INDOT contract B-42777-A bid tabulation

BRIDGE REPLACEMENT. Let by Indiana DOT on March 11, 2026, Noble, Fort Wayne. 4 bids received; low bid $3,652,797 by R L McCoy Inc.

Owner
Indiana DOT
Letting
11 MAR 2026
Pay items
91
Data through
05 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1R L McCoy Inc$3,652,797Low
2Milestone Contractors LP$3,770,652+3.0%
3Beaty Construction Inc$4,344,713+19%
4Phend & Brown Inc$4,801,317+31%
INDOT contract B-42777-A: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. R L McCoy Inc2. Milestone Contractors LP3. Beaty Construction Inc4. Phend & Brown Inc
0001Construction engineering (105-06845)LS1$32,000$49,000$54,000$75,000
0002Liquidated damages (109-08359)DOL1$1.00$1.00$1.00$1.00
0003Contract liens (109-08360)DOL1$1.00$1.00$1.00$1.00
0004Quality adjustments, HMA (109-08440)DOL1$1.00$1.00$1.00$1.00
0005Quality adjustments, temporary traffic control devices (109-08443)DOL1$1.00$1.00$1.00$1.00
0006Quality adjustments, failed materials (109-08444)DOL1$1.00$1.00$1.00$1.00
0007Payment adjustment, PG asphalt binder (109-09489)DOL1$1.00$1.00$1.00$1.00
0008Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362)DOL1$1.00$1.00$1.00$1.00
0009Mobilization and demobilization (110-01001)LS1$182,600$188,533$217,235$230,000
0010Clearing right-of-way (201-52370)LS1$36,500$37,707$43,445$170,000
0011Present structure, remove, structure no. 1 (202-51330)LS1$415,000$147,198$383,176$200,000
0012Excavation, common (203-02000)CYS1,250$24.00$24.00$18.25$55.00
0013Borrow (203-02070)CYS27,550$20.00$20.00$31.00$24.00
0014Stormwater management budget (205-12108)DOL57,000$1.00$1.00$1.00$1.00
0015Stormwater management implementation (205-12616)LS1$18,000$1,500.00$38,000$13,500
0016SWQCP preparation (205-12618)LS1$3,400.00$1,400.00$5,000.00$3,400.00
0017Excavation, foundation, unclassified (206-51230)CYS1,651$20.00$20.00$33.00$22.00
0018Subgrade treatment, type II (207-08264)SYS485$29.00$29.00$18.75$32.00
0019Subgrade treatment, type III (207-08266)SYS4,075$4.00$4.00$2.00$3.00
0020B borrow (211-02050)CYS1,435$50.00$130.00$72.50$120.00
0021Structure backfill, type 1 (211-09264)CYS35$65.00$65.00$74.50$45.00
0022Structure backfill, type 3 (211-09266)CYS1,755$86.00$145.00$72.50$120.00
0023Geotextile for pavement, type 2B (214-12239)SYS1,586$5.50$5.20$4.50$5.50
0024Compacted aggregate, no. 53 (301-12234)CYS486$75.00$75.00$117.25$98.00
0025Subbase for PCCP (302-06464)CYS34$200.00$200.00$163.00$150.00
0026Compacted aggregate, no. 53 (303-01180)TON595$38.00$38.00$48.25$50.00
0027QC/QA-HMA, 2, 58S, surface, 9.5 MM (401-000001)TON295$115.00$115.00$115.00$130.00
0028QC/QA-HMA, 2, 58S, intermediate, 19.0 MM (401-000037)TON505$95.00$95.00$95.00$110.00
0029QC/QA-HMA, 2, 58S, base, 25.0 MM (401-000046)TON830$86.00$86.00$86.00$102.00
0030Joint adhesive (401-11526)LFT4,000$0.47$0.47$0.47$1.00
0031Asphalt for tack coat (406-05521)SYS7,225$0.33$0.33$0.33$1.00
0032Guardrail, remove (601-02241)LFT100$7.00$7.00$20.00$24.00
0033Guardrail terminal system, W-beam, curved, type 7 (601-05071)EACH1$3,500.00$3,500.00$3,200.00$3,300.00
0034Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281)LFT144$25.00$25.00$22.00$24.00
0035Guardrail height transition, MGS (601-12289)EACH1$1,250.00$1,250.00$1,135.00$1,000.00
0036Guardrail transition, MGS without curb (601-12292)EACH4$3,425.00$3,425.00$3,350.00$3,600.00
0037Guardrail end treatment, type OS (601-94689)EACH3$3,175.00$3,175.00$2,275.00$3,100.00
0038Reinforced concrete bridge approach, 10 in. (609-06257)SYS132$275.00$155.00$205.00$155.00
0039HMA for approaches, type B (610-07487)TON194$115.00$115.00$115.00$115.00
0040Mailbox assembly, single (611-06497)EACH3$315.00$315.00$250.00$500.00
0041Monument, type B (615-06505)EACH2$1,155.00$1,155.00$1,700.00$1,200.00
0042Riprap, revetment (616-06405)TON130$67.00$67.00$70.00$165.00
0043Geotextile for riprap, type 1A (616-12246)SYS235$7.00$7.00$6.00$20.00
0044Clean steel bridge, QP-2, bridge no. 1 (619-11052)LS1$60,000$40,000$60,000$60,000
0045Coat steel bridge, bridge no. 1 (619-51859)LS1$30,000$15,000$30,000$30,000
0046Mobilization and demobilization for seeding (621-01004)EACH2$500.00$500.00$650.00$650.00
0047Erosion control blanket (621-02770)SYS3,000$2.75$2.75$1.52$2.00
0048Seed mixture, type R (621-06553)LBS345$9.25$9.25$7.38$7.38
0049Mulching material (621-06565)TON3$750.00$750.00$622.00$622.00
0050Water (621-06567)KGAL7$1.00$1.00$10.00$10.00
0051Topsoil (621-06570)CYS30$100.00$100.00$75.00$100.00
0052Sodding (621-06574)SYS1,845$6.75$6.75$6.65$6.65
0053Field office, type C (628-09403)MOS20$2,860.00$3,200.00$3,800.00$3,800.00
0054Computer system equipment (628-11976)EACH1$850.00$1,000.00$1,500.00$650.00
0055Topsoil processing and distribution (629-000149)SYS9,825$10.25$10.25$3.00$7.50
0056Topsoil amendment budget (629-000150)DOL19,650$1.00$1.00$1.00$1.00
0057Test pile, indicator, production (701-09558)LFT135$140.00$110.00$58.50$100.00
0058Test pile, indicator, restrike (701-09560)EACH2$3,000.00$2,600.00$2,000.00$2,500.00
0059Pile, steel pipe, 0.312 in., diameter 14 in. (701-09663)LFT575$98.00$99.00$123.75$70.00
0060Conical pile tip, 14 in. (701-09679)EACH12$500.00$550.00$325.00$400.00
0061Concrete, A, substructure (702-51005)CYS24$1,250.00$1,500.00$1,275.00$860.00
0062Reinforcing bars, epoxy coated (703-06029)LBS39,041$1.60$2.00$1.60$1.45
0063Threaded tie bar assembly, epoxy coated (703-97936)EACH26$64.00$51.00$47.75$60.00
0064Concrete, C, superstructure (704-51002)CYS111.20$1,500.00$1,600.00$1,400.00$1,200.00
0065Concrete bridge railing transition, type TPF-1 (706-06351)EACH4$9,000.00$2,500.00$4,850.00$4,000.00
0066Railing, steel type PF-1 , modified (706-11404)LFT244$265.00$282.00$563.00$350.00
0067Railing, concrete type PF-1 (706-11602)CYS14$2,200.00$1,000.00$1,875.00$2,200.00
0068Structural member, concrete, bulb-T beam, 42 in. X 49 in. (707-08158)LFT450$720.00$950.00$1,015.00$1,585.00
0069Repair , historical trusses, STR. no. 1 (708-05394)LS1$75,000$25,000$75,000$15,402
0070Structural steel (711-51035)LBS255$40.00$23.00$40.00$60.40
0071Pipe, type 4, circular, diameter 6 in. (715-05048)LFT200$40.00$19.00$7.00$4.50
0072Pipe, type 3, circular, diameter 12 in. (715-05168)LFT50$72.00$72.00$74.00$125.00
0073Pipe, type 3, circular, diameter 15 in. (715-05169)LFT275$74.00$74.00$82.00$75.00
0074Pipe, slotted drain, diameter 15 in. , .064 in. (715-05423)LFT50$350.00$350.00$255.00$275.00
0075Pipe end section, diameter 15 in. (715-46005)EACH4$950.00$950.00$1,025.00$1,800.00
0076Geotextile for underdrains, type 1B (718-12306)SYS180$5.00$11.00$6.00$7.00
0077Aggregate for underdrains (718-52610)CYS24$200.00$160.00$53.00$120.00
0078Inlet, type E7 (720-45030)EACH3$3,200.00$3,200.00$2,800.00$4,500.00
0079Inlet, type F7 (720-45035)EACH1$3,000.00$3,000.00$2,800.00$5,000.00
0080Longitudinal grooving (722-12732)SYS434$13.00$8.50$11.00$8.07
0081Face panels, concrete (731-93945)SFT3,105$111.00$145.00$120.00$111.00
0082Wall erection (731-93946)SFT3,105$21.00$35.00$21.00$38.00
0083Leveling pad, concrete (731-93947)LFT340$50.00$90.00$47.50$32.00
0084Road closure sign assembly (801-04308)EACH4$350.00$350.00$175.00$390.00
0085Detour route marker assembly (801-06625)EACH10$175.00$175.00$85.00$237.00
0086Construction sign, type A (801-06640)EACH4$225.00$225.00$175.00$306.00
0087Maintaining traffic (801-06775)LS1$2,500.00$12,695$185,000$485,000
0088Barricade, type III-A (801-07118)LFT48$18.00$18.00$25.00$23.10
0089Barricade, type III-B (801-07119)LFT48$18.00$18.00$25.00$23.10
0090Line, paint, solid, white, 4 in. (808-06713)LFT3,250$0.40$0.40$0.75$1.00
0091Line, paint, solid, yellow, 4 in. (808-06714)LFT3,250$0.40$0.40$0.75$1.00
INDOT contract B-42777-A: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

Every contract let that day: INDOT letting of March 11, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy