INDOT contract B-43734-A bid tabulation

BRIDGE DECK OVERLAY. Let by Indiana DOT on August 6, 2025, Harrison, Seymour. 5 bids received; low bid $3,765,000 by E & B Paving LLC.

Owner
Indiana DOT
Letting
06 AUG 2025
Pay items
130
Data through
05 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1E & B Paving LLC$3,765,000Low
2Ragle, Inc.$4,152,996+10%
3Force Construction Co Inc$4,332,981+15%
4American Contracting & Services Inc$4,398,653+17%
5Milestone Contractors LP$4,648,723+23%
INDOT contract B-43734-A: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. E & B Paving LLC2. Ragle, Inc.3. Force Construction Co Inc4. American Contracting & Services Inc5. Milestone Contractors LP
0001Construction engineering (105-06845)LS1$58,142$30,250$32,910$25,000$60,600
0002Liquidated damages (109-08359)DOL1$1.00$1.00$1.00$1.00$1.00
0003Contract liens (109-08360)DOL1$1.00$1.00$1.00$1.00$1.00
0004Quality adjustments, HMA (109-08440)DOL1$1.00$1.00$1.00$1.00$1.00
0005Quality adjustments, temporary traffic control devices (109-08443)DOL1$1.00$1.00$1.00$1.00$1.00
0006Quality adjustments, failed materials (109-08444)DOL1$1.00$1.00$1.00$1.00$1.00
0007Project estimate adjustment (109-08463)DOL1$1.00$1.00$1.00$1.00$1.00
0008Quality adjustments, pavement traffic markings (109-09377)DOL1$1.00$1.00$1.00$1.00$1.00
0009Payment adjustment, PG asphalt binder (109-09489)DOL1$1.00$1.00$1.00$1.00$1.00
0010Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362)DOL1$1.00$1.00$1.00$1.00$1.00
0011Mobilization and demobilization (110-01001)LS1$188,250$207,500$215,000$219,933$235,000
0012Clearing right-of-way (201-52370)LS1$75,300$83,000$14,990$87,973$80,500
0013Pavement removal (202-02240)SYS440$60.60$92.50$37.00$40.00$85.00
0014Gutter turnout, reinforced concrete, remove (202-02276)EACH1$924.83$575.00$1,128.00$1,000.00$5,435.00
0015Present structure, remove portions, structure no. 1 (202-51328)LS1$88,741$130,250$81,560$135,000$200,000
0016Present structure, remove portions, structure no. 2 (202-51328)LS1$125,000$130,250$53,090$125,000$150,000
0017Slopewall, remove (202-51368)SYS40$216.00$155.00$79.00$200.00$539.00
0018Excavation, common (203-02000)CYS370$68.00$67.50$68.00$100.00$128.00
0019Stormwater management budget (205-12108)DOL34,227$1.00$1.00$1.00$1.00$1.00
0020Stormwater management implementation (205-12616)LS1$12,000$15,000$17,070$25,000$5,900.00
0021Subgrade treatment, type II (207-08264)SYS141$68.00$30.00$43.00$55.00$45.00
0022Subgrade treatment, type IC (207-09935)SYS104$106.00$73.50$65.00$110.00$64.00
0023Aggregate for end bent backfill (211-06467)CYS18$336.00$155.00$153.00$300.00$295.00
0024Flowable backfill, non- removable (213-09269)CYS26$365.00$400.00$289.00$375.00$465.00
0025Geogrid, type IB (214-11796)SYS138$10.00$5.75$8.60$10.00$8.50
0026Geotextile for pavement, type 2B (214-12239)SYS474$7.00$11.00$7.00$8.00$4.10
0027Compacted aggregate, no. 53 (301-12234)CYS12$208.00$160.00$97.00$125.00$155.00
0028Subbase for PCCP (302-06464)CYS112$250.00$155.00$125.00$125.00$360.00
0029Compacted aggregate, no. 53 (303-01180)TON327$65.00$43.50$47.00$55.00$78.00
0030HMA patching, full depth, type B (304-12623)TON19$840.00$840.00$990.00$1,000.00$1,205.00
0031Milling, asphalt, 1 1/2 in. (306-08034)SYS1,125$2.95$6.00$8.30$10.00$13.50
0032Milling, transition (306-08043)SYS897$2.20$5.00$6.60$10.00$7.00
0033Milling, asphalt, 5 in. (306-11619)SYS158$10.00$21.50$23.00$17.00$44.00
0034QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002)TON192$418.00$418.00$430.00$418.00$215.00
0035QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038)TON65$690.00$690.00$710.00$690.00$445.00
0036QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047)TON80$475.00$475.00$489.00$475.00$348.00
0037Joint adhesive, surface (401-10258)LFT1,032$0.10$0.10$0.10$0.10$2.25
0038Joint adhesive, intermediate (401-10259)LFT279$0.10$0.10$0.10$0.10$8.75
0039Asphalt for tack coat (406-05520)TON2$0.10$0.10$0.10$0.10$850.00
0040Cracks and joints in asphalt pavement, rout and seal (408-07478)TON2$5,000.00$3,500.00$1,029.00$5,000.00$8,200.00
0041Guardrail, remove (601-02241)LFT1,570$6.75$6.75$6.90$6.75$6.75
0042Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281)LFT382$24.00$24.00$25.00$24.00$24.00
0043Guardrail height transition, MGS (601-12289)EACH2$950.00$950.00$977.00$950.00$950.00
0044Guardrail transition, MGS with curb (601-12291)EACH1$3,250.00$3,250.00$3,343.00$3,250.00$3,250.00
0045Guardrail transition, MGS without curb (601-12292)EACH7$3,000.00$3,000.00$3,086.00$3,000.00$3,000.00
0046Guardrail end treatment, type OS (601-94689)EACH6$3,200.00$3,200.00$3,291.00$3,200.00$3,200.00
0047Barrier delineator (602-06729)EACH64$22.65$9.00$34.00$25.00$24.00
0048Curb and gutter, concrete, type B (605-06145)LFT40$132.00$104.00$100.00$120.00$178.00
0049Milled HMA corrugations, conventional (606-12399)LFT705$11.05$9.50$7.00$20.00$11.75
0050Reinforced concrete bridge approach, 12 in. (609-06259)SYS437$260.00$250.00$245.00$290.00$362.00
0051Monument, type B (615-06505)EACH5$1,265.00$1,265.00$1,301.00$1,265.00$1,265.00
0052Monument, type C (615-06510)EACH1$2,130.00$2,130.00$2,191.00$2,130.00$2,130.00
0053Grout for riprap (616-02281)CYS43$300.00$400.00$300.00$350.00$365.00
0054Riprap, class 1 (616-05688)TON145$200.00$85.00$82.00$90.00$88.00
0055Riprap, revetment (616-06405)TON74$126.00$85.00$67.00$80.00$127.00
0056Geotextile for riprap, type 2A (616-12248)SYS299$5.00$5.00$6.10$5.00$5.10
0057Slopewall, concrete, 4 in. (616-51367)SYS40$84.00$110.00$253.00$750.00$245.00
0058Paved side ditch, break (616-95754)LFT125$3.80$10.00$24.00$25.00$31.00
0059Clean steel bridge, partial, QP-2, bridge no. 1 (619-11050)LS1$40,000$40,000$41,140$40,000$40,000
0060Coat steel bridge, partial, bridge no. 1 (619-51860)LS1$20,000$20,000$20,570$20,000$20,000
0061Clean and coat bearing assemblies, bridge no. 1 (619-95315)LS1$20,000$20,000$20,570$20,000$20,000
0062Mobilization and demobilization for seeding (621-01004)EACH4$1,100.00$200.00$206.00$800.00$1,100.00
0063Fertilizer, for permanent seeding , for permanent seeding (621-06545)TON2$900.00$10.00$10.00$10.00$900.00
0064Seed mixture, type R (621-06553)LBS118$4.50$70.00$72.00$70.00$4.50
0065Mulching material (621-06565)TON2$550.00$400.00$411.00$400.00$550.00
0066Water (621-06567)KGAL2$10.00$0.10$0.10$0.10$10.00
0067Sodding (621-06574)SYS49$110.00$100.00$93.00$90.00$158.29
0068Field office, type C (628-09403)MOS24$2,650.00$2,800.00$3,086.00$3,000.00$5,300.00
0069Computer system equipment (628-11976)EACH3$500.00$750.00$823.00$1,200.00$705.00
0070Computer system (628-11977)EACH1$500.00$1,200.00$1,234.00$5,000.00$705.00
0071Field drilled hole in concrete (702-51863)EACH20$32.00$22.00$30.00$50.00$45.00
0072Concrete, C, substructure (702-92857)CYS29.50$2,400.00$2,350.00$1,818.00$3,900.00$4,175.00
0073Reinforcing bars, epoxy coated (703-06029)LBS37,765$2.00$2.10$1.90$1.75$2.20
0074Threaded tie bar assembly, epoxy coated (703-97936)EACH274$45.00$60.00$46.00$50.00$52.00
0075Inertial profiler, bridge encounter , bridge no. 1 (704-000080)LS1$8,000.00$5,500.00$14,400$15,000$4,800.00
0076Corrective grinding, bridge encounter , bridge no. 1 (704-000082)LS1$12,500$10,000$86,210$50,000$6,000.00
0077Concrete, C, superstructure (704-51002)CYS22.20$3,850.00$3,500.00$3,251.00$4,660.00$6,700.00
0078Railing, concrete type FC (706-09960)LFT54$500.00$310.00$460.00$370.00$1,200.00
0079Concrete bridge railing transition, type TFC (706-11620)EACH8$4,500.00$5,150.00$7,482.00$3,200.00$10,750
0080Fiber wrap concrete casing system , bridge no. 2 (709-04647)LS1$3,600.00$3,600.00$3,703.00$3,600.00$3,600.00
0081Surface seal , bridge no. 1 (709-51821)LS1$20,853$20,534$19,390$33,000$18,853
0082Surface seal , bridge no. 2 (709-51821)LS1$6,069.02$3,907.00$4,185.00$5,500.00$4,069.02
0083Bolt , replace (711-01373)EACH10$275.00$105.00$514.00$500.00$285.00
0084Repair existing structure , bridge no. 1 (711-91996)LS1$50,000$79,878$34,100$40,000$60,000
0085Pipe, underdrain outlet, diameter 6 in. (715-05053)LFT58$62.00$26.50$50.00$50.00$27.00
0086Pipe, end bent drain, diameter 6 in. (715-05407)LFT96$45.00$21.50$26.00$50.00$31.00
0087Pipe, roadway drain casting extension (715-10238)EACH31$1,025.00$1,500.00$1,179.00$1,000.00$850.00
0088Outlet protector, type 2 (718-06529)EACH2$4,430.00$1,500.00$2,110.00$2,000.00$10,300
0089Geotextile for underdrains, type 2A (718-12307)SYS98$12.00$8.50$9.30$10.00$4.00
0090Hydrodemolition (722-01066)SYS6,505$62.00$75.00$57.00$75.00$74.75
0091Bridge deck overlay budget (722-12380)DOL203,335$1.00$1.00$1.00$1.00$1.00
0092Bridge deck, remove existing concrete overlay , bridge no. 1 (722-12463)SYS5,989$5.02$6.50$6.50$13.00$4.75
0093Bridge deck, remove concrete surface , bridge no. 2 (722-12464)SYS516$17.50$15.00$16.00$24.00$26.25
0094Longitudinal grooving (722-12732)SYS6,985$11.00$7.00$5.70$8.00$5.80
0095Bridge deck patching, full depth (722-51401)SFT393$65.00$60.00$82.00$70.00$105.00
0096Overlay dam (722-51874)SFT88$78.00$50.00$76.00$50.00$135.00
0097Bridge expansion joint, type M, replace (724-12775)LFT94$2,600.00$3,500.00$2,462.00$3,300.00$3,050.00
0098Bridge deck, remove existing polymer overlay system , bridge no. 1 (738-12917)SYS5,989$1.05$4.25$9.10$2.00$5.50
0099Construction sign, type D (801-03291)EACH3$293.00$293.00$201.00$100.00$100.00
0100Temporary pavement marking, removable, 4 in. (801-06207)LFT7,130$1.45$1.45$3.30$1.30$1.30
0101Temporary pavement marking, removable, 6 in. (801-06209)LFT12,950$1.88$1.88$3.30$2.00$2.00
0102Temporary transverse pavement marking, 24 in. (801-06216)LFT24$11.64$11.64$4.10$10.00$10.00
0103Temporary transverse pavement marking, removable, 24 in. (801-06218)LFT24$12.91$12.91$13.00$10.00$10.00
0104Construction sign, type A (801-06640)EACH26$234.00$234.00$201.00$200.00$200.00
0105Construction sign, type B (801-06645)EACH7$117.00$117.00$118.00$100.00$100.00
0106Maintaining traffic (801-06775)LS1$58,830$40,000$626,800$55,000$90,000
0107Energy absorbing terminal, CZ, TL-2 (801-07023)EACH4$9,600.00$9,600.00$9,874.00$12,000$9,600.00
0108Barricade, type III-A (801-07118)LFT108$15.89$15.89$19.00$16.00$16.00
0109Temporary traffic barrier, anchored, type 2 (801-08508)LFT2,160$35.00$60.00$57.00$54.00$100.25
0110Portable changeable message sign (801-11642)EACH2$5,491.00$5,491.00$5,657.00$9,000.00$9,000.00
0111Portable signal (801-12081)LS1$58,000$100,000$29,960$45,000$68,534
0112Driveway assistance device (801-12482)EACH3$10,200$10,000$15,450$3,000.00$1,500.00
0113Temporary worksite speed limit sign assembly, continuous (801-12883)EACH6$1,209.00$1,209.00$1,543.00$400.00$400.00
0114Temporary buzz strips (801-97643)LFT1,728$20.65$20.65$10.00$17.50$17.50
0115Reference post (802-04893)EACH3$225.00$225.00$231.00$225.00$225.00
0116Sign post, square, type 1, reinforced anchor base (802-05701)LFT38$14.00$14.00$14.00$14.00$14.00
0117Sign, sheet, with legend, 0.100 in. thickness (802-09840)SFT23$24.00$24.00$25.00$24.00$24.00
0118Sign, ground mounted, reset (802-91122)EACH2$350.00$350.00$360.00$350.00$350.00
0119Line, remove (808-06716)LFT9,590$0.55$0.55$0.70$0.50$1.16
0120Retro-reflectivity testing (808-09381)LS1$3,000.00$3,000.00$4,114.00$500.00$2,000.00
0121Line, multi-component, solid, white, 6 in. (808-10049)LFT5,580$1.75$1.75$1.00$1.50$1.75
0122Line, multi-component, solid, yellow, 6 in. (808-10057)LFT4,000$1.75$1.75$1.00$1.50$1.75
0123Grooving for pavement markings (808-12032)LFT4,895$2.50$1.26$0.45$2.00$2.00
0124Line, multi-component, broken, yellow, 6 in. (808-12841)LFT550$1.75$1.75$2.00$1.50$1.75
0125Snowplowable raised pavement marker, remove (808-75996)EACH28$75.00$22.50$257.00$25.00$150.00
0126Snowplowable raised pavement marker (808-75998)EACH24$75.00$75.00$201.00$100.00$75.00
0127Bridge deck overlay, latex modified (722-51842)SYS6,571$98.00$120.00
0128Bridge deck overlay, silica fume modified (722-01061)SYS6,571$82.50$100.00$89.54
0129Guardrail, reset (601-06035)LFT150$15.00$15.00$15.00$15.00$15.00
0130Patching concrete structures (710-09158)SFT15$10.00$10.00$10.00$100.00$10.00
INDOT contract B-43734-A: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

Every contract let that day: INDOT letting of August 6, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy