IDOT contract 93833 bid tabulation

Project Number: Aara-086 / /, section 05-00164-03-FP. Let by Illinois DOT on August 1, 2025, Sangamon, District 06. 2 bids received; low bid $6,690,296 by Illinois Valley Paving, a div of UCM, Inc..

Owner
Illinois DOT
Letting
01 AUG 2025
Pay items
101
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Illinois Valley Paving, a div of UCM, Inc.$6,690,296Low
2Truman L. Flatt & Sons Co., Inc.$7,722,589+15%
IDOT contract 93833: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Illinois Valley Paving, a div of UCM, Inc.2. Truman L. Flatt & Sons Co., Inc.
1Storm sew CL B 1 8 (XX009453)LF211$67.67$70.80
2Solar-power FB as CMP (X0326899)EACH1$2,524.50$4,410.00
3Manhole special (X6020084)EACH1$15,180$11,135
4Conc med TSB6.24 SPL (X6060300)SF6,624$15.44$25.50
5Traf cont & prot SPL (X7010216)LS1$65,183$4,946.82
6Rem EX sign compl (X7240207)EACH4$322.19$118.75
7Construction layout (Z0013798)LS1$76,381$97,650
8Trainees (Z0076600)HR3,000$0.80$0.80
9Trainees TPG (Z0076604)HR3,000$15.00$15.00
10Tree remov acres (20100500)ACRE0.50$26,182$25,179
11Earth excavation (20200100)CY8,055$12.02$19.48
12Furnished excavation (20400800)CY52,135$8.02$20.22
13Trench backfill (20800150)CY318.30$147.91$76.06
14Topsoil exc & plac (21101505)CY20,215$8.94$17.08
15Seeding CL 2 (25000200)ACRE9.25$2,040.00$6,037.42
16Seeding CL 3 (25000300)ACRE0.25$5,100.00$6,037.40
17Nitrogen fert nutr (25000400)LB939$2.04$1.84
18Phosphorus fert nutr (25000500)LB939$2.04$3.00
19Potassium fert nutr (25000600)LB939$2.04$3.35
20Agr ground limestone (25000700)TON21.80$102.00$315.00
21Mulch method 2 (25100115)ACRE9.50$1,020.00$4,024.94
22Erosion contr blanket (25100630)SY15,318$1.53$1.89
23Sodding salt tolerant (25200110)SY6,743$19.38$12.76
24Supple watering (25200200)UNIT337$204.00$0.01
25Temp eros contr seed (28000250)LB931.25$5.10$4.99
26Temp ditch checks (28000305)LF1,410$11.61$9.56
27Perimeter eros bar (28000400)LF11,729$2.24$5.10
28Inlet & pipe protect (28000500)EACH8$381.29$231.16
29Stone riprap CL B4 (28100127)SY1,444$61.59$88.59
30Stone dump rip CL A1 (28100701)SY1,444$29.21$28.17
31Filter fabric (28200200)SY1,444$5.56$5.45
32Process mod soil 12 (30200650)SY38,842$4.60$3.84
33Lime (30201500)TON1,036$163.20$168.00
34Sub gran mat B 3 (31101191)SY38,842$6.95$6.99
35Agg surf cse A 8 (40200700)SY925$18.37$28.14
36Bit matls tack CT (40600290)LB13,998$0.97$0.70
37Long joint sealant (40600370)LF24,021$2.93$3.89
38Matl transfer device (40600405)TON16,041$0.01$4.40
39P HMA SC IL-9.5 D N50 (40604160)TON31$126.04$157.60
40HMA pavt FD 9 1/4 (40701866)SY30,967$62.14$64.09
41Protective coat (42001300)SY6,766$0.01$0.01
42PCC driveway pavt 8 (42300400)SY269$123.19$104.69
43HMA surf rem 2 (44000157)SY293$16.67$10.91
44Comb curb gutter rem (44000500)LF48$18.71$22.53
45P cul CL A 1 36 (542A0241)LF418$188.91$206.30
46P cul CL A 2 60 (542A1105)LF179$425.12$383.23
47P cul CL C 1 18 (542C0223)LF152$110.45$141.23
48P cul CL C 1 24 (542C0229)LF46$117.12$115.01
49PRC flar end sec 12 (54213657)EACH91$1,533.15$1,250.24
50PRC flar end sec 36 (54213681)EACH6$3,514.61$2,788.80
51Cip RC end sec 60 (54215460)EACH2$21,314$29,190
52Metal FL end sec 18" (54262718)EACH6$428.48$394.64
53Metal FL end sec 24" (54262724)EACH2$768.58$645.16
54Storm sew CL A 1 12 (550A0050)LF2,035$106.48$93.88
55Conc HDWL for P drain (60100060)EACH6$1,148.09$447.18
56Pipe drains 6 (60100915)LF120$42.97$43.82
57Pipe drains 8 (60100925)LF120$45.71$47.18
58Pipe drains 12 (60100945)LF120$62.19$69.12
59Pipe underdr T 1 4 (60108104)LF11,196$10.29$15.04
60Man TA 4 dia T3F&G (60218500)EACH5$5,378.08$4,426.52
61Man TA 4 dia T11F&G (60219300)EACH1$6,290.52$4,273.76
62Inlets TA T3F&G (60235700)EACH98$2,017.96$2,197.87
63Inlets TA T11F&G (60236800)EACH4$2,472.72$2,179.23
64Inlets TB T3F&G (60240220)EACH2$3,576.72$2,862.15
65Comb CC&G TB6.18 (60604400)LF48$113.86$103.56
66Comb CC&G TY B-6.24 (60605000)LF20,766.50$44.00$42.84
67Conc median surf 4 (60618300)SF592$15.94$8.99
68Conc thrust blocks (61000050)EACH6$934.97$561.60
69Explor trench 52 (61100500)LF1,120$3.62$12.65
70Misc concrete (61100605)CY3$1,716.84$1,516.03
71Storm sew prot A 6 (61101007)LF400$55.08$50.67
72Storm sew prot A 8 (61101009)LF400$58.34$50.19
73Storm sew prot A 15 (61101017)LF550$73.28$55.88
74Storm sew prot A 18 (61101020)LF200$92.98$53.68
75Perm surv MKRS T1 (66700205)EACH5$910.91$776.83
76Mobilization (67100100)LS1$282,029$291,707
77TR cont & prot 701601 (70102630)LS1$0.01$13,373
78TR cont & prot 701701 (70102635)LS1$0.01$4,299.18
79Sign panel T1 (72000100)SF118.90$42.33$37.86
80Sign panel T2 (72000200)SF10$22.44$57.94
81Teles STL sin support (72800100)LF36$15.81$26.22
82Wood sin support (73000100)LF272$28.51$19.98
83Base tel STL sin supp (73100100)EACH3$331.50$562.31
84PT PVT MK LTRS & symb (78001100)SF162$3.06$3.15
85Paint PVT MK line 5 (78001120)LF31,210$0.26$0.26
86Paint PVT MK line 6 (78001130)LF1,581$0.37$0.38
87Paint PVT MK line 12 (78001150)LF296$0.77$0.79
88Paint PVT MK line 24 (78001180)LF175$4.08$4.20
89Raised refl pavt MKR (78100100)EACH246$37.18$38.27
90Raised ref PVT MK rem (78300200)EACH59$10.79$18.76
91PVT MKG rem WTR blast (78300202)SF3,973$1.53$1.58
92Undrgrd C IM 2 (81028550)LF148$78.03$80.33
93UD 2#8 #8G xlpuse 3/4 (81603000)LF316$37.03$38.12
94EC C XLP use 1C 10 (81702110)LF451$5.81$5.99
95Lum LED rdwy E (82110005)EACH3$948.60$976.50
96Lum LED rdwy H (82110008)EACH4$948.60$976.50
97LT cont pedm 240V 60 (82500330)EACH1$26,010$26,775
98LT P A 40MH 15MA (83008600)EACH2$8,262.00$8,505.00
99LT P A 45MH 12MA (83009500)EACH3$8,017.20$8,253.00
100LP F M 15BC 8 5/8X6 (83600356)EACH3$2,019.60$2,079.00
101Bkwy dev cou SS SCRN (83800650)EACH20$211.14$217.35
IDOT contract 93833: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of August 1, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy