INDOT contract B-42832-A bid tabulation
BRIDGE REPLACEMENT. Let by Indiana DOT on January 15, 2025, Porter, LaPorte. 5 bids received; low bid $1,316,580 by Dunnet Bay Construction Company.
- Owner
- Indiana DOT
- Letting
- 15 JAN 2025
- Pay items
- 81
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Dunnet Bay Construction Company | $1,316,580 | Low |
| 2 | F H Paschen S N Nielsen & Associates LLC | $1,622,094 | +23% |
| 3 | Milestone Contractors LP | $1,649,040 | +25% |
| 4 | Gariup Construction Co Inc | $1,685,700 | +28% |
| 5 | Rieth-Riley Construction Co., Inc. | $1,791,353 | +36% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Dunnet Bay Construction Company | 2. F H Paschen S N Nielsen & Associates LLC | 3. Milestone Contractors LP | 4. Gariup Construction Co Inc | 5. Rieth-Riley Construction Co., Inc. |
|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $156,364 | $68,958 | $27,500 | $25,000 | $50,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $65,000 | $81,000 | $82,450 | $139,088 | $86,000 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $25,000 | $32,500 | $22,500 | $70,000 | $50,000 |
| 0011 | Present structure, remove, structure no. 64-00098 (202-51330) | LS | 1 | $100,000 | $150,000 | $178,000 | $120,000 | $298,722 |
| 0012 | Sign, remove (202-74035) | EACH | 4 | $100.00 | $102.00 | $100.00 | $120.00 | $102.00 |
| 0013 | Pipe, remove (202-96133) | LFT | 140 | $7.00 | $51.89 | $25.00 | $25.00 | $35.00 |
| 0014 | Excavation, common (203-02000) | CYS | 520 | $46.00 | $87.09 | $80.00 | $65.00 | $78.00 |
| 0015 | Stormwater management budget (205-12108) | DOL | 14,571 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0016 | Stormwater management implementation (205-12616) | LS | 1 | $39,730 | $5,000.00 | $5,000.00 | $2,500.00 | $22,000 |
| 0017 | SWQCP preparation (205-12618) | LS | 1 | $1,800.00 | $2,350.00 | $1,800.00 | $45,000 | $1,800.00 |
| 0018 | Excavation, foundation, unclassified (206-51230) | CYS | 390 | $55.00 | $37.80 | $65.00 | $80.00 | $1.00 |
| 0019 | Subgrade treatment, type II (207-08264) | SYS | 52 | $28.00 | $44.07 | $60.00 | $30.00 | $73.00 |
| 0020 | Subgrade treatment, type IC (207-09935) | SYS | 1,643 | $37.00 | $46.16 | $55.00 | $25.00 | $45.00 |
| 0021 | Aggregate for end bent backfill (211-06467) | CYS | 85 | $80.00 | $78.99 | $155.00 | $85.00 | $136.00 |
| 0022 | Structure backfill, type 1 (211-09264) | CYS | 5 | $150.00 | $96.00 | $170.00 | $300.00 | $255.00 |
| 0023 | Geogrid, type IB (214-11796) | SYS | 1,643 | $2.50 | $3.16 | $3.25 | $5.00 | $2.76 |
| 0024 | Geotextile for pavement, type 2B (214-12239) | SYS | 184 | $6.50 | $9.28 | $10.25 | $12.00 | $7.76 |
| 0025 | Subbase for PCCP (302-06464) | CYS | 46 | $125.00 | $223.55 | $230.00 | $100.00 | $162.00 |
| 0026 | Dense graded subbase (302-07455) | CYS | 8 | $105.00 | $132.46 | $305.32 | $200.00 | $201.00 |
| 0027 | Compacted aggregate, no. 53 (303-01180) | TON | 128 | $110.00 | $49.85 | $80.00 | $60.00 | $58.00 |
| 0028 | Widening with HMA, type B (304-07493) | TON | 13 | $535.00 | $535.00 | $575.00 | $600.00 | $640.00 |
| 0029 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 112 | $50.00 | $57.23 | $60.00 | $22.00 | $48.00 |
| 0030 | QC/QA-HMA, 2, 58S, surface, 9.5 MM (401-000001) | TON | 128 | $126.00 | $126.00 | $195.00 | $145.00 | $126.00 |
| 0031 | QC/QA-HMA, 2, 58S, intermediate, 19.0 MM (401-000037) | TON | 198 | $106.00 | $106.00 | $160.00 | $120.00 | $106.00 |
| 0032 | QC/QA-HMA, 2, 58S, base, 25.0 MM (401-000046) | TON | 242 | $110.00 | $110.00 | $140.00 | $160.00 | $110.00 |
| 0033 | Joint adhesive, surface (401-10258) | LFT | 470 | $3.10 | $3.10 | $0.01 | $4.00 | $3.10 |
| 0034 | Joint adhesive, intermediate (401-10259) | LFT | 520 | $2.80 | $2.80 | $0.01 | $3.50 | $2.80 |
| 0035 | Liquid asphalt sealant (401-11785) | LFT | 470 | $1.20 | $1.20 | $0.01 | $1.50 | $1.20 |
| 0036 | Asphalt for tack coat (406-05520) | TON | 2 | $1,600.00 | $1,600.00 | $0.01 | $1,800.00 | $1,600.00 |
| 0037 | Guardrail transition, type TGB (601-01522) | EACH | 1 | $3,200.00 | $3,200.00 | $3,200.00 | $3,600.00 | $3,200.00 |
| 0038 | Guardrail terminal system, W-beam curved, type 3 (601-01846) | EACH | 1 | $2,500.00 | $2,500.00 | $2,500.00 | $2,800.00 | $2,500.00 |
| 0039 | Guardrail, remove (601-02241) | LFT | 123 | $3.00 | $3.00 | $3.00 | $3.50 | $3.00 |
| 0040 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 38 | $27.00 | $27.00 | $27.00 | $30.00 | $27.00 |
| 0041 | Guardrail transition, MGS without curb (601-12292) | EACH | 3 | $3,100.00 | $3,100.00 | $3,100.00 | $3,500.00 | $3,100.00 |
| 0042 | Guardrail end treatment, type OS (601-94689) | EACH | 3 | $3,000.00 | $3,000.00 | $3,000.00 | $3,400.00 | $3,000.00 |
| 0043 | Guardrail, W-beam, 6 FT 3 in. spacing (601-99105) | LFT | 44 | $31.00 | $31.00 | $31.00 | $35.00 | $31.00 |
| 0044 | Barrier delineator (602-06729) | EACH | 8 | $20.00 | $23.65 | $30.00 | $90.00 | $62.00 |
| 0045 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 184 | $180.00 | $185.00 | $230.00 | $200.00 | $165.00 |
| 0046 | PCCP for approaches, 6 in. (610-08446) | SYS | 43 | $98.00 | $119.12 | $140.00 | $110.00 | $170.00 |
| 0047 | Mailbox assembly, single (611-06497) | EACH | 1 | $200.00 | $200.00 | $200.00 | $230.00 | $200.00 |
| 0048 | Monument, type B (615-06505) | EACH | 2 | $976.00 | $976.00 | $976.00 | $1,100.00 | $976.00 |
| 0049 | Riprap, class 1 (616-05688) | TON | 750 | $60.00 | $75.00 | $155.00 | $110.00 | $112.00 |
| 0050 | Riprap, revetment (616-06405) | TON | 38 | $100.00 | $150.00 | $155.00 | $130.00 | $130.00 |
| 0051 | Geotextile for riprap, type 1A (616-12246) | SYS | 1,164 | $1.50 | $4.05 | $1.25 | $6.00 | $3.00 |
| 0052 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $500.00 | $500.00 | $500.00 | $1,000.00 | $500.00 |
| 0053 | Mulched seeding, type R (621-06559) | SYS | 2,078 | $1.15 | $1.15 | $1.15 | $1.30 | $1.15 |
| 0054 | Water (621-06567) | KGAL | 1 | $100.00 | $100.00 | $100.00 | $120.00 | $100.00 |
| 0055 | Sodding (621-06574) | SYS | 218 | $11.50 | $11.50 | $11.50 | $13.00 | $11.50 |
| 0056 | Test pile, indicator, production (701-09558) | LFT | 181 | $250.00 | $145.02 | $95.00 | $150.00 | $88.00 |
| 0057 | Test pile, indicator, restrike (701-09560) | EACH | 2 | $5,000.00 | $1,738.17 | $2,350.00 | $6,500.00 | $7,000.00 |
| 0058 | Pile shoe, HP 12 X 63 (701-09682) | EACH | 12 | $140.00 | $142.96 | $150.00 | $250.00 | $200.00 |
| 0059 | Pile, steel H, HP, 12 X 63 (701-93658) | LFT | 802 | $40.00 | $135.64 | $115.00 | $175.00 | $80.00 |
| 0060 | Concrete, C, substructure (702-92857) | CYS | 48.80 | $1,200.00 | $1,150.00 | $1,605.00 | $1,800.00 | $1,700.00 |
| 0061 | Reinforcing bars, epoxy coated (703-06029) | LBS | 58,227 | $1.50 | $1.42 | $1.80 | $1.85 | $1.65 |
| 0062 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 34 | $52.00 | $52.34 | $60.00 | $50.00 | $60.00 |
| 0063 | Concrete, C, superstructure (704-51002) | CYS | 106.80 | $970.00 | $1,625.00 | $1,740.00 | $1,000.00 | $1,600.00 |
| 0064 | Railing, concrete type FC (706-11600) | CYS | 15.20 | $990.00 | $1,650.00 | $1,550.00 | $1,500.00 | $1,410.00 |
| 0065 | Concrete bridge railing transition, type TFC (706-11620) | EACH | 4 | $3,200.00 | $3,000.00 | $4,500.00 | $3,100.00 | $4,500.00 |
| 0066 | Structural member, concrete, bulb-T beam, 36 in. X 49 in. (707-09865) | LFT | 311 | $500.00 | $625.00 | $710.00 | $775.00 | $834.00 |
| 0067 | Surface seal (709-51821) | LS | 1 | $1.00 | $500.00 | $0.01 | $2,600.00 | $2,300.00 |
| 0068 | Pipe, type 3, circular, diameter 15 in. (715-05169) | LFT | 50 | $85.00 | $81.77 | $75.00 | $190.00 | $88.00 |
| 0069 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 168 | $20.00 | $22.11 | $15.00 | $80.00 | $7.00 |
| 0070 | Pipe end section, diameter 15 in. (715-46005) | EACH | 2 | $950.00 | $1,692.98 | $1,350.00 | $1,200.00 | $1,500.00 |
| 0071 | Longitudinal grooving (722-12732) | SYS | 447 | $10.00 | $8.73 | $8.73 | $16.00 | $12.00 |
| 0072 | Road closure sign assembly (801-04308) | EACH | 4 | $258.00 | $258.00 | $350.00 | $400.00 | $350.00 |
| 0073 | Detour route marker assembly (801-06625) | EACH | 24 | $158.00 | $158.00 | $175.00 | $195.00 | $175.00 |
| 0074 | Construction sign, type A (801-06640) | EACH | 13 | $211.00 | $211.00 | $200.00 | $225.00 | $200.00 |
| 0075 | Maintaining traffic (801-06775) | LS | 1 | $15,000 | $150,885 | $18,500 | $30,000 | $80,000 |
| 0076 | Barricade, type III-A (801-07118) | LFT | 48 | $15.21 | $15.21 | $15.00 | $17.00 | $15.00 |
| 0077 | Barricade, type III-B (801-07119) | LFT | 24 | $15.21 | $15.21 | $15.00 | $17.00 | $15.00 |
| 0078 | Sign, ground mounted, reset (802-91122) | EACH | 1 | $205.00 | $205.00 | $205.00 | $230.00 | $205.00 |
| 0079 | Line, multi-component, solid, white, 4 in. (808-10033) | LFT | 1,200 | $1.18 | $1.18 | $2.00 | $3.00 | $2.00 |
| 0080 | Line, multi-component, solid, yellow, 4 in. (808-10034) | LFT | 1,200 | $1.18 | $1.18 | $2.00 | $3.00 | $2.00 |
| 0081 | Grooving for pavement markings (808-12032) | LFT | 1,876 | $0.73 | $0.73 | $0.85 | $1.00 | $0.85 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of January 15, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.