INDOT contract B-43233-A bid tabulation
SMALL STRUCTURE REPLACEMENT. Let by Indiana DOT on January 14, 2026, Martin, Vincennes. 5 bids received; low bid $1,467,300 by Blankenberger Brothers Inc.
- Owner
- Indiana DOT
- Letting
- 14 JAN 2026
- Pay items
- 76
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Blankenberger Brothers Inc | $1,467,300 | Low |
| 2 | Ragle, Inc. | $1,559,189 | +6.0% |
| 3 | E & B Paving LLC | $1,760,600 | +20% |
| 4 | Milestone Contractors LP | $1,912,380 | +30% |
| 5 | Morphey Construction Inc. | $1,976,000 | +35% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Blankenberger Brothers Inc | 2. Ragle, Inc. | 3. E & B Paving LLC | 4. Milestone Contractors LP | 5. Morphey Construction Inc. |
|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $20,000 | $37,000 | $15,500 | $10,800 | $10,800 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $73,350 | $77,200 | $87,482 | $92,900 | $100,000 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $44,000 | $45,150 | $30,500 | $57,250 | $15,000 |
| 0011 | Present structure, remove, structure no. CV 231-051-58.09 (202-51330) | LS | 1 | $25,000 | $25,000 | $38,500 | $55,000 | $18,000 |
| 0012 | Pipe, remove (202-96133) | LFT | 50 | $60.80 | $21.00 | $19.00 | $33.05 | $45.00 |
| 0013 | Excavation, common (203-02000) | CYS | 655 | $58.65 | $60.00 | $158.00 | $49.00 | $65.00 |
| 0014 | Borrow (203-02070) | CYS | 1,060 | $37.50 | $24.00 | $48.00 | $83.00 | $55.00 |
| 0015 | Excavation, waterway (203-51223) | CYS | 5 | $75.00 | $213.00 | $158.00 | $260.00 | $140.00 |
| 0016 | Settlement plate (204-02290) | EACH | 1 | $2,100.00 | $780.00 | $4,550.00 | $3,000.00 | $5,000.00 |
| 0017 | Pump around (205-11626) | EACH | 1 | $45,700 | $18,118 | $25,000 | $37,000 | $50,000 |
| 0018 | Stormwater management budget (205-12108) | DOL | 24,235 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0019 | Stormwater management implementation (205-12616) | LS | 1 | $20,000 | $5,383.00 | $10,100 | $25,000 | $750.00 |
| 0020 | Subgrade treatment, type IC (207-09935) | SYS | 1,120 | $39.35 | $38.00 | $37.75 | $49.00 | $58.00 |
| 0021 | Structure backfill, type 2 (211-09265) | CYS | 64 | $73.35 | $88.00 | $105.00 | $189.00 | $100.00 |
| 0022 | Structure backfill, type 5 (211-09268) | CYS | 368 | $180.00 | $280.00 | $220.00 | $310.00 | $250.00 |
| 0023 | Geotextile for pavement, type 2A (214-12238) | SYS | 1,126 | $4.40 | $4.00 | $2.60 | $5.90 | $4.00 |
| 0024 | Geotextile for pavement, type 2B (214-12239) | SYS | 924 | $4.20 | $4.50 | $2.90 | $5.40 | $5.00 |
| 0025 | Compacted aggregate, no. 8 (301-12233) | CYS | 275 | $92.75 | $110.00 | $194.00 | $206.00 | $128.00 |
| 0026 | Compacted aggregate, no. 53 (303-01180) | TON | 718 | $51.00 | $44.50 | $55.50 | $63.00 | $47.00 |
| 0027 | Widening with HMA, type C (304-07494) | TON | 88 | $175.00 | $195.00 | $210.00 | $365.00 | $330.00 |
| 0028 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 1,876 | $4.20 | $2.00 | $4.85 | $5.50 | $6.00 |
| 0029 | Milling, transition (306-08043) | SYS | 437 | $7.30 | $2.50 | $5.80 | $20.00 | $12.00 |
| 0030 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 268 | $154.00 | $154.00 | $154.00 | $250.00 | $154.00 |
| 0031 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 150 | $188.00 | $188.00 | $188.00 | $208.00 | $188.00 |
| 0032 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 388 | $127.00 | $127.00 | $127.00 | $160.00 | $127.00 |
| 0033 | Joint adhesive (401-11526) | LFT | 2,689 | $1.75 | $1.75 | $1.75 | $1.12 | $1.75 |
| 0034 | Asphalt for tack coat (406-05520) | TON | 3 | $650.00 | $650.00 | $650.00 | $735.00 | $650.00 |
| 0035 | Cracks in asphalt pavement, fill (408-12028) | TON | 0.20 | $850.00 | $850.00 | $850.00 | $4,190.00 | $850.00 |
| 0036 | Guardrail, remove (601-02241) | LFT | 554 | $7.50 | $7.50 | $6.00 | $7.50 | $6.00 |
| 0037 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 293.75 | $22.00 | $22.00 | $24.00 | $22.00 | $24.00 |
| 0038 | Guardrail, MGS, long span, type 2 (601-12288) | EACH | 2 | $1,200.00 | $1,200.00 | $1,586.00 | $1,200.00 | $1,586.00 |
| 0039 | Guardrail end treatment, type OS (601-94689) | EACH | 4 | $2,300.00 | $2,300.00 | $3,287.00 | $2,300.00 | $3,287.00 |
| 0040 | Milled HMA corrugations, sinusoidal (606-12400) | LFT | 550 | $4.00 | $9.95 | $2.00 | $9.95 | $25.00 |
| 0041 | Right-of-way marker (615-06490) | EACH | 6 | $175.00 | $175.00 | $176.00 | $175.00 | $176.00 |
| 0042 | Riprap, revetment (616-06405) | TON | 323 | $89.80 | $70.50 | $120.00 | $82.00 | $190.00 |
| 0043 | Geotextile for riprap, type 1A (616-12246) | SYS | 520 | $3.75 | $2.80 | $2.85 | $5.78 | $4.00 |
| 0044 | Mobilization and demobilization for seeding (621-01004) | EACH | 3 | $900.00 | $300.00 | $900.00 | $300.00 | $300.00 |
| 0045 | Erosion control blanket (621-02770) | SYS | 521 | $2.50 | $4.00 | $2.50 | $4.00 | $14.00 |
| 0046 | Fertilizer for permanent seeding (621-06545) | TON | 1 | $800.00 | $50.00 | $800.00 | $50.00 | $50.00 |
| 0047 | Seed mixture, type R (621-06553) | LBS | 203 | $4.50 | $20.00 | $4.50 | $20.00 | $155.00 |
| 0048 | Mulching material (621-06565) | TON | 2 | $510.00 | $650.00 | $510.00 | $650.00 | $650.00 |
| 0049 | Computer system equipment (628-11976) | EACH | 2 | $550.00 | $1,366.00 | $500.00 | $1,500.00 | $800.00 |
| 0050 | Field office, type D (628-12683) | MOS | 12 | $2,860.00 | $3,000.00 | $3,100.00 | $3,500.00 | $2,500.00 |
| 0051 | Test pile, indicator, production (701-09558) | LFT | 107 | $99.25 | $100.00 | $240.00 | $150.00 | $75.00 |
| 0052 | Test pile, indicator, restrike (701-09560) | EACH | 2 | $2,500.00 | $2,624.00 | $1,500.00 | $6,000.00 | $4,500.00 |
| 0053 | Pile shoe, HP 12 X 74 (701-09683) | EACH | 28 | $150.00 | $150.00 | $115.00 | $230.00 | $165.00 |
| 0054 | Pile, steel H, HP 12 X 74 (701-95780) | LFT | 1,125 | $95.75 | $140.00 | $220.00 | $135.00 | $75.00 |
| 0055 | Temporary shoring (702-04325) | LS | 1 | $25,000 | $35,000 | $53,250 | $43,646 | $250,000 |
| 0056 | Concrete, foundation seal (702-51046) | CYS | 15 | $550.00 | $360.00 | $695.00 | $1,300.00 | $830.00 |
| 0057 | Waterproofing membrane, type 2 (714-000086) | SFT | 1,967 | $3.40 | $3.75 | $5.00 | $6.00 | $8.00 |
| 0058 | Pipe, type 3, circular, diameter 24 in. (715-05173) | LFT | 60 | $120.95 | $118.00 | $161.00 | $130.00 | $215.00 |
| 0059 | Pipe end section, diameter 24 in. (715-46020) | EACH | 2 | $1,800.00 | $1,208.00 | $1,500.00 | $1,350.00 | $2,700.00 |
| 0060 | Structure, coated reinforced concrete, three-sided sections, 216 in. X 120 in. (723-000179) | LFT | 52 | $6,500.00 | $7,400.00 | $6,475.00 | $7,525.00 | $8,500.00 |
| 0061 | Construction sign, type D (801-03291) | EACH | 1 | $175.00 | $255.00 | $175.00 | $195.00 | $125.00 |
| 0062 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 4,031 | $1.55 | $1.71 | $1.65 | $3.15 | $1.85 |
| 0063 | Temporary pavement marking, removable, 24 in. (801-06577) | LFT | 43 | $10.85 | $11.04 | $10.85 | $14.95 | $10.00 |
| 0064 | Construction sign, type A (801-06640) | EACH | 18 | $185.00 | $209.00 | $185.00 | $165.00 | $175.00 |
| 0065 | Construction sign, type B (801-06645) | EACH | 7 | $115.00 | $104.00 | $115.00 | $120.00 | $75.00 |
| 0066 | Maintaining traffic (801-06775) | LS | 1 | $53,056 | $37,700 | $25,000 | $38,000 | $110,784 |
| 0067 | Energy absorbing terminal, CZ, TL-2 (801-07023) | EACH | 3 | $6,300.00 | $6,300.00 | $8,137.67 | $6,300.00 | $7,571.00 |
| 0068 | Temporary traffic barrier, anchored, type 2 (801-08508) | LFT | 820 | $60.00 | $66.50 | $57.50 | $90.00 | $48.00 |
| 0069 | Portable signal (801-12081) | LS | 1 | $30,000 | $31,510 | $48,875 | $36,000 | $18,000 |
| 0070 | Driveway assistance device (801-12482) | EACH | 1 | $10,000 | $3,416.00 | $4,775.00 | $6,000.00 | $2,820.00 |
| 0071 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 4 | $750.00 | $994.00 | $750.00 | $850.00 | $350.00 |
| 0072 | Grooving for pavement markings (808-12032) | LFT | 1,240 | $0.90 | $2.98 | $0.90 | $0.95 | $2.00 |
| 0073 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 1,100 | $1.25 | $2.00 | $1.25 | $1.25 | $3.00 |
| 0074 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 6 | $25.00 | $14.55 | $24.75 | $50.00 | $10.00 |
| 0075 | Snowplowable raised pavement marker (808-75998) | EACH | 5 | $75.00 | $201.45 | $75.00 | $125.00 | $150.00 |
| 0076 | Line, thermoplastic, broken, yellow, 6 in. (808-96078) | LFT | 140 | $1.50 | $6.00 | $1.50 | $2.95 | $3.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of January 14, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.