IDOT contract 99757 bid tabulation
Project Number: Mni4-133 / /, section 21-00164-00-PV. Let by Illinois DOT on February 27, 2026, Williamson, District 09. 3 bids received; low bid $1,715,790 by Samron Midwest Contracting, Inc..
- Owner
- Illinois DOT
- Letting
- 27 FEB 2026
- Pay items
- 68
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Samron Midwest Contracting, Inc. | $1,715,790 | Low |
| 2 | E. T. Simonds Construction Company | $1,816,142 | +6.0% |
| 3 | Baxmeyer Construction, Inc. | $2,004,777 | +17% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Samron Midwest Contracting, Inc. | 2. E. T. Simonds Construction Company | 3. Baxmeyer Construction, Inc. |
|---|---|---|---|---|---|---|
| 1 | Landscaping gravel (X0323117) | SY | 153 | $33.00 | $31.50 | $77.00 |
| 2 | Stamp CLRD PCC med 4 (X1700011) | SF | 10,340 | $15.00 | $18.89 | $15.75 |
| 3 | Stamped CLRDPCCPVT8J (X4200468) | SY | 535 | $150.00 | $181.40 | $149.00 |
| 4 | Comb CC&G TM SPL (X6061815) | LF | 331 | $60.00 | $59.89 | $96.75 |
| 5 | Traf cont & prot SPL (X7010216) | LS | 1 | $39,000 | $51,054 | $49,000 |
| 6 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 | $0.80 |
| 7 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 | $15.00 |
| 8 | Tree remov acres (20100500) | ACRE | 0.45 | $20,000 | $14,700 | $0.01 |
| 9 | Earth excavation (20200100) | CY | 2,165 | $11.00 | $12.60 | $32.00 |
| 10 | Rem & disp uns matl (20201200) | CY | 988 | $17.00 | $13.65 | $26.00 |
| 11 | Furnished excavation (20400800) | CY | 3,160 | $16.00 | $18.80 | $28.80 |
| 12 | Trench backfill (20800150) | CY | 16 | $150.00 | $110.25 | $48.50 |
| 13 | Seeding CL 1B (25000115) | ACRE | 1.25 | $2,800.00 | $3,753.75 | $4,250.00 |
| 14 | Nitrogen fert nutr (25000400) | LB | 106 | $3.00 | $1.73 | $5.75 |
| 15 | Phosphorus fert nutr (25000500) | LB | 106 | $3.00 | $1.73 | $5.75 |
| 16 | Potassium fert nutr (25000600) | LB | 106 | $3.00 | $1.73 | $5.75 |
| 17 | Agr ground limestone (25000700) | TON | 2.40 | $200.00 | $372.75 | $960.00 |
| 18 | Mulch method 2 (25100115) | ACRE | 1.25 | $2,900.00 | $2,598.75 | $4,935.00 |
| 19 | Temp eros contr seed (28000250) | LB | 118 | $2.50 | $2.63 | $15.75 |
| 20 | Temp ditch checks (28000305) | LF | 120 | $14.00 | $10.50 | $29.50 |
| 21 | Perimeter eros bar (28000400) | LF | 2,555 | $0.01 | $4.20 | $6.25 |
| 22 | Inlet & pipe protect (28000500) | EACH | 7 | $135.00 | $78.75 | $0.01 |
| 23 | Stone riprap CL A4 (28100107) | SY | 30 | $150.00 | $73.50 | $177.00 |
| 24 | Filter fabric (28200200) | SY | 30 | $0.01 | $6.30 | $29.00 |
| 25 | Sub gran mat A (31100100) | TON | 6,702 | $28.50 | $27.62 | $28.50 |
| 26 | Sub gran mat C (31102000) | CY | 988 | $45.00 | $33.17 | $63.50 |
| 27 | PCC PVT 8 jointed (42000301) | SY | 5,665 | $84.00 | $96.93 | $89.50 |
| 28 | Protective coat (42001300) | SY | 7,123 | $0.01 | $0.01 | $0.01 |
| 29 | PCC driveway pavt 6 (42300200) | SY | 129 | $123.00 | $188.79 | $133.00 |
| 30 | Pavement rem (44000100) | SY | 4,418 | $6.75 | $6.80 | $9.00 |
| 31 | PCC shoulders 8 (48300300) | SY | 24 | $100.00 | $181.32 | $223.50 |
| 32 | Pipe culvert remov (50105220) | LF | 42 | $10.00 | $5.25 | $22.00 |
| 33 | P cul CL D 1 12 (542D0217) | LF | 18 | $37.00 | $36.75 | $57.50 |
| 34 | P cul CL D 1 15 (542D0220) | LF | 25 | $45.00 | $42.00 | $80.00 |
| 35 | Metal FL end sec 12" (54262712) | EACH | 2 | $311.00 | $307.65 | $545.00 |
| 36 | Metal FL end sec 15" (54262715) | EACH | 4 | $390.00 | $383.25 | $745.00 |
| 37 | Storm sew CL B 1 15 (550B0070) | LF | 150 | $32.00 | $27.30 | $50.50 |
| 38 | Storm sewer rem 15 (55100700) | LF | 90 | $10.00 | $15.75 | $15.50 |
| 39 | Inlets TB T8G (60240301) | EACH | 1 | $3,200.00 | $2,908.50 | $2,250.00 |
| 40 | Remov inlets (60500060) | EACH | 1 | $500.00 | $735.00 | $475.00 |
| 41 | Class SI conc outlet (60600095) | CY | 6 | $2,800.00 | $773.16 | $3,180.00 |
| 42 | Conc curb TB (60600605) | LF | 210 | $42.00 | $48.04 | $107.00 |
| 43 | Comb CC&G TY B-6.24 (60605000) | LF | 4,567 | $47.00 | $47.59 | $46.50 |
| 44 | Fur erect row markers (66600105) | EACH | 10 | $300.00 | $309.46 | $375.00 |
| 45 | Mobilization (67100100) | LS | 1 | $100,000 | $113,784 | $155,877 |
| 46 | Changeable message SN (70107025) | CAL DAY | 700 | $35.00 | $0.01 | $47.00 |
| 47 | Sign panel T1 (72000100) | SF | 549 | $35.00 | $0.01 | $36.00 |
| 48 | Sign panel T2 (72000200) | SF | 80 | $0.01 | $0.01 | $27.50 |
| 49 | Remov sin pan assy TB (72400200) | EACH | 6 | $0.01 | $70.43 | $250.00 |
| 50 | Rem & rel sign panel asmbly TB (72400210) | EACH | 2 | $250.00 | $211.28 | $445.00 |
| 51 | Wood sin support (73000100) | LF | 495 | $38.00 | $24.89 | $20.00 |
| 52 | Mod ureth PM LTR-sym (78009000) | SF | 140 | $6.75 | $6.30 | $6.50 |
| 53 | Mod ureth PM line 4 (78009004) | LF | 7,014 | $2.00 | $2.05 | $2.10 |
| 54 | Mod ureth PM line 12 (78009012) | LF | 139 | $6.75 | $6.14 | $6.30 |
| 55 | Mod ureth PM line 18 (78009018) | LF | 56 | $13.00 | $12.29 | $12.60 |
| 56 | GRV RCSD PM LTR & sym (78011000) | SF | 140 | $5.75 | $5.25 | $5.40 |
| 57 | GRV RCSD PVT MRKG 5 (78011025) | LF | 7,014 | $1.50 | $1.44 | $1.50 |
| 58 | GRV RCSD PVT MRKG 13 (78011065) | LF | 139 | $3.25 | $3.15 | $3.25 |
| 59 | GRV RCSD PVT MRKG 19 (78011095) | LF | 56 | $9.00 | $8.40 | $8.65 |
| 60 | Elect serv install (80400100) | EACH | 1 | $8,500.00 | $5,159.51 | $5,250.00 |
| 61 | Undrgrd C CNC 2 (81028750) | LF | 250 | $30.00 | $29.09 | $29.55 |
| 62 | Handhole (81400100) | EACH | 5 | $2,500.00 | $2,679.79 | $2,725.00 |
| 63 | UD 2#10#10GXLPUSE 3/4 (81603010) | LF | 400 | $15.00 | $14.76 | $15.00 |
| 64 | Lum LED rdwy G (82110007) | EACH | 4 | $750.00 | $796.12 | $810.00 |
| 65 | LT cont PM 240V 30 (82500300) | EACH | 1 | $6,700.00 | $6,548.20 | $6,655.00 |
| 66 | LT P A 45MH 15DA (83003600) | EACH | 4 | $6,800.00 | $6,658.69 | $6,775.00 |
| 67 | LP F M 15BC 8 5/8X6 (83600356) | EACH | 4 | $1,500.00 | $1,268.26 | $1,300.00 |
| 68 | Bkwy dev cou SS SCRN (83800650) | EACH | 16 | $260.00 | $255.90 | $260.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of February 27, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.