INDOT contract B-42829-A bid tabulation
BRIDGE REPLACEMENT. Let by Indiana DOT on January 15, 2025, Lake, LaPorte. 4 bids received; low bid $3,046,991 by Dunnet Bay Construction Company.
- Owner
- Indiana DOT
- Letting
- 15 JAN 2025
- Pay items
- 132
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Dunnet Bay Construction Company | $3,046,991 | Low |
| 2 | Rieth-Riley Construction Co., Inc. | $3,344,505 | +10% |
| 3 | Icc Group Inc | $3,588,000 | +18% |
| 4 | F H Paschen S N Nielsen & Associates LLC | $3,651,119 | +20% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Dunnet Bay Construction Company | 2. Rieth-Riley Construction Co., Inc. | 3. Icc Group Inc | 4. F H Paschen S N Nielsen & Associates LLC |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $234,379 | $63,980 | $46,000 | $100,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $150,000 | $168,000 | $178,908 | $182,500 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $90,000 | $7,778.06 | $107,000 | $109,000 |
| 0011 | Curb and gutter, remove (202-02279) | LFT | 775 | $10.00 | $13.16 | $5.00 | $7.24 |
| 0012 | Casting, remove (202-02772) | EACH | 3 | $100.00 | $1,016.78 | $400.00 | $573.58 |
| 0013 | Present structure, remove, structure no. 45-00259 (202-51330) | LS | 1 | $150,000 | $162,200 | $350,000 | $374,000 |
| 0014 | Sidewalk concrete, remove (202-52710) | SYS | 347 | $22.00 | $27.07 | $6.50 | $33.31 |
| 0015 | Excavation, common (203-02000) | CYS | 685 | $44.00 | $125.00 | $55.00 | $61.77 |
| 0016 | Excavation, waterway (203-51223) | CYS | 130 | $65.00 | $155.00 | $65.00 | $85.35 |
| 0017 | Stormwater management budget (205-12108) | DOL | 18,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0018 | Stormwater management implementation (205-12616) | LS | 1 | $15,000 | $11,416 | $49,810 | $2,211.00 |
| 0019 | Excavation, wet (206-51220) | CYS | 100 | $290.00 | $334.40 | $200.00 | $121.70 |
| 0020 | Cofferdam (206-51235) | LS | 1 | $275,000 | $220,620 | $378,000 | $400,000 |
| 0021 | Subgrade treatment, type II (207-08264) | SYS | 141 | $25.00 | $70.19 | $28.00 | $42.63 |
| 0022 | Subgrade treatment, type III (207-08266) | SYS | 637 | $3.50 | $5.71 | $5.00 | $5.05 |
| 0023 | Subgrade treatment, type IC (207-09935) | SYS | 1,978 | $37.00 | $65.71 | $45.00 | $34.14 |
| 0024 | Structure backfill, type 2 (211-09265) | CYS | 12 | $165.00 | $304.97 | $100.00 | $43.58 |
| 0025 | Structure backfill, type 4 (211-09267) | CYS | 22 | $265.00 | $314.94 | $200.00 | $180.57 |
| 0026 | Geogrid, type IB (214-11796) | SYS | 86 | $14.00 | $9.93 | $10.00 | $10.51 |
| 0027 | Geotextile for pavement, type 2B (214-12239) | SYS | 430 | $6.00 | $9.12 | $6.00 | $5.09 |
| 0028 | Compacted aggregate, no. 53 (301-12234) | CYS | 84 | $95.00 | $107.50 | $100.00 | $133.71 |
| 0029 | Subbase for PCCP (302-06464) | CYS | 108 | $125.00 | $174.82 | $125.00 | $222.45 |
| 0030 | Dense graded subbase (302-07455) | CYS | 25 | $95.00 | $200.57 | $85.00 | $128.07 |
| 0031 | Compacted aggregate, no. 53 (303-01180) | TON | 116 | $70.00 | $86.66 | $65.00 | $47.27 |
| 0032 | Milling, transition (306-08043) | SYS | 568 | $14.00 | $20.00 | $30.00 | $20.90 |
| 0033 | QC/QA-HMA, 2, 58S, surface, 9.5 MM (401-000001) | TON | 38 | $225.00 | $310.00 | $225.00 | $225.00 |
| 0034 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 184 | $180.00 | $163.00 | $180.00 | $180.00 |
| 0035 | QC/QA-HMA, 2, 58S, intermediate, 19.0 MM (401-000037) | TON | 52 | $155.00 | $240.00 | $155.00 | $155.00 |
| 0036 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 228 | $155.00 | $139.00 | $155.00 | $155.00 |
| 0037 | QC/QA-HMA, 3, 58S, base, 19.0 MM (401-000053) | TON | 546 | $120.00 | $116.00 | $120.00 | $120.00 |
| 0038 | Joint adhesive, surface (401-10258) | LFT | 1,472 | $0.10 | $2.00 | $0.10 | $0.10 |
| 0039 | Joint adhesive, intermediate (401-10259) | LFT | 1,122 | $0.10 | $2.00 | $0.10 | $0.10 |
| 0040 | Liquid asphalt sealant (401-11785) | LFT | 1,472 | $0.01 | $0.50 | $0.01 | $0.01 |
| 0041 | Asphalt for tack coat (406-05521) | SYS | 4,332 | $0.10 | $1.30 | $0.10 | $0.10 |
| 0042 | Guardrail transition, type TGB (601-01522) | EACH | 1 | $3,200.00 | $3,327.00 | $3,327.00 | $3,200.00 |
| 0043 | Guardrail terminal system, W-beam curved, type 3 (601-01846) | EACH | 1 | $3,300.00 | $3,151.00 | $3,151.00 | $3,300.00 |
| 0044 | Guardrail, remove (601-02241) | LFT | 345 | $4.00 | $5.00 | $5.00 | $4.00 |
| 0045 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 25 | $20.00 | $37.00 | $37.00 | $20.00 |
| 0046 | Guardrail transition, MGS without curb (601-12292) | EACH | 1 | $3,600.00 | $3,200.00 | $3,200.00 | $3,600.00 |
| 0047 | Guardrail end treatment, type OS (601-94689) | EACH | 1 | $2,975.00 | $3,296.00 | $3,296.00 | $2,975.00 |
| 0048 | Guardrail, W-beam, 6 FT 3 in. spacing (601-99105) | LFT | 50 | $23.00 | $39.00 | $39.00 | $23.00 |
| 0049 | Barrier delineator (602-06729) | EACH | 8 | $30.00 | $78.19 | $25.00 | $23.65 |
| 0050 | Curb and gutter, concrete (605-06140) | LFT | 404 | $60.00 | $57.49 | $60.00 | $60.00 |
| 0051 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 430 | $170.00 | $162.10 | $225.00 | $200.00 |
| 0052 | PCCP for approaches, 6 in. (610-08446) | SYS | 55 | $100.00 | $151.55 | $100.00 | $100.00 |
| 0053 | PCCP for approaches, 9 in. (610-09108) | SYS | 86 | $125.00 | $138.49 | $125.00 | $125.00 |
| 0054 | Monument, type B (615-06505) | EACH | 2 | $1,250.00 | $982.00 | $982.00 | $1,250.00 |
| 0055 | Plaque (615-08351) | EACH | 1 | $2,000.00 | $2,190.48 | $1,200.00 | $2,500.00 |
| 0056 | Riprap, revetment (616-06405) | TON | 708 | $75.00 | $119.71 | $150.00 | $95.68 |
| 0057 | Geotextile for riprap, type 1A (616-12246) | SYS | 832 | $2.50 | $2.69 | $3.00 | $4.79 |
| 0058 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $500.00 | $550.00 | $500.00 | $500.00 |
| 0059 | Erosion control blanket (621-02770) | SYS | 2,120 | $1.48 | $2.55 | $1.48 | $1.48 |
| 0060 | Mulched seeding, type U (621-06560) | SYS | 2,120 | $1.26 | $1.25 | $1.26 | $1.26 |
| 0061 | Water (621-06567) | KGAL | 1 | $100.00 | $1.00 | $100.00 | $100.00 |
| 0062 | Sodding, nursery (621-06575) | SYS | 121 | $14.00 | $23.50 | $14.00 | $14.00 |
| 0063 | Field office, type C (628-09403) | MOS | 12 | $2,700.00 | $3,450.21 | $2,200.00 | $2,300.00 |
| 0064 | Computer system equipment (628-11976) | EACH | 1 | $200.00 | $373.14 | $800.00 | $583.58 |
| 0065 | Dynamic pile load test (701-06011) | EACH | 1 | $8,000.00 | $8,440.94 | $6,500.00 | $5,256.05 |
| 0066 | Test pile, dynamic, production (701-09557) | LFT | 55 | $55.00 | $94.63 | $200.00 | $417.74 |
| 0067 | Test pile, indicator, production (701-09558) | LFT | 52 | $60.00 | $88.29 | $200.00 | $439.25 |
| 0068 | Test pile, dynamic, restrike (701-09559) | EACH | 1 | $5,000.00 | $829.65 | $10,000 | $4,779.69 |
| 0069 | Test pile, indicator, restrike (701-09560) | EACH | 1 | $5,000.00 | $829.65 | $5,000.00 | $1,529.69 |
| 0070 | Pile, steel pipe, 0.312 in., diameter 14 in. (701-09663) | LFT | 1,502 | $54.00 | $96.26 | $65.00 | $156.27 |
| 0071 | Conical pile tip, 14 in. (701-09679) | EACH | 38 | $620.00 | $355.59 | $450.00 | $305.90 |
| 0072 | Concrete, A, substructure (702-51005) | CYS | 258.20 | $600.00 | $904.77 | $1,000.00 | $850.00 |
| 0073 | Concrete, B, footings (702-51015) | CYS | 20 | $1,150.00 | $1,328.52 | $1,000.00 | $900.00 |
| 0074 | Concrete, foundation seal (702-51046) | CYS | 165.20 | $410.00 | $553.59 | $475.00 | $250.00 |
| 0075 | Threaded tie bar assembly (703-01540) | EACH | 80 | $52.00 | $73.57 | $50.00 | $51.51 |
| 0076 | Reinforcing bars (703-06028) | LBS | 18,186 | $1.50 | $1.63 | $1.50 | $1.37 |
| 0077 | Reinforcing bars, epoxy coated (703-06029) | LBS | 144,246 | $1.50 | $1.55 | $1.75 | $1.36 |
| 0078 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 388 | $46.00 | $55.13 | $50.00 | $51.30 |
| 0079 | Concrete, C, superstructure (704-51002) | CYS | 511.90 | $1,150.00 | $1,370.53 | $1,200.00 | $1,100.00 |
| 0080 | Concrete bridge railing transition, type TPF-1 (706-06351) | EACH | 2 | $4,200.00 | $5,500.00 | $6,000.00 | $3,748.31 |
| 0081 | Concrete bridge railing transition, type TPS-1 (706-06353) | EACH | 2 | $4,200.00 | $6,000.00 | $7,000.00 | $4,443.82 |
| 0082 | Railing, concrete type PS-1 (706-09961) | LFT | 111 | $75.00 | $175.00 | $200.00 | $174.00 |
| 0083 | Railing, concrete type PF-1 (706-09962) | LFT | 111 | $75.00 | $150.00 | $200.00 | $115.17 |
| 0084 | Railing, steel type PF-1 (706-11404) | LFT | 119 | $78.00 | $157.00 | $175.00 | $78.00 |
| 0085 | Railing, steel type PS-1 (706-11418) | LFT | 119 | $78.00 | $157.00 | $175.00 | $78.00 |
| 0086 | Surface seal , 45-00259 (709-51821) | LS | 1 | $1.00 | $1.00 | $4,800.00 | $500.00 |
| 0087 | Pipe, type 2, circular, diameter 12 in. (715-05149) | LFT | 34 | $100.00 | $236.39 | $100.00 | $120.05 |
| 0088 | Casting, type 4, furnish and adjust to grade (720-44025) | EACH | 1 | $3,200.00 | $1,557.26 | $1,000.00 | $1,182.04 |
| 0089 | Casting, type 7, furnish and adjust to grade (720-44040) | EACH | 1 | $3,200.00 | $1,487.52 | $1,000.00 | $1,109.78 |
| 0090 | Casting, type 8, furnish and adjust to grade (720-44045) | EACH | 2 | $3,200.00 | $1,965.35 | $1,000.00 | $1,605.34 |
| 0091 | Inlet, type E (720-96125) | EACH | 1 | $3,200.00 | $6,990.15 | $5,000.00 | $3,096.14 |
| 0092 | Longitudinal grooving (722-12732) | SYS | 956 | $7.50 | $10.86 | $4.49 | $6.06 |
| 0093 | Controller, reset timing (801-02595) | EACH | 4 | $207.58 | $207.58 | $207.58 | $207.58 |
| 0094 | Temporary pavement marking, removable, 4 in. (801-06207) | LFT | 14,805 | $1.41 | $1.41 | $1.41 | $1.41 |
| 0095 | Temporary pavement message marking, removable, lane indication arrow (801-06211) | EACH | 3 | $192.00 | $192.00 | $192.00 | $192.00 |
| 0096 | Temporary traffic signal installation, maintain (801-06539) | LS | 1 | $5,491.90 | $5,491.90 | $5,491.90 | $5,491.90 |
| 0097 | Temporary pavement marking, removable, 24 in. (801-06577) | LFT | 92 | $11.62 | $11.62 | $11.62 | $11.62 |
| 0098 | Construction sign, type A (801-06640) | EACH | 11 | $211.00 | $211.00 | $211.00 | $211.00 |
| 0099 | Construction sign, type B (801-06645) | EACH | 20 | $104.00 | $104.00 | $104.00 | $104.00 |
| 0100 | Flashing arrow sign (801-06710) | DAY | 480 | $15.00 | $15.00 | $15.00 | $15.00 |
| 0101 | Maintaining traffic (801-06775) | LS | 1 | $50,000 | $63,420 | $36,364 | $188,968 |
| 0102 | Energy absorbing terminal, CZ, TL-2 (801-07023) | EACH | 2 | $5,700.00 | $8,149.02 | $7,089.00 | $5,700.00 |
| 0103 | Barricade, type III-A (801-07118) | LFT | 57 | $15.48 | $15.48 | $15.48 | $15.48 |
| 0104 | Temporary traffic barrier, anchored, type 2 (801-08508) | LFT | 740 | $38.00 | $51.64 | $56.00 | $44.73 |
| 0105 | Temporary pedestrian channelizer (801-12862) | LFT | 30 | $88.95 | $88.95 | $88.95 | $127.30 |
| 0106 | Signal head relocate (801-94295) | EACH | 20 | $621.75 | $621.75 | $621.75 | $621.75 |
| 0107 | Sign, sheet, remove (802-04089) | EACH | 3 | $54.80 | $54.80 | $54.80 | $54.80 |
| 0108 | Sign post, square, type 1, unreinforced anchor base (802-05704) | LFT | 11 | $31.91 | $31.91 | $31.91 | $31.91 |
| 0109 | Sign, sheet, and supports, remove (802-07059) | EACH | 3 | $118.72 | $118.72 | $118.72 | $118.72 |
| 0110 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 8 | $28.25 | $28.25 | $28.25 | $28.25 |
| 0111 | Sign, ground mounted, reset (802-91122) | EACH | 1 | $164.39 | $164.39 | $164.39 | $164.39 |
| 0112 | Span, catenary, and tether (805-78415) | EACH | 1 | $4,077.44 | $4,077.44 | $4,077.44 | $4,077.44 |
| 0113 | Luminaire, mast arm, 8 FT (807-02780) | EACH | 2 | $1,231.92 | $1,231.92 | $1,231.92 | $1,231.92 |
| 0114 | Light structure, remove (807-03934) | EACH | 2 | $741.72 | $741.72 | $741.72 | $741.72 |
| 0115 | Light pole, ornamental (807-03951) | EACH | 2 | $7,663.31 | $7,663.31 | $7,663.31 | $7,663.31 |
| 0116 | Wire, no. 4 copper, in plastic duct, in trench, 4 1/C (807-07580) | LFT | 427 | $13.12 | $13.12 | $13.12 | $13.12 |
| 0117 | Luminaire, high lumen roadway (807-12199) | EACH | 2 | $960.43 | $960.43 | $960.43 | $960.43 |
| 0118 | Lighting foundation, conventional pole, concrete, with grounding (807-12791) | EACH | 2 | $2,699.42 | $2,699.42 | $2,699.42 | $2,699.42 |
| 0119 | Cable, pole circuit, THWN, no. 10 copper, stranded 1/C (807-86889) | LFT | 264 | $1.58 | $1.58 | $1.58 | $1.58 |
| 0120 | Connector kit, unfused (807-86910) | EACH | 4 | $43.06 | $43.06 | $43.06 | $43.06 |
| 0121 | Connector kit, fused (807-86915) | EACH | 4 | $43.06 | $43.06 | $43.06 | $43.06 |
| 0122 | Insulation link, waterproofed (807-86935) | EACH | 8 | $28.42 | $28.42 | $28.42 | $28.42 |
| 0123 | Line, remove (808-06716) | LFT | 5,567 | $0.51 | $0.51 | $0.51 | $0.51 |
| 0124 | Retro-reflectivity testing (808-09381) | LS | 1 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 0125 | Line, multi-component, broken, white, 4 in. (808-10031) | LFT | 1,863 | $1.21 | $1.21 | $1.21 | $1.21 |
| 0126 | Line, multi-component, solid, yellow, 4 in. (808-10034) | LFT | 10,247 | $1.02 | $1.02 | $1.02 | $1.02 |
| 0127 | Line, multi-component, solid, white, 8 in. (808-10037) | LFT | 150 | $4.09 | $4.09 | $4.09 | $4.09 |
| 0128 | Grooving for pavement markings (808-12032) | LFT | 8,173 | $0.72 | $0.72 | $0.72 | $0.72 |
| 0129 | Transverse marking, thermoplastic, crosshatch line, yellow, 24 in. (808-75290) | LFT | 71 | $13.21 | $13.21 | $13.21 | $13.21 |
| 0130 | Transverse marking, thermoplastic, stop line, white, 24 in. (808-75297) | LFT | 60 | $13.21 | $13.21 | $13.21 | $13.21 |
| 0131 | Transverse marking, thermoplastic, crosswalk line, white, 6 in. (808-75300) | LFT | 112 | $3.44 | $3.44 | $3.44 | $3.44 |
| 0132 | Pavement message marking, thermoplastic, lane indication arrow (808-75320) | EACH | 1 | $231.00 | $231.00 | $231.00 | $231.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of January 15, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.