IDOT contract 89873 bid tabulation
Project Number: Qf4C-244 / /, section 22-00112-00-BR. Let by Illinois DOT on January 16, 2026, Peoria, District 04. 4 bids received; low bid $898,500 by Otto Baum Company, Inc..
- Owner
- Illinois DOT
- Letting
- 16 JAN 2026
- Pay items
- 52
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Otto Baum Company, Inc. | $898,500 | Low |
| 2 | Illinois Civil Contractors, Inc. | $918,425 | +2.0% |
| 3 | Stark Excavating, Inc. | $968,386 | +8.0% |
| 4 | Knapp Concrete Contractors, Inc. | $997,319 | +11% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Otto Baum Company, Inc. | 2. Illinois Civil Contractors, Inc. | 3. Stark Excavating, Inc. | 4. Knapp Concrete Contractors, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Explor trench SPL (X2130010) | LF | 50 | $70.94 | $49.81 | $23.00 | $63.60 |
| 2 | Temp access- FLD ent (X4024000) | EACH | 2 | $2,555.38 | $1,131.30 | $1,790.00 | $2,650.00 |
| 3 | Dewatering (X5021507) | LS | 1 | $16,257 | $14,768 | $16,000 | $15,900 |
| 4 | Memb WTRPRF sys B STR (X5810103) | SY | 137 | $31.57 | $68.73 | $51.00 | $50.88 |
| 5 | Traf cont & prot SPL (X7010216) | LS | 1 | $17,421 | $21,893 | $12,400 | $21,200 |
| 6 | Change message SN SPL (X7010237) | CAL DAY | 108 | $26.81 | $109.74 | $26.00 | $90.10 |
| 7 | Temp info signing (X7200061) | SF | 50 | $21.45 | $53.77 | $21.00 | $53.00 |
| 8 | Construction layout (Z0013798) | LS | 1 | $9,865.01 | $10,096 | $5,010.00 | $9,752.00 |
| 9 | Trainees (Z0076600) | HR | 1,000 | $0.80 | $0.80 | $0.80 | $0.80 |
| 10 | Trainees TPG (Z0076604) | HR | 1,000 | $15.00 | $15.00 | $15.00 | $15.00 |
| 11 | Earth excavation (20200100) | CY | 873 | $39.44 | $51.62 | $30.00 | $42.40 |
| 12 | Rem & disp uns matl (20201200) | CY | 80 | $43.70 | $49.81 | $39.00 | $180.20 |
| 13 | Porous gran embank (20700220) | CY | 484 | $103.44 | $83.50 | $110.00 | $97.52 |
| 14 | Geotech fab F/GR stab (21001000) | SY | 478 | $2.51 | $2.43 | $2.40 | $5.51 |
| 15 | Topsoil F & P 4 (21101615) | SY | 3,593 | $5.90 | $10.17 | $4.25 | $5.83 |
| 16 | Seeding CL 2A (25000210) | ACRE | 0.75 | $4,289.15 | $4,696.83 | $2,800.00 | $4,240.00 |
| 17 | Nitrogen fert nutr (25000400) | LB | 67 | $5.36 | $5.49 | $2.55 | $5.30 |
| 18 | Phosphorus fert nutr (25000500) | LB | 67 | $5.36 | $5.49 | $2.55 | $5.30 |
| 19 | Potassium fert nutr (25000600) | LB | 67 | $5.36 | $5.49 | $2.55 | $5.30 |
| 20 | Erosion contr blanket (25100630) | SY | 3,593 | $1.61 | $1.65 | $1.22 | $1.59 |
| 21 | Perimeter eros bar (28000400) | LF | 900 | $3.75 | $5.48 | $2.90 | $3.71 |
| 22 | Inlet & pipe protect (28000500) | EACH | 2 | $268.08 | $260.44 | $165.00 | $265.00 |
| 23 | Stone riprap CL A4 (28100107) | SY | 250 | $90.11 | $145.96 | $112.00 | $90.10 |
| 24 | Filter fabric (28200200) | SY | 702 | $4.76 | $3.49 | $5.00 | $6.47 |
| 25 | Aggregate ditch (28300400) | TON | 265 | $99.29 | $116.42 | $111.00 | $54.06 |
| 26 | Agg subgrade improve (30300001) | CY | 80 | $107.59 | $65.57 | $85.00 | $84.80 |
| 27 | Agg subgrade impr 12 (30300112) | SY | 1,289 | $17.72 | $20.55 | $37.00 | $29.68 |
| 28 | Agg surf cse B (40200900) | CY | 27 | $193.06 | $86.90 | $130.00 | $84.80 |
| 29 | Bit matls PR CT (40600275) | LB | 2,800 | $1.61 | $1.10 | $1.05 | $1.06 |
| 30 | Bit matls tack CT (40600290) | LB | 840 | $2.68 | $1.76 | $1.70 | $1.70 |
| 31 | HMA BC IL-19.0 N50 (40603080) | TON | 419 | $160.84 | $195.98 | $180.00 | $189.74 |
| 32 | HMA SC IL-9.5 D N50 (40604060) | TON | 140 | $214.46 | $247.68 | $228.00 | $239.56 |
| 33 | Pavement rem (44000100) | SY | 1,022 | $11.99 | $25.12 | $10.00 | $21.20 |
| 34 | Paved ditch removal (44004000) | LF | 268 | $29.82 | $19.26 | $12.00 | $12.72 |
| 35 | Rem exist struct (50100100) | EACH | 1 | $24,763 | $34,202 | $57,085 | $13,780 |
| 36 | Pipe culvert remov (50105220) | LF | 44 | $49.41 | $35.94 | $16.00 | $42.40 |
| 37 | Structure excavation (50200100) | CY | 580 | $30.32 | $47.11 | $23.00 | $42.40 |
| 38 | Reinforcement bars (50800105) | LB | 59,180 | $1.58 | $1.55 | $1.80 | $2.10 |
| 39 | Name plates (51500100) | EACH | 1 | $1,718.28 | $1,475.51 | $1,500.00 | $1,017.60 |
| 40 | Conc box cul (54003000) | CY | 209 | $1,106.71 | $874.88 | $1,320.00 | $1,404.50 |
| 41 | P cul CL A 1 18 (542A0223) | LF | 56 | $139.60 | $96.94 | $95.00 | $121.90 |
| 42 | PRC flar end sec 18 (54213663) | EACH | 4 | $1,593.11 | $1,862.37 | $1,200.00 | $1,817.90 |
| 43 | Geocomposite wall DR (59100100) | SY | 137 | $29.86 | $23.13 | $26.75 | $42.93 |
| 44 | Misc concrete (61100605) | CY | 10 | $1,348.95 | $594.75 | $182.00 | $508.80 |
| 45 | FLD tile jun vault 2D (61133100) | EACH | 2 | $2,350.86 | $1,838.54 | $2,230.00 | $2,111.52 |
| 46 | Storm sewer spec 4 (61139800) | LF | 20 | $100.33 | $23.11 | $40.15 | $63.60 |
| 47 | Storm sewer spec 6 (61139900) | LF | 20 | $119.60 | $46.57 | $74.70 | $68.90 |
| 48 | Storm sewer spec 8 (61140000) | LF | 20 | $140.27 | $58.15 | $80.30 | $74.20 |
| 49 | Mobilization (67100100) | LS | 1 | $55,336 | $45,921 | $58,000 | $21,200 |
| 50 | Remov sin pan assy TA (72400100) | EACH | 3 | $187.65 | $119.72 | $175.00 | $848.00 |
| 51 | Mod ureth PM line 4 (78009004) | LF | 1,000 | $7.51 | $7.68 | $7.05 | $11.66 |
| 52 | GRV RCSD PVT MRKG 5 (78011025) | LF | 1,000 | $6.43 | $6.58 | $6.05 | $11.66 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.