INDOT contract B-43559-A bid tabulation
SMALL STRUCTURE REPLACEMENT. Let by Indiana DOT on April 9, 2025, Union, Greenfield. 6 bids received; low bid $358,061 by Olco Inc.
- Owner
- Indiana DOT
- Letting
- 09 APR 2025
- Pay items
- 58
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Olco Inc | $358,061 | Low |
| 2 | Morphey Construction Inc. | $405,000 | +13% |
| 3 | Paul H Rohe Company Inc | $436,829 | +22% |
| 4 | Dave Omara Contractor Inc | $456,768 | +28% |
| 5 | Force Construction Co Inc | $486,258 | +36% |
| 6 | His Constructors Inc | $486,552 | +36% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Olco Inc | 2. Morphey Construction Inc. | 3. Paul H Rohe Company Inc | 4. Dave Omara Contractor Inc | 5. Force Construction Co Inc | 6. His Constructors Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $8,060.00 | $5,000.00 | $5,900.00 | $6,490.00 | $11,520 | $6,400.00 |
| 0002 | Inspection hole, 3 FT deep or less (107-09367) | EACH | 2 | $1.00 | $2,000.00 | $1,010.00 | $1,250.00 | $868.00 | $1,050.00 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $9,553.00 | $20,250 | $21,790 | $23,250 | $24,000 | $29,830 |
| 0011 | Clearing and grubbing (201-01015) | LS | 1 | $10,881 | $8,100.00 | $5,450.00 | $19,500 | $8,493.00 | $17,200 |
| 0012 | Clearing right-of-way (201-52370) | LS | 1 | $12,067 | $8,100.00 | $17,945 | $9,300.00 | $9,834.00 | $9,800.00 |
| 0013 | Present structure, remove, structure no. 1 (202-51330) | LS | 1 | $31,494 | $25,000 | $38,330 | $19,297 | $21,770 | $65,000 |
| 0014 | Pipe, remove (202-96133) | LFT | 24 | $28.75 | $75.00 | $80.00 | $62.00 | $67.00 | $86.00 |
| 0015 | Excavation, common (203-02000) | CYS | 120 | $80.21 | $100.00 | $110.00 | $95.00 | $83.00 | $52.00 |
| 0016 | Linear grading (203-08607) | LFT | 47 | $37.82 | $55.00 | $25.00 | $129.00 | $33.00 | $19.00 |
| 0017 | Pump around (205-11626) | EACH | 1 | $5,174.76 | $8,500.00 | $20,735 | $19,015 | $9,716.00 | $29,000 |
| 0018 | Stormwater management budget (205-12108) | DOL | 9,374 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0019 | Stormwater management implementation (205-12616) | LS | 1 | $4,902.34 | $5,956.00 | $4,500.00 | $6,200.00 | $4,190.00 | $9,374.00 |
| 0020 | Subgrade treatment, type IC (207-09935) | SYS | 168 | $61.55 | $70.00 | $80.00 | $89.00 | $80.00 | $53.00 |
| 0021 | Structure backfill, type 2 (211-09265) | CYS | 325 | $79.43 | $100.00 | $84.00 | $100.00 | $117.00 | $87.00 |
| 0022 | Geotextile for pavement, type 2B (214-12239) | SYS | 168 | $6.31 | $5.00 | $4.80 | $10.00 | $16.00 | $12.00 |
| 0023 | Compacted aggregate, no. 5 (301-12232) | CYS | 16 | $103.46 | $180.00 | $150.00 | $120.00 | $120.00 | $181.00 |
| 0024 | Compacted aggregate, no. 53 (301-12234) | CYS | 16 | $92.22 | $180.00 | $140.00 | $120.00 | $136.00 | $173.00 |
| 0025 | Compacted aggregate, no. 53 (303-01180) | TON | 18 | $69.38 | $200.00 | $80.00 | $75.00 | $82.00 | $87.00 |
| 0026 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 334 | $17.06 | $26.00 | $11.00 | $19.00 | $18.00 | $15.00 |
| 0027 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 40 | $221.15 | $200.00 | $220.00 | $300.00 | $318.00 | $260.00 |
| 0028 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 21 | $195.72 | $200.00 | $205.00 | $300.00 | $318.00 | $250.00 |
| 0029 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 52 | $200.03 | $200.00 | $205.00 | $300.00 | $318.00 | $249.00 |
| 0030 | Joint adhesive, surface (401-10258) | LFT | 441 | $1.75 | $1.00 | $0.80 | $0.50 | $0.55 | $1.00 |
| 0031 | Joint adhesive, intermediate (401-10259) | LFT | 141 | $1.75 | $1.00 | $2.00 | $0.50 | $0.55 | $2.00 |
| 0032 | Asphalt for tack coat (406-05521) | SYS | 632 | $1.02 | $1.00 | $0.50 | $0.50 | $0.55 | $1.00 |
| 0033 | Cracks and joints in asphalt pavement, rout and seal (408-07478) | TON | 1 | $3,050.69 | $500.00 | $5,400.00 | $2,500.00 | $1,592.00 | $5,800.00 |
| 0034 | Milled HMA corrugations, sinusoidal (606-12400) | LFT | 441 | $10.25 | $16.00 | $12.00 | $4.00 | $11.00 | $29.00 |
| 0035 | Right-of-way marker (615-06490) | EACH | 8 | $288.16 | $500.00 | $500.00 | $500.00 | $531.00 | $540.00 |
| 0036 | Riprap, class 1 (616-05688) | TON | 52 | $87.14 | $200.00 | $110.00 | $125.00 | $105.00 | $97.00 |
| 0037 | Riprap, revetment (616-06405) | TON | 33 | $60.66 | $200.00 | $105.00 | $85.00 | $78.00 | $90.00 |
| 0038 | Geotextile for riprap, type 1A (616-12246) | SYS | 129 | $4.25 | $3.00 | $6.00 | $7.50 | $11.00 | $8.00 |
| 0039 | Geotextile for riprap, type 2B (616-12249) | SYS | 245 | $5.80 | $4.00 | $5.00 | $7.50 | $11.00 | $8.00 |
| 0040 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $335.26 | $1,500.00 | $800.00 | $1,750.00 | $1,592.00 | $860.00 |
| 0041 | Mulched seeding, type R (621-06559) | SYS | 2,324 | $3.57 | $7.00 | $2.00 | $2.00 | $1.60 | $2.20 |
| 0042 | Field office, type C (628-09403) | MOS | 12 | $1,471.02 | $2,475.00 | $3,250.00 | $2,000.00 | $3,408.00 | $2,967.00 |
| 0043 | Computer system equipment (628-11976) | EACH | 1 | $895.84 | $195.00 | $950.00 | $500.00 | $849.00 | $540.00 |
| 0044 | Waterproofing membrane type 2 (714-000086) | SFT | 1,743 | $5.47 | $4.00 | $3.10 | $5.00 | $3.50 | $4.50 |
| 0045 | Structure, reinforced concrete, box sections, 4 FT X 3 FT (714-11192) | LFT | 86 | $1,085.91 | $1,100.00 | $1,240.00 | $1,150.00 | $931.00 | $1,020.00 |
| 0046 | Geotextile for underdrains, type 2A (718-12307) | SYS | 553 | $3.98 | $2.00 | $3.90 | $5.00 | $6.70 | $4.00 |
| 0047 | Pipe, plug existing (720-02442) | EACH | 2 | $1,420.03 | $1,000.00 | $1,000.00 | $750.00 | $1,781.00 | $1,050.00 |
| 0048 | Road closure sign assembly (801-04308) | EACH | 2 | $125.00 | $125.00 | $125.00 | $485.00 | $206.00 | $475.00 |
| 0049 | Detour route marker assembly (801-06625) | EACH | 50 | $75.00 | $75.00 | $75.00 | $160.00 | $173.00 | $158.00 |
| 0050 | Construction sign, type A (801-06640) | EACH | 22 | $150.00 | $150.00 | $150.00 | $250.00 | $202.00 | $237.00 |
| 0051 | Maintaining traffic (801-06775) | LS | 1 | $13,029 | $9,518.00 | $15,405 | $30,317 | $86,000 | $9,296.70 |
| 0052 | Barricade, type III-A (801-07118) | LFT | 72 | $10.00 | $10.00 | $10.00 | $16.00 | $11.00 | $16.00 |
| 0053 | Barricade, type III-B (801-07119) | LFT | 48 | $10.00 | $10.00 | $10.00 | $16.00 | $12.00 | $16.00 |
| 0054 | Portable changeable message sign (801-11642) | EACH | 2 | $2,000.00 | $2,000.00 | $2,000.00 | $2,400.00 | $2,389.00 | $2,300.00 |
| 0055 | Grooving for pavement markings (808-12032) | LFT | 294 | $4.00 | $4.00 | $4.00 | $20.00 | $2.10 | $20.00 |
| 0056 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 294 | $4.00 | $4.00 | $4.00 | $15.00 | $1.10 | $13.00 |
| 0057 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 147 | $4.00 | $4.00 | $4.00 | $15.00 | $1.10 | $13.00 |
| 0058 | Line, thermoplastic, broken, yellow, 6 in. (808-96078) | LFT | 37 | $4.00 | $4.00 | $4.00 | $15.00 | $2.10 | $13.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of April 9, 2025. Compiled by Mirage Metrics.