IDOT contract 97856 bid tabulation
Glen Carbon, section 23-00032-01-BT. Let by Illinois DOT on March 7, 2025, Madison, District 08. 2 bids received; low bid $954,648 by Baxmeyer Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 07 MAR 2025
- Pay items
- 70
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Baxmeyer Construction, Inc. | $954,648 | Low |
| 2 | Keller Construction, Inc. | $1,000,000 | +5.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Baxmeyer Construction, Inc. | 2. Keller Construction, Inc. |
|---|---|---|---|---|---|
| 1 | Solar-power FB as CMP (X0326899) | EACH | 2 | $11,000 | $10,553 |
| 2 | Potholing (X1700066) | EACH | 50 | $439.00 | $0.01 |
| 3 | Sidewalk rem SPL (X4404700) | SF | 62 | $4.00 | $26.80 |
| 4 | Downspout connection (X5230168) | EACH | 11 | $870.00 | $500.00 |
| 5 | Inlets SPL N1 (X6024242) | EACH | 2 | $3,100.00 | $4,300.00 |
| 6 | Inlets SPL N2 (X6024244) | EACH | 4 | $3,600.00 | $4,722.00 |
| 7 | Traf cont & prot SPL (X7010216) | LS | 1 | $4,175.00 | $4,000.00 |
| 8 | Sign removal (X7240300) | EACH | 2 | $969.00 | $1,750.00 |
| 9 | Light pole special (X8300001) | EACH | 2 | $7,140.00 | $6,825.00 |
| 10 | Concrete steps (Z0012450) | CY | 1.20 | $3,740.00 | $5,381.25 |
| 11 | Storm sew WM req 15 (Z0056610) | LF | 299 | $80.70 | $107.15 |
| 12 | Storm sew WM req 18 (Z0056612) | LF | 481 | $89.50 | $122.50 |
| 13 | Storm sew WM req 24 (Z0056616) | LF | 108 | $137.00 | $182.95 |
| 14 | Storm sew WM req 30 (Z0056620) | LF | 190 | $225.65 | $236.15 |
| 15 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 |
| 16 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 |
| 17 | Tree remov 6-15 (20100110) | UNIT | 46 | $54.00 | $194.50 |
| 18 | Earth excavation (20200100) | CY | 425 | $111.50 | $69.45 |
| 19 | Rem & disp uns matl (20201200) | CY | 100 | $32.70 | $25.75 |
| 20 | Furnished excavation (20400800) | CY | 330 | $0.01 | $35.75 |
| 21 | Seeding CL 2A (25000210) | ACRE | 0.50 | $10,800 | $21,805 |
| 22 | Nitrogen fert nutr (25000400) | LB | 40 | $18.30 | $1.21 |
| 23 | Phosphorus fert nutr (25000500) | LB | 40 | $18.30 | $1.21 |
| 24 | Potassium fert nutr (25000600) | LB | 40 | $18.30 | $1.21 |
| 25 | Mulch method 2 (25100115) | ACRE | 0.50 | $5,627.00 | $16,758 |
| 26 | Temp eros contr seed (28000250) | LB | 80 | $17.00 | $6.85 |
| 27 | Temp ditch checks (28000305) | LF | 63 | $24.50 | $18.80 |
| 28 | Inlet & pipe protect (28000500) | EACH | 31 | $210.00 | $290.00 |
| 29 | Agg subgrade improve (30300011) | TON | 200 | $50.00 | $45.50 |
| 30 | Agg base cse B (35101400) | TON | 941 | $54.00 | $44.35 |
| 31 | PCC bse cse 7 (35300200) | SY | 361 | $33.00 | $84.90 |
| 32 | Agg surf cse A (40200100) | TON | 2 | $70.00 | $275.00 |
| 33 | Aggregate-temp access (40201000) | TON | 145 | $80.00 | $110.00 |
| 34 | Bit matls PR CT (40600275) | LB | 3,184 | $3.40 | $3.25 |
| 35 | Bit matls tack CT (40600290) | LB | 173 | $13.25 | $12.63 |
| 36 | HMA SC IL-9.5FG C N70 (40604002) | TON | 149 | $334.70 | $313.82 |
| 37 | HMA SC IL-9.5 C N70 (40604052) | TON | 43 | $340.00 | $313.82 |
| 38 | Incidental HMA surf (40800050) | TON | 12 | $370.30 | $313.82 |
| 39 | PCC driveway pavt 6 (42300200) | SY | 413 | $152.00 | $115.50 |
| 40 | PCC driveway pavt 8 (42300400) | SY | 337 | $147.00 | $143.85 |
| 41 | PC conc sidewalk 4 (42400100) | SF | 1,585 | $16.45 | $11.18 |
| 42 | Detectable warnings (42400800) | SF | 161 | $68.00 | $53.00 |
| 43 | Pavement rem (44000100) | SY | 358 | $12.25 | $33.75 |
| 44 | Drive pavement rem (44000200) | SY | 527 | $15.70 | $32.50 |
| 45 | Comb curb gutter rem (44000500) | LF | 36 | $16.00 | $25.00 |
| 46 | Paved SHLD removal (44004250) | SY | 895 | $16.20 | $7.65 |
| 47 | CL C patch T3 7 (44201321) | SY | 25 | $591.00 | $312.50 |
| 48 | Pipe culvert remov (50105220) | LF | 539 | $23.20 | $26.25 |
| 49 | P cul CL C 1 15 (542C0220) | LF | 34 | $46.80 | $80.75 |
| 50 | PRC flar end sec 12 (54213657) | EACH | 1 | $1,350.00 | $2,112.00 |
| 51 | Concrete collar (54248510) | CY | 0.30 | $1,360.00 | $6,475.00 |
| 52 | Storm sew CL A 1 12 (550A0050) | LF | 126 | $55.30 | $100.00 |
| 53 | Storm sew CL A 1 15 (550A0070) | LF | 254 | $66.70 | $85.50 |
| 54 | Storm sew CL A 1 18 (550A0090) | LF | 143 | $74.70 | $101.25 |
| 55 | Storm sew CL A 1 24 (550A0120) | LF | 98 | $102.00 | $125.50 |
| 56 | Storm sew CL A 2 12 (550A0340) | LF | 17 | $64.25 | $111.75 |
| 57 | Storm sew CL A 2 15 (550A0360) | LF | 17 | $78.00 | $119.65 |
| 58 | Inlets TA T1F CL (60235300) | EACH | 1 | $1,817.50 | $3,680.00 |
| 59 | Inlets TA T3F&G (60235700) | EACH | 1 | $1,817.50 | $3,865.00 |
| 60 | Inlets TA T8G (60236200) | EACH | 7 | $1,781.00 | $3,495.00 |
| 61 | Inlets TB T3F&G (60240220) | EACH | 13 | $2,451.00 | $4,208.00 |
| 62 | Inlets TB T8G (60240301) | EACH | 1 | $2,414.00 | $3,864.00 |
| 63 | Comb CC&G TY B-6.24 (60605000) | LF | 1,603 | $74.50 | $42.90 |
| 64 | Mobilization (67100100) | LS | 1 | $52,360 | $77,236 |
| 65 | Sign panel T1 (72000100) | SF | 22 | $46.00 | $43.85 |
| 66 | Reloc sin pan assy TA (72400500) | EACH | 5 | $193.00 | $157.65 |
| 67 | Teles STL sin support (72800100) | LF | 161 | $15.40 | $14.70 |
| 68 | Paint PVT MK line 4 (78001110) | LF | 288 | $1.20 | $1.13 |
| 69 | Paint PVT MK line 12 (78001150) | LF | 20 | $4.50 | $4.23 |
| 70 | Paint PVT MK line 24 (78001180) | LF | 432 | $3.25 | $3.10 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of March 7, 2025. Compiled by Mirage Metrics.