IDOT contract 89852 bid tabulation
City Of Washington, section 22-00130-00-SW. Let by Illinois DOT on April 25, 2025, Tazewell, District 04. 4 bids received; low bid $791,727 by Stark Excavating, Inc..
- Owner
- Illinois DOT
- Letting
- 25 APR 2025
- Pay items
- 48
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Stark Excavating, Inc. | $791,727 | Low |
| 2 | Illinois Civil Contractors, Inc. | $817,880 | +3.0% |
| 3 | Otto Baum Company, Inc. | $959,400 | +21% |
| 4 | Knapp Concrete Contractors, Inc. | $1,007,424 | +27% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Stark Excavating, Inc. | 2. Illinois Civil Contractors, Inc. | 3. Otto Baum Company, Inc. | 4. Knapp Concrete Contractors, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Relocate EX mailbox (X0327301) | EACH | 14 | $700.00 | $198.17 | $488.13 | $977.50 |
| 2 | Comb curb-SW 4IN SPL (X4240130) | SF | 154 | $17.50 | $13.47 | $55.74 | $23.00 |
| 3 | Pro SS conn to EX man (X5510011) | EACH | 1 | $2,500.00 | $1,707.69 | $1,273.21 | $747.50 |
| 4 | CH LK fence remov (X6640300) | LF | 10 | $65.00 | $29.73 | $62.35 | $23.00 |
| 5 | Chain link fence post (X6640502) | EACH | 1 | $3,500.00 | $575.81 | $535.89 | $287.50 |
| 6 | Traf cont & prot SPL (X7010216) | LS | 1 | $6,000.00 | $3,099.70 | $14,680 | $11,385 |
| 7 | Construction layout (Z0013798) | LS | 1 | $15,000 | $12,719 | $9,660.30 | $40,945 |
| 8 | Storm sew WM req 12 (Z0056608) | LF | 406 | $167.25 | $118.22 | $118.00 | $124.20 |
| 9 | Storm sew WM req 15 (Z0056610) | LF | 892 | $84.00 | $130.41 | $126.92 | $179.40 |
| 10 | Tree remov over 15 (20100210) | UNIT | 16 | $170.00 | $160.33 | $281.61 | $184.00 |
| 11 | Tree trunk protection (20101100) | EACH | 3 | $250.00 | $143.50 | $264.88 | $345.00 |
| 12 | Tree root pruning (20101200) | EACH | 1 | $230.00 | $240.49 | $1,684.18 | $1,725.00 |
| 13 | Earth excavation (20200100) | CY | 790 | $47.00 | $79.96 | $69.75 | $51.75 |
| 14 | Trench backfill (20800150) | CY | 820 | $45.00 | $55.06 | $126.60 | $92.00 |
| 15 | Topsoil F & P 4 (21101615) | SY | 2,295 | $7.00 | $13.36 | $13.42 | $14.95 |
| 16 | Nitrogen fert nutr (25000400) | LB | 27 | $6.50 | $6.95 | $6.98 | $8.05 |
| 17 | Phosphorus fert nutr (25000500) | LB | 27 | $6.50 | $6.95 | $6.98 | $8.05 |
| 18 | Potassium fert nutr (25000600) | LB | 27 | $6.50 | $6.95 | $6.98 | $8.05 |
| 19 | Sodding salt tolerant (25200110) | SY | 2,295 | $20.00 | $18.92 | $19.00 | $26.45 |
| 20 | Temp eros contr seed (28000250) | LB | 49 | $2.60 | $5.88 | $2.15 | $46.00 |
| 21 | Perimeter eros bar (28000400) | LF | 1,228 | $3.50 | $4.40 | $4.87 | $6.90 |
| 22 | Inlet & pipe protect (28000500) | EACH | 18 | $160.00 | $264.29 | $304.83 | $575.00 |
| 23 | Agg base cse A 2 (35100120) | SY | 72 | $31.00 | $11.88 | $43.97 | $11.50 |
| 24 | Agg base cse A 8 (35100700) | SY | 140 | $65.00 | $48.28 | $87.11 | $28.75 |
| 25 | Agg base cse B 2 (35101582) | SY | 1,834 | $25.00 | $10.30 | $11.59 | $10.35 |
| 26 | Bit matls tack CT (40600290) | LB | 148 | $2.05 | $2.14 | $2.15 | $2.30 |
| 27 | Incidental HMA surf (40800050) | TON | 36 | $410.00 | $427.54 | $429.35 | $460.00 |
| 28 | Protective coat (42001300) | SY | 1,904 | $0.01 | $0.53 | $1.59 | $3.45 |
| 29 | PCC driveway pavt 6 (42300200) | SY | 848 | $98.30 | $99.68 | $104.70 | $103.50 |
| 30 | PC conc sidewalk 4 (42400100) | SF | 8,877 | $11.30 | $10.19 | $11.11 | $14.95 |
| 31 | Detectable warnings (42400800) | SF | 81 | $36.90 | $32.88 | $44.20 | $39.10 |
| 32 | Pavement rem (44000100) | SY | 138 | $43.25 | $17.07 | $82.61 | $28.75 |
| 33 | Drive pavement rem (44000200) | SY | 845 | $46.70 | $27.50 | $31.50 | $28.75 |
| 34 | Comb curb gutter rem (44000500) | LF | 170 | $23.60 | $14.66 | $17.92 | $14.95 |
| 35 | Sidewalk rem (44000600) | SF | 435 | $3.10 | $1.70 | $10.33 | $2.30 |
| 36 | PRC flar end sec 15 (54213660) | EACH | 1 | $2,000.00 | $1,636.20 | $1,585.30 | $1,725.00 |
| 37 | Storm sewer rem 15 (55100700) | LF | 20 | $30.00 | $41.03 | $107.05 | $80.50 |
| 38 | Man TA 4 dia T1F CL (60218400) | EACH | 13 | $3,800.00 | $4,006.57 | $5,720.42 | $5,191.10 |
| 39 | Inlets TA T8G (60236200) | EACH | 13 | $1,800.00 | $3,546.01 | $2,701.52 | $2,510.45 |
| 40 | Man adjust (60255500) | EACH | 1 | $800.00 | $881.07 | $2,419.86 | $1,380.00 |
| 41 | Inlets adjust (60260100) | EACH | 1 | $675.00 | $2,186.61 | $3,392.27 | $977.50 |
| 42 | Comb CC&G TB6.12 (60603800) | LF | 114 | $105.00 | $83.40 | $108.15 | $86.25 |
| 43 | Comb CC&G TY B-6.24 (60605000) | LF | 71 | $110.00 | $97.83 | $133.06 | $92.00 |
| 44 | Mobilization (67100100) | LS | 1 | $43,000 | $49,073 | $57,422 | $36,800 |
| 45 | Sign panel T1 (72000100) | SF | 17 | $26.00 | $51.31 | $51.52 | $27.60 |
| 46 | Reloc sin pan assy TA (72400500) | EACH | 1 | $101.00 | $293.93 | $295.17 | $747.50 |
| 47 | Metal post TY A (72900100) | LF | 27 | $15.00 | $40.62 | $40.79 | $8.05 |
| 48 | Mod ureth PM line 24 (78009024) | LF | 108 | $101.00 | $115.44 | $103.58 | $224.25 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way