10 | $0.60 | $1.00 |
| 31 | HMA BC IL-19.0 N50 (40603080) | TON | 887 | $86.00 | $88.00 | $142.00 |
| 32 | HMA SC IL-9.5 C N50 (40604050) | TON | 592 | $97.00 | $110.00 | $135.00 |
| 33 | Incidental HMA surf (40800050) | TON | 54 | $114.00 | $140.00 | $195.00 |
| 34 | Protective coat (42001300) | SY | 50 | $4.40 | $0.01 | $17.00 |
| 35 | PC conc sidewalk 5 (42400200) | SF | 33 | $26.00 | $33.00 | $60.00 |
| 36 | Aggregate SHLDS B (48101200) | TON | 432 | $32.00 | $33.00 | $45.00 |
| 37 | HMA shoulders (48203100) | TON | 163 | $166.00 | $110.00 | $155.00 |
| 38 | Rem exist struct (50100100) | EACH | 1 | $209,000 | $170,000 | $110,000 |
| 39 | Structure excavation (50200100) | CY | 155 | $55.00 | $45.00 | $45.00 |
| 40 | Cofferdam excavation (50200300) | CY | 75 | $77.00 | $229.00 | $45.00 |
| 41 | Cofferdam typ 1 loc 1 (50201101) | EACH | 1 | $4,000.00 | $138,000 | $115,000 |
| 42 | Cofferdam typ 1 loc 2 (50201102) | EACH | 1 | $4,000.00 | $138,000 | $115,000 |
| 43 | Conc struct (50300225) | CY | 127.20 | $1,250.00 | $1,310.00 | $1,700.00 |
| 44 | BR deck grooving (50300260) | SY | 673 | $16.00 | $13.50 | $13.00 |
| 45 | Concrete encasement (50300280) | CY | 8.40 | $1,550.00 | $2,000.00 | $4,500.00 |
| 46 | Protective coat (50300300) | SY | 712 | $4.00 | $3.00 | $12.00 |
| 47 | P P conc DK BM 27 DP (50400505) | SF | 6,351 | $119.00 | $125.00 | $150.00 |
| 48 | Reinf bars, epoxy CTD (50800205) | LB | 21,320 | $2.75 | $3.10 | $2.85 |
| 49 | Steel railing TY SM (50901050) | LF | 354 | $220.00 | $209.00 | $235.00 |
| 50 | Slope wall 6 (51100300) | SY | 688 | $145.00 | $254.00 | $215.00 |
| 51 | Fur STL pile HP12X53 (51201600) | LF | 900 | $91.00 | $69.00 | $70.00 |
| 52 | Driving piles (51202305) | LF | 900 | $1.00 | $0.10 | $1.00 |
| 53 | Test pile ST HP12X53 (51203600) | EACH | 4 | $5,400.00 | $7,000.00 | $10,500 |
| 54 | Pile shoes (51204650) | EACH | 24 | $150.00 | $130.00 | $575.00 |
| 55 | Name plates (51500100) | EACH | 1 | $1,400.00 | $980.00 | $1,600.00 |
| 56 | P cul CL A 1 15 (542A0220) | LF | 52 | $69.00 | $66.00 | $135.00 |
| 57 | P cul CL A 1 18 (542A0223) | LF | 116 | $68.00 | $80.00 | $125.00 |
| 58 | P cul CL D 1 15 (542D0220) | LF | 158 | $48.00 | $56.00 | $70.00 |
| 59 | PRC flar end sec 15 (54213660) | EACH | 2 | $1,000.00 | $1,000.00 | $1,200.00 |
| 60 | PRC flar end sec 18 (54213663) | EACH | 2 | $1,150.00 | $1,100.00 | $1,500.00 |
| 61 | Metal FL end sec 15" (54262715) | EACH | 6 | $325.00 | $350.00 | $650.00 |
| 62 | Granular backfill STR (58600101) | CY | 100 | $42.00 | $76.62 | $140.00 |
| 63 | Geocomposite wall DR (59100100) | SY | 70 | $24.00 | $28.00 | $30.00 |
| 64 | P undr for struct 4 (60146304) | LF | 158 | $25.00 | $43.00 | $40.00 |
| 65 | Comb CC&G TB6.18 (60604400) | LF | 204 | $56.00 | $57.00 | $90.00 |
| 66 | Flap gate 15 (60801015) | EACH | 1 | $3,494.00 | $2,600.00 | $4,000.00 |
| 67 | Flap gate 18 (60801018) | EACH | 1 | $4,758.00 | $3,400.00 | $4,500.00 |
| 68 | SPBGR TY A 6FT posts (63000001) | LF | 100 | $41.00 | $39.00 | $45.00 |
| 69 | Traf bar term T6A (63100087) | EACH | 2 | $4,300.00 | $4,200.00 | $4,700.00 |
| 70 | TR bar TRM T1 SPL FLR (63100169) | EACH | 2 | $3,200.00 | $3,100.00 | $3,500.00 |
| 71 | Mobilization (67100100) | LS | 1 | $155,000 | $199,673 | $230,000 |
| 72 | Terminal marker - DA (72501000) | EACH | 2 | $24.00 | $20.00 | $25.00 |
| 73 | Grdrail ref type B (78200006) | EACH | 8 | $24.00 | $20.00 | $25.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.