IDOT contract 89802 bid tabulation
Morton, section 20-00130-00-RS. Let by Illinois DOT on April 25, 2025, Tazewell, District 04. 2 bids received; low bid $2,452,499 by R. A. Cullinan and Son, a div of UCM, Inc..
- Owner
- Illinois DOT
- Letting
- 25 APR 2025
- Pay items
- 80
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | R. A. Cullinan and Son, a div of UCM, Inc. | $2,452,499 | Low |
| 2 | Otto Baum Company, Inc. | $2,500,000 | +2.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. R. A. Cullinan and Son, a div of UCM, Inc. | 2. Otto Baum Company, Inc. |
|---|---|---|---|---|---|
| 1 | HMA sidewalk (XX008693) | SY | 22 | $379.01 | $402.87 |
| 2 | PC conc sidewalk 4 SP (X4240420) | SF | 32,802 | $6.27 | $10.39 |
| 3 | Remov EX flar end sec (X5427602) | EACH | 2 | $1,066.26 | $343.03 |
| 4 | Concrete island SPL (X6061055) | SF | 3,878 | $38.85 | $20.84 |
| 5 | Fence removal (X6640104) | LF | 48 | $65.29 | $100.72 |
| 6 | Traf cont & prot SPL (X7010216) | LS | 1 | $48,455 | $39,223 |
| 7 | Accessible ped signal (X8760200) | EACH | 10 | $3,292.17 | $3,181.27 |
| 8 | Ped pushbutton post (X8760201) | EACH | 6 | $5,992.37 | $5,790.52 |
| 9 | Illuminated sign SPL (X8910050) | EACH | 3 | $12,425 | $13,209 |
| 10 | Construction layout (Z0013798) | LS | 1 | $27,830 | $26,680 |
| 11 | RR prot liability ins (Z0048665) | LS | 1 | $7,937.23 | $7,791.36 |
| 12 | Earth excavation (20200100) | CY | 2,950 | $78.32 | $42.08 |
| 13 | Topsoil F & P 4 (21101615) | SY | 10,327 | $6.66 | $13.08 |
| 14 | Seeding CL 1A (25000110) | ACRE | 2.25 | $4,686.00 | $4,528.16 |
| 15 | Nitrogen fert nutr (25000400) | LB | 204 | $2.20 | $2.13 |
| 16 | Phosphorus fert nutr (25000500) | LB | 204 | $2.20 | $2.13 |
| 17 | Potassium fert nutr (25000600) | LB | 204 | $2.20 | $2.13 |
| 18 | Mulch method 2 (25100115) | ACRE | 2.25 | $4,686.00 | $4,528.16 |
| 19 | Temp eros contr seed (28000250) | LB | 450 | $8.36 | $5.95 |
| 20 | Perimeter eros bar (28000400) | LF | 3,376 | $5.49 | $4.35 |
| 21 | Inlet & pipe protect (28000500) | EACH | 5 | $620.98 | $174.09 |
| 22 | Inlet filters (28000510) | EACH | 7 | $928.23 | $373.20 |
| 23 | Sub gran mat B (31101000) | TON | 1,589 | $90.10 | $59.90 |
| 24 | P bit matls tack CT (40600295) | LB | 23,449 | $1.57 | $1.67 |
| 25 | Temporary ramp (40600990) | SY | 500 | $19.49 | $20.72 |
| 26 | P HMA SC IL-9.5 D N50 (40604160) | TON | 3,648 | $151.62 | $161.16 |
| 27 | Incidental HMA surf (40800050) | TON | 29 | $497.14 | $528.43 |
| 28 | Protective coat (42001300) | SY | 4,628 | $0.99 | $1.81 |
| 29 | PCC driveway pavt 8 (42300400) | SY | 470 | $129.32 | $94.60 |
| 30 | Detectable warnings (42400800) | SF | 160 | $45.22 | $48.08 |
| 31 | Pavement rem (44000100) | SY | 114 | $34.68 | $106.33 |
| 32 | HMA surf rem 2 (44000157) | SY | 32,520 | $5.21 | $5.54 |
| 33 | Drive pavement rem (44000200) | SY | 123 | $19.14 | $16.59 |
| 34 | Comb curb gutter rem (44000500) | LF | 284 | $15.49 | $18.72 |
| 35 | Median removal (44003100) | SF | 3,880 | $9.81 | $3.66 |
| 36 | Pavt patch T2 10 (44200120) | SY | 26 | $255.14 | $262.34 |
| 37 | Pavt patch T4 10 (44200126) | SY | 47 | $242.59 | $232.15 |
| 38 | Pipe culvert remov (50105220) | LF | 10 | $26.56 | $92.46 |
| 39 | P cul CL C 1 30 (542C0235) | LF | 68 | $194.29 | $177.07 |
| 40 | PRC flar end sec 12 (54213657) | EACH | 1 | $1,998.81 | $1,372.30 |
| 41 | Metal FL end sec 30" (54262730) | EACH | 2 | $1,851.51 | $1,349.05 |
| 42 | Storm sew CL A 1 12 (550A0050) | LF | 45 | $124.02 | $181.27 |
| 43 | Storm sew CL A 1 15 (550A0070) | LF | 33 | $177.23 | $283.65 |
| 44 | Storm sewer rem 6 (55100200) | LF | 28 | $30.14 | $33.02 |
| 45 | Pipe drains 6 (60100915) | LF | 82 | $69.09 | $58.54 |
| 46 | Inlets TA T8G (60236200) | EACH | 2 | $1,813.74 | $2,269.37 |
| 47 | Man adjust (60255500) | EACH | 2 | $3,153.41 | $3,841.03 |
| 48 | Comb CC&G TB6.12 (60603800) | LF | 130 | $105.78 | $114.30 |
| 49 | Comb CC&G TY B-6.24 (60605000) | LF | 153 | $153.33 | $104.82 |
| 50 | Conc med TSB6.06 (60619200) | SF | 375 | $102.05 | $45.17 |
| 51 | CH LK fence 6 (66400305) | LF | 42 | $189.20 | $182.83 |
| 52 | Mobilization (67100100) | LS | 1 | $73,508 | $170,588 |
| 53 | Changeable message SN (70107025) | CAL DAY | 100 | $82.50 | $106.29 |
| 54 | Short term pavt mking (70300100) | LF | 7,012 | $2.93 | $2.44 |
| 55 | SHRT TRM pavt MK rem (70300150) | SF | 611 | $4.87 | $7.65 |
| 56 | Sign panel T1 (72000100) | SF | 9 | $239.70 | $231.63 |
| 57 | Mod ureth PM LTR-sym (78009000) | SF | 1,045 | $5.06 | $4.89 |
| 58 | Mod ureth PM line 4 (78009004) | LF | 15,322 | $1.38 | $1.33 |
| 59 | Mod ureth PM line 8 (78009008) | LF | 2,975 | $3.32 | $3.21 |
| 60 | Mod ureth PM line 12 (78009012) | LF | 379 | $4.95 | $4.78 |
| 61 | Mod ureth PM line 24 (78009024) | LF | 385 | $9.90 | $9.57 |
| 62 | Undrgrd C PVC 2 (81028350) | LF | 83 | $42.20 | $40.77 |
| 63 | Undrgrd C PVC 3 (81028370) | LF | 15 | $56.89 | $54.98 |
| 64 | Undrgrd C PVC 4 (81028390) | LF | 325 | $71.92 | $69.50 |
| 65 | Handhole PCC (81400700) | EACH | 2 | $5,744.27 | $5,550.78 |
| 66 | Cont cab type IV (86300400) | EACH | 1 | $53,377 | $51,579 |
| 67 | Elcbl C signal 14 3C (87301225) | LF | 557 | $4.69 | $4.53 |
| 68 | Elcbl C signal 14 5C (87301245) | LF | 2,030 | $5.70 | $5.51 |
| 69 | Elcbl C signal 14 7C (87301255) | LF | 1,494 | $6.83 | $6.60 |
| 70 | Elcbl C egrdc 6 1C (87301900) | LF | 471 | $7.99 | $7.72 |
| 71 | TS post galvs 10 (87502440) | EACH | 2 | $4,125.56 | $4,615.30 |
| 72 | TS post galvs 16 (87502500) | EACH | 2 | $4,824.77 | $5,072.23 |
| 73 | Conc FDN TY A (87800100) | LF | 6 | $735.91 | $711.12 |
| 74 | Conc FDN TY D (87800200) | LF | 4 | $1,387.06 | $1,340.33 |
| 75 | Drill EX handhole (87900200) | EACH | 4 | $1,270.20 | $1,227.42 |
| 76 | SH LED 1F 4S BM (88030070) | EACH | 4 | $2,715.74 | $2,624.26 |
| 77 | Ped SH LED 1F BM CDT (88102717) | EACH | 4 | $2,289.81 | $2,326.53 |
| 78 | Ped SH LED 2F BM CDT (88102747) | EACH | 3 | $3,503.26 | $3,608.82 |
| 79 | TS backplate ret-refl (88200510) | EACH | 4 | $639.12 | $839.75 |
| 80 | Remov EX handhole (89502380) | EACH | 3 | $1,754.04 | $1,371.19 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.