INDOT contract B-42837-A bid tabulation
SUPERSTRUCTURE REPLACEMENT. Let by Indiana DOT on March 12, 2025, Laporte, LaPorte. 4 bids received; low bid $1,168,561 by Milestone Contractors LP.
- Owner
- Indiana DOT
- Letting
- 12 MAR 2025
- Pay items
- 67
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Milestone Contractors LP | $1,168,561 | Low |
| 2 | Rieth-Riley Construction Co., Inc. | $1,226,826 | +5.0% |
| 3 | Laporte Construction Company Inc | $1,388,845 | +19% |
| 4 | Superior Construction Co Inc | $1,619,800 | +39% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Milestone Contractors LP | 2. Rieth-Riley Construction Co., Inc. | 3. Laporte Construction Company Inc | 4. Superior Construction Co Inc |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $12,000 | $22,500 | $17,255 | $54,117 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $57,500 | $61,000 | $65,000 | $80,000 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $30,000 | $24,000 | $12,743 | $48,000 |
| 0011 | Pavement removal (202-02240) | SYS | 167 | $35.00 | $55.00 | $52.44 | $26.00 |
| 0012 | Present structure, remove portions, structure no. 1 (202-51328) | LS | 1 | $125,000 | $170,000 | $271,664 | $620,000 |
| 0013 | Excavation, common (203-02000) | CYS | 140 | $75.00 | $150.00 | $93.07 | $50.00 |
| 0015 | Stormwater management budget (205-12108) | DOL | 16,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0016 | Stormwater management implementation (205-12616) | LS | 1 | $4,500.00 | $12,500 | $9,800.00 | $20,000 |
| 0017 | Cofferdam (206-51235) | LS | 1 | $5,000.00 | $33,500 | $149,157 | $1.00 |
| 0018 | Subgrade treatment, type II (207-08264) | SYS | 25 | $55.00 | $88.00 | $57.69 | $90.00 |
| 0019 | Subgrade treatment, type IC (207-09935) | SYS | 735 | $50.00 | $46.00 | $64.70 | $60.00 |
| 0020 | Aggregate for end bent backfill (211-06467) | CYS | 18 | $250.00 | $140.00 | $171.70 | $140.00 |
| 0021 | Geotextile for pavement, type 2B (214-12239) | SYS | 903 | $6.00 | $4.00 | $4.34 | $8.00 |
| 0022 | Compacted aggregate, no. 53 (301-12234) | CYS | 14 | $225.00 | $200.00 | $172.88 | $275.00 |
| 0023 | Subbase for PCCP (302-06464) | CYS | 42 | $190.00 | $94.00 | $189.71 | $160.00 |
| 0024 | Compacted aggregate, no. 53 (303-01180) | TON | 92 | $65.00 | $65.00 | $116.62 | $68.00 |
| 0025 | Milling, transition (306-08043) | SYS | 230 | $20.00 | $23.00 | $15.74 | $11.00 |
| 0026 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 70 | $295.00 | $188.00 | $295.00 | $295.00 |
| 0027 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 86 | $220.00 | $165.00 | $220.00 | $220.00 |
| 0028 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 213 | $160.00 | $153.00 | $160.00 | $160.00 |
| 0029 | Joint adhesive, surface (401-10258) | LFT | 293 | $1.00 | $0.10 | $1.00 | $1.00 |
| 0030 | Joint adhesive, intermediate (401-10259) | LFT | 244 | $1.00 | $0.10 | $1.00 | $1.00 |
| 0031 | Asphalt for tack coat (406-05521) | SYS | 1,270 | $0.25 | $5.00 | $0.25 | $0.25 |
| 0032 | Guardrail, remove (601-02241) | LFT | 335 | $5.00 | $5.00 | $5.00 | $5.00 |
| 0033 | Guardrail, thrie-beam, 6 FT 3 in. spacing , modified (601-04150) | LFT | 29 | $88.00 | $88.00 | $88.00 | $88.00 |
| 0034 | Guardrail transition, type TGS-1 (601-06374) | EACH | 3 | $1,235.00 | $1,235.00 | $1,235.00 | $1,235.00 |
| 0035 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 38 | $31.00 | $31.00 | $31.00 | $31.00 |
| 0036 | Guardrail height transition, MGS (601-12289) | EACH | 1 | $1,353.00 | $1,353.00 | $1,353.00 | $1,353.00 |
| 0037 | Guardrail end treatment, type OS (601-94689) | EACH | 2 | $3,138.00 | $3,138.00 | $3,138.00 | $3,138.00 |
| 0038 | Reinforced concrete bridge approach, 10 in. (609-06257) | SYS | 168 | $225.00 | $185.00 | $125.00 | $150.00 |
| 0039 | HMA for approaches, type B (610-07487) | TON | 6 | $400.00 | $775.00 | $175.00 | $400.00 |
| 0040 | Mailbox assembly, reset, single (611-08232) | EACH | 1 | $391.00 | $391.00 | $391.00 | $391.00 |
| 0041 | Right-of-way marker (615-06490) | EACH | 6 | $169.00 | $169.00 | $169.00 | $169.00 |
| 0042 | Riprap, revetment (616-06405) | TON | 218 | $160.00 | $260.00 | $226.99 | $120.00 |
| 0043 | Geotextile for riprap, type 2A (616-12248) | SYS | 346 | $2.50 | $9.00 | $4.83 | $13.00 |
| 0044 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $300.00 | $600.00 | $300.00 | $600.00 |
| 0045 | Mulched seeding, type R (621-06559) | SYS | 455 | $3.98 | $2.00 | $3.98 | $2.00 |
| 0047 | Field drilled hole in concrete (702-51863) | EACH | 136 | $15.00 | $24.00 | $24.26 | $35.00 |
| 0048 | Reinforcing bars, epoxy coated (703-06029) | LBS | 39,854 | $2.00 | $1.45 | $1.28 | $1.30 |
| 0049 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 28 | $30.00 | $60.00 | $47.64 | $48.00 |
| 0050 | Concrete, C, superstructure (704-51002) | CYS | 118.40 | $1,900.00 | $1,450.00 | $1,500.00 | $1,200.00 |
| 0051 | Railing, steel type TS-1 (706-06344) | LFT | 254 | $114.00 | $150.00 | $114.00 | $145.00 |
| 0052 | Structural member, concrete, box beam, 17 in. X 36 in. (707-11443) | LFT | 491 | $425.00 | $400.00 | $362.19 | $300.00 |
| 0053 | Patching concrete structures (710-09158) | SFT | 60 | $125.00 | $256.00 | $256.00 | $200.00 |
| 0054 | Pipe, type 4, circular, diameter 18 in. (715-05209) | LFT | 50 | $45.00 | $123.00 | $125.75 | $68.00 |
| 0055 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 108 | $13.00 | $22.00 | $29.22 | $18.00 |
| 0056 | Pipe end section, diameter 18 in. (715-46010) | EACH | 1 | $1,000.00 | $2,115.00 | $1,098.85 | $1,100.00 |
| 0057 | Geotextile for underdrains, type 2B (718-12308) | SYS | 60 | $10.00 | $22.00 | $18.63 | $15.00 |
| 0058 | Automatic drainage gate, diameter 18 in. (721-43010) | EACH | 1 | $2,500.00 | $4,570.00 | $2,495.00 | $5,700.00 |
| 0059 | Longitudinal grooving (722-12732) | SYS | 537 | $11.50 | $11.00 | $11.99 | $15.00 |
| 0060 | Bearing assembly, elastomeric (726-92406) | EACH | 24 | $1,500.00 | $1,550.00 | $2,307.89 | $1,700.00 |
| 0061 | Road closure sign assembly (801-04308) | EACH | 5 | $218.00 | $218.00 | $218.00 | $218.00 |
| 0062 | Detour route marker assembly (801-06625) | EACH | 18 | $133.00 | $133.00 | $133.00 | $133.00 |
| 0063 | Construction sign, type A (801-06640) | EACH | 11 | $158.00 | $158.00 | $158.00 | $158.00 |
| 0064 | Maintaining traffic (801-06775) | LS | 1 | $15,000 | $28,500 | $6,199.86 | $50,000 |
| 0065 | Barricade, type III-A (801-07118) | LFT | 48 | $13.55 | $13.55 | $13.55 | $13.55 |
| 0066 | Barricade, type III-B (801-07119) | LFT | 72 | $13.55 | $13.55 | $13.55 | $13.55 |
| 0067 | Line, paint, solid, white, 4 in. (808-06713) | LFT | 950 | $1.05 | $1.05 | $1.05 | $1.05 |
| 0068 | Line, paint, solid, yellow, 4 in. (808-06714) | LFT | 950 | $1.05 | $1.05 | $1.05 | $1.05 |
| 0069 | Field office, type C (628-09403) | MOS | 10 | $3,500.00 | $3,360.00 | $3,000.00 | $2,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of March 12, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.