Illinois Civil Contractors, Inc.: IDOT bid record
Illinois Civil Contractors, Inc. submitted 30 bids on Illinois DOT contracts in the data, from 15 JAN 2021 to 18 SEP 2026, and was the low bidder on 9 of them (30%). When it was not low, its total sat a median +20% above the low bid.
- Owner
- Illinois DOT
- Low bid volume
- $6,095,967
- Latest bid
- 18 SEP 2026
- Data through
- 18 SEP 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2021 | 6 | 4 | 67% |
| 2022 | 7 | 1 | 14% |
| 2023 | 3 | 1 | 33% |
| 2024 | 6 | 2 | 33% |
| 2025 | 4 | 1 | 25% |
| 2026 | 4 | 0 | 0% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 04 | 29 | 9 | 31% |
| District 05 | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Perimeter eros bar | 28000400 | LF | 21 | 6 (29%) | $5.75 | $3.50 |
| Temp ditch checks | 28000305 | LF | 7 | 6 (86%) | $11.22 | $12.50 |
| Trainees TPG | Z0076604 | HR | 6 | 6 (100%) | $15.00 | $15.00 |
| Trainees | Z0076600 | HR | 6 | 6 (100%) | $0.80 | $0.80 |
| Temp eros contr seed | 28000250 | LB | 15 | 5 (33%) | $5.88 | $5.00 |
| Earth excavation | 20200100 | CY | 24 | 4 (17%) | $62.20 | $48.00 |
| Pavement rem | 44000100 | SY | 22 | 4 (18%) | $24.70 | $20.30 |
| Inlet & pipe protect | 28000500 | EACH | 16 | 4 (25%) | $267.00 | $200.00 |
| Detectable warnings | 42400800 | SF | 13 | 4 (31%) | $33.23 | $37.00 |
| Reinforcement bars | 50800105 | LB | 6 | 4 (67%) | $3.29 | $2.50 |
| Filter fabric | 28200200 | SY | 13 | 3 (23%) | $3.46 | $4.65 |
| Trench backfill | 20800150 | CY | 10 | 3 (30%) | $51.02 | $55.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Otto Baum Company, Inc. | 23 | 13 of 23 |
| Stark Excavating, Inc. | 17 | 10 of 17 |
| R. A. Cullinan and Son, a div of UCM, Inc. | 13 | 6 of 13 |
| Knapp Concrete Contractors, Inc. | 11 | 5 of 11 |
| Phoenix Corporation of the Quad Cities | 7 | 3 of 7 |
| Gensini Excavating, Inc. | 5 | 5 of 5 |
| White Construction LLC | 3 | 0 of 3 |
| Gunther Construction, a div of UCM, Inc. | 3 | 1 of 3 |
| Brandt Construction Co. | 3 | 1 of 3 |
| McCarthy Improvement Company | 2 | 1 of 2 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 18 SEP 2026 | 68H60 | District 04 | Section (35)N-2 | 4 of 4 | $822,460 | +27% |
| 27 FEB 2026 | 68J46 | District 04 | Section 116N,TS-1 | 3 of 4 | $856,937 | +14% |
| 27 FEB 2026 | 70D72 | District 05 | Section (55)CR | 2 of 3 | $789,400 | +15% |
| 16 JAN 2026 | 89873 | District 04 | Project Number: Qf4C-244 / /, section 22-00112-00-BR | 2 of 4 | $918,425 | +2.0% |
| 01 AUG 2025 | 68B70 | District 04 | Section (Y,72-6)TS | 3 of 3 | $2,166,876 | +24% |
| 13 JUN 2025 | 89866 | District 04 | Galesburg, section 24-02201-35-SW | 1 of 5 | $302,246 | Low, 6.0% under the second |
| 25 APR 2025 | 89852 | District 04 | City Of Washington, section 22-00130-00-SW | 2 of 4 | $817,880 | +3.0% |
| 07 MAR 2025 | 89818 | District 04 | East Peoria, section 19-00171-00-RP | 4 of 5 | $2,935,613 | +10% |
| 08 NOV 2024 | 89816 | District 04 | Project Number: Yufr-842 / /, section 19-00115-01-PV | 5 of 5 | $8,517,855 | +20% |
| 02 AUG 2024 | 89861 | District 04 | Creve Coeur, section 22-00049-00-SW | 3 of 5 | $152,441 | +10% |
| 14 JUN 2024 | 89845 | District 04 | Galesburg, section 22-02201-33-SW | 4 of 5 | $576,637 | +41% |
| 26 APR 2024 | 68H83 | District 04 | Section (72-7-3)CLV | 1 of 2 | $138,627 | Low, 46% under the second |
| 26 APR 2024 | 68H86 | District 04 | Section (103,48)PP,DR | 3 of 3 | $992,468 | +19% |
| 08 MAR 2024 | 89850 | District 04 | Pekin, section 21-00198-00-BT | 1 of 3 | $573,961 | Low, 4.0% under the second |
| 16 JUN 2023 | 68H66 | District 04 | Section D4 | 3 of 6 | $427,714 | +35% |
| 16 JUN 2023 | 68H67 | District 04 | Section D4 | 2 of 5 | $433,658 | +6.0% |
| 20 JAN 2023 | 89822 | District 04 | Project Number: Ays0-285 / /, section 18-00072-00-BR | 1 of 5 | $1,333,481 | Low, 2.0% under the second |
| 18 NOV 2022 | 68E32 | District 04 | Section (116-A)CLV | 2 of 5 | $581,345 | +77% |
| 18 NOV 2022 | 68F51 | District 04 | Section (106)SLP,CLV | 4 of 4 | $829,278 | +46% |
| 23 SEP 2022 | 68H08 | District 04 | Section D4 | 1 of 4 | $436,864 | Low, 8.0% under the second |
| 05 AUG 2022 | 68H12 | District 04 | Section (117)TS,MED | 2 of 2 | $738,053 | +14% |
| 11 MAR 2022 | 68F32 | District 04 | Section 11-DR | 4 of 4 | $131,190 | +64% |
| 21 JAN 2022 | 89787 | District 04 | Morton, section 19-00128-00-PV | 5 of 5 | $3,548,993 | +38% |
| 21 JAN 2022 | MA032 | District 04 | Section MARSHALL | 6 of 8 | $877,416 | +21% |
| 17 SEP 2021 | 68G62 | District 04 | Section (143,23)N,L | 1 of 2 | $723,553 | Low, 0.0% under the second |
How this record was read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Every bid counted here matched its published total to within one dollar; IDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.