INDOT contract B-43734-A bid tabulation
BRIDGE DECK OVERLAY. Let by Indiana DOT on August 6, 2025, Harrison, Seymour. 5 bids received; low bid $3,765,000 by E & B Paving LLC.
- Owner
- Indiana DOT
- Letting
- 06 AUG 2025
- Pay items
- 130
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | E & B Paving LLC | $3,765,000 | Low |
| 2 | Ragle, Inc. | $4,152,996 | +10% |
| 3 | Force Construction Co Inc | $4,332,981 | +15% |
| 4 | American Contracting & Services Inc | $4,398,653 | +17% |
| 5 | Milestone Contractors LP | $4,648,723 | +23% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E & B Paving LLC | 2. Ragle, Inc. | 3. Force Construction Co Inc | 4. American Contracting & Services Inc | 5. Milestone Contractors LP |
|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $58,142 | $30,250 | $32,910 | $25,000 | $60,600 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, pavement traffic markings (109-09377) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0011 | Mobilization and demobilization (110-01001) | LS | 1 | $188,250 | $207,500 | $215,000 | $219,933 | $235,000 |
| 0012 | Clearing right-of-way (201-52370) | LS | 1 | $75,300 | $83,000 | $14,990 | $87,973 | $80,500 |
| 0013 | Pavement removal (202-02240) | SYS | 440 | $60.60 | $92.50 | $37.00 | $40.00 | $85.00 |
| 0014 | Gutter turnout, reinforced concrete, remove (202-02276) | EACH | 1 | $924.83 | $575.00 | $1,128.00 | $1,000.00 | $5,435.00 |
| 0015 | Present structure, remove portions, structure no. 1 (202-51328) | LS | 1 | $88,741 | $130,250 | $81,560 | $135,000 | $200,000 |
| 0016 | Present structure, remove portions, structure no. 2 (202-51328) | LS | 1 | $125,000 | $130,250 | $53,090 | $125,000 | $150,000 |
| 0017 | Slopewall, remove (202-51368) | SYS | 40 | $216.00 | $155.00 | $79.00 | $200.00 | $539.00 |
| 0018 | Excavation, common (203-02000) | CYS | 370 | $68.00 | $67.50 | $68.00 | $100.00 | $128.00 |
| 0019 | Stormwater management budget (205-12108) | DOL | 34,227 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0020 | Stormwater management implementation (205-12616) | LS | 1 | $12,000 | $15,000 | $17,070 | $25,000 | $5,900.00 |
| 0021 | Subgrade treatment, type II (207-08264) | SYS | 141 | $68.00 | $30.00 | $43.00 | $55.00 | $45.00 |
| 0022 | Subgrade treatment, type IC (207-09935) | SYS | 104 | $106.00 | $73.50 | $65.00 | $110.00 | $64.00 |
| 0023 | Aggregate for end bent backfill (211-06467) | CYS | 18 | $336.00 | $155.00 | $153.00 | $300.00 | $295.00 |
| 0024 | Flowable backfill, non- removable (213-09269) | CYS | 26 | $365.00 | $400.00 | $289.00 | $375.00 | $465.00 |
| 0025 | Geogrid, type IB (214-11796) | SYS | 138 | $10.00 | $5.75 | $8.60 | $10.00 | $8.50 |
| 0026 | Geotextile for pavement, type 2B (214-12239) | SYS | 474 | $7.00 | $11.00 | $7.00 | $8.00 | $4.10 |
| 0027 | Compacted aggregate, no. 53 (301-12234) | CYS | 12 | $208.00 | $160.00 | $97.00 | $125.00 | $155.00 |
| 0028 | Subbase for PCCP (302-06464) | CYS | 112 | $250.00 | $155.00 | $125.00 | $125.00 | $360.00 |
| 0029 | Compacted aggregate, no. 53 (303-01180) | TON | 327 | $65.00 | $43.50 | $47.00 | $55.00 | $78.00 |
| 0030 | HMA patching, full depth, type B (304-12623) | TON | 19 | $840.00 | $840.00 | $990.00 | $1,000.00 | $1,205.00 |
| 0031 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 1,125 | $2.95 | $6.00 | $8.30 | $10.00 | $13.50 |
| 0032 | Milling, transition (306-08043) | SYS | 897 | $2.20 | $5.00 | $6.60 | $10.00 | $7.00 |
| 0033 | Milling, asphalt, 5 in. (306-11619) | SYS | 158 | $10.00 | $21.50 | $23.00 | $17.00 | $44.00 |
| 0034 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 192 | $418.00 | $418.00 | $430.00 | $418.00 | $215.00 |
| 0035 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 65 | $690.00 | $690.00 | $710.00 | $690.00 | $445.00 |
| 0036 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 80 | $475.00 | $475.00 | $489.00 | $475.00 | $348.00 |
| 0037 | Joint adhesive, surface (401-10258) | LFT | 1,032 | $0.10 | $0.10 | $0.10 | $0.10 | $2.25 |
| 0038 | Joint adhesive, intermediate (401-10259) | LFT | 279 | $0.10 | $0.10 | $0.10 | $0.10 | $8.75 |
| 0039 | Asphalt for tack coat (406-05520) | TON | 2 | $0.10 | $0.10 | $0.10 | $0.10 | $850.00 |
| 0040 | Cracks and joints in asphalt pavement, rout and seal (408-07478) | TON | 2 | $5,000.00 | $3,500.00 | $1,029.00 | $5,000.00 | $8,200.00 |
| 0041 | Guardrail, remove (601-02241) | LFT | 1,570 | $6.75 | $6.75 | $6.90 | $6.75 | $6.75 |
| 0042 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 382 | $24.00 | $24.00 | $25.00 | $24.00 | $24.00 |
| 0043 | Guardrail height transition, MGS (601-12289) | EACH | 2 | $950.00 | $950.00 | $977.00 | $950.00 | $950.00 |
| 0044 | Guardrail transition, MGS with curb (601-12291) | EACH | 1 | $3,250.00 | $3,250.00 | $3,343.00 | $3,250.00 | $3,250.00 |
| 0045 | Guardrail transition, MGS without curb (601-12292) | EACH | 7 | $3,000.00 | $3,000.00 | $3,086.00 | $3,000.00 | $3,000.00 |
| 0046 | Guardrail end treatment, type OS (601-94689) | EACH | 6 | $3,200.00 | $3,200.00 | $3,291.00 | $3,200.00 | $3,200.00 |
| 0047 | Barrier delineator (602-06729) | EACH | 64 | $22.65 | $9.00 | $34.00 | $25.00 | $24.00 |
| 0048 | Curb and gutter, concrete, type B (605-06145) | LFT | 40 | $132.00 | $104.00 | $100.00 | $120.00 | $178.00 |
| 0049 | Milled HMA corrugations, conventional (606-12399) | LFT | 705 | $11.05 | $9.50 | $7.00 | $20.00 | $11.75 |
| 0050 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 437 | $260.00 | $250.00 | $245.00 | $290.00 | $362.00 |
| 0051 | Monument, type B (615-06505) | EACH | 5 | $1,265.00 | $1,265.00 | $1,301.00 | $1,265.00 | $1,265.00 |
| 0052 | Monument, type C (615-06510) | EACH | 1 | $2,130.00 | $2,130.00 | $2,191.00 | $2,130.00 | $2,130.00 |
| 0053 | Grout for riprap (616-02281) | CYS | 43 | $300.00 | $400.00 | $300.00 | $350.00 | $365.00 |
| 0054 | Riprap, class 1 (616-05688) | TON | 145 | $200.00 | $85.00 | $82.00 | $90.00 | $88.00 |
| 0055 | Riprap, revetment (616-06405) | TON | 74 | $126.00 | $85.00 | $67.00 | $80.00 | $127.00 |
| 0056 | Geotextile for riprap, type 2A (616-12248) | SYS | 299 | $5.00 | $5.00 | $6.10 | $5.00 | $5.10 |
| 0057 | Slopewall, concrete, 4 in. (616-51367) | SYS | 40 | $84.00 | $110.00 | $253.00 | $750.00 | $245.00 |
| 0058 | Paved side ditch, break (616-95754) | LFT | 125 | $3.80 | $10.00 | $24.00 | $25.00 | $31.00 |
| 0059 | Clean steel bridge, partial, QP-2, bridge no. 1 (619-11050) | LS | 1 | $40,000 | $40,000 | $41,140 | $40,000 | $40,000 |
| 0060 | Coat steel bridge, partial, bridge no. 1 (619-51860) | LS | 1 | $20,000 | $20,000 | $20,570 | $20,000 | $20,000 |
| 0061 | Clean and coat bearing assemblies, bridge no. 1 (619-95315) | LS | 1 | $20,000 | $20,000 | $20,570 | $20,000 | $20,000 |
| 0062 | Mobilization and demobilization for seeding (621-01004) | EACH | 4 | $1,100.00 | $200.00 | $206.00 | $800.00 | $1,100.00 |
| 0063 | Fertilizer, for permanent seeding , for permanent seeding (621-06545) | TON | 2 | $900.00 | $10.00 | $10.00 | $10.00 | $900.00 |
| 0064 | Seed mixture, type R (621-06553) | LBS | 118 | $4.50 | $70.00 | $72.00 | $70.00 | $4.50 |
| 0065 | Mulching material (621-06565) | TON | 2 | $550.00 | $400.00 | $411.00 | $400.00 | $550.00 |
| 0066 | Water (621-06567) | KGAL | 2 | $10.00 | $0.10 | $0.10 | $0.10 | $10.00 |
| 0067 | Sodding (621-06574) | SYS | 49 | $110.00 | $100.00 | $93.00 | $90.00 | $158.29 |
| 0068 | Field office, type C (628-09403) | MOS | 24 | $2,650.00 | $2,800.00 | $3,086.00 | $3,000.00 | $5,300.00 |
| 0069 | Computer system equipment (628-11976) | EACH | 3 | $500.00 | $750.00 | $823.00 | $1,200.00 | $705.00 |
| 0070 | Computer system (628-11977) | EACH | 1 | $500.00 | $1,200.00 | $1,234.00 | $5,000.00 | $705.00 |
| 0071 | Field drilled hole in concrete (702-51863) | EACH | 20 | $32.00 | $22.00 | $30.00 | $50.00 | $45.00 |
| 0072 | Concrete, C, substructure (702-92857) | CYS | 29.50 | $2,400.00 | $2,350.00 | $1,818.00 | $3,900.00 | $4,175.00 |
| 0073 | Reinforcing bars, epoxy coated (703-06029) | LBS | 37,765 | $2.00 | $2.10 | $1.90 | $1.75 | $2.20 |
| 0074 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 274 | $45.00 | $60.00 | $46.00 | $50.00 | $52.00 |
| 0075 | Inertial profiler, bridge encounter , bridge no. 1 (704-000080) | LS | 1 | $8,000.00 | $5,500.00 | $14,400 | $15,000 | $4,800.00 |
| 0076 | Corrective grinding, bridge encounter , bridge no. 1 (704-000082) | LS | 1 | $12,500 | $10,000 | $86,210 | $50,000 | $6,000.00 |
| 0077 | Concrete, C, superstructure (704-51002) | CYS | 22.20 | $3,850.00 | $3,500.00 | $3,251.00 | $4,660.00 | $6,700.00 |
| 0078 | Railing, concrete type FC (706-09960) | LFT | 54 | $500.00 | $310.00 | $460.00 | $370.00 | $1,200.00 |
| 0079 | Concrete bridge railing transition, type TFC (706-11620) | EACH | 8 | $4,500.00 | $5,150.00 | $7,482.00 | $3,200.00 | $10,750 |
| 0080 | Fiber wrap concrete casing system , bridge no. 2 (709-04647) | LS | 1 | $3,600.00 | $3,600.00 | $3,703.00 | $3,600.00 | $3,600.00 |
| 0081 | Surface seal , bridge no. 1 (709-51821) | LS | 1 | $20,853 | $20,534 | $19,390 | $33,000 | $18,853 |
| 0082 | Surface seal , bridge no. 2 (709-51821) | LS | 1 | $6,069.02 | $3,907.00 | $4,185.00 | $5,500.00 | $4,069.02 |
| 0083 | Bolt , replace (711-01373) | EACH | 10 | $275.00 | $105.00 | $514.00 | $500.00 | $285.00 |
| 0084 | Repair existing structure , bridge no. 1 (711-91996) | LS | 1 | $50,000 | $79,878 | $34,100 | $40,000 | $60,000 |
| 0085 | Pipe, underdrain outlet, diameter 6 in. (715-05053) | LFT | 58 | $62.00 | $26.50 | $50.00 | $50.00 | $27.00 |
| 0086 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 96 | $45.00 | $21.50 | $26.00 | $50.00 | $31.00 |
| 0087 | Pipe, roadway drain casting extension (715-10238) | EACH | 31 | $1,025.00 | $1,500.00 | $1,179.00 | $1,000.00 | $850.00 |
| 0088 | Outlet protector, type 2 (718-06529) | EACH | 2 | $4,430.00 | $1,500.00 | $2,110.00 | $2,000.00 | $10,300 |
| 0089 | Geotextile for underdrains, type 2A (718-12307) | SYS | 98 | $12.00 | $8.50 | $9.30 | $10.00 | $4.00 |
| 0090 | Hydrodemolition (722-01066) | SYS | 6,505 | $62.00 | $75.00 | $57.00 | $75.00 | $74.75 |
| 0091 | Bridge deck overlay budget (722-12380) | DOL | 203,335 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0092 | Bridge deck, remove existing concrete overlay , bridge no. 1 (722-12463) | SYS | 5,989 | $5.02 | $6.50 | $6.50 | $13.00 | $4.75 |
| 0093 | Bridge deck, remove concrete surface , bridge no. 2 (722-12464) | SYS | 516 | $17.50 | $15.00 | $16.00 | $24.00 | $26.25 |
| 0094 | Longitudinal grooving (722-12732) | SYS | 6,985 | $11.00 | $7.00 | $5.70 | $8.00 | $5.80 |
| 0095 | Bridge deck patching, full depth (722-51401) | SFT | 393 | $65.00 | $60.00 | $82.00 | $70.00 | $105.00 |
| 0096 | Overlay dam (722-51874) | SFT | 88 | $78.00 | $50.00 | $76.00 | $50.00 | $135.00 |
| 0097 | Bridge expansion joint, type M, replace (724-12775) | LFT | 94 | $2,600.00 | $3,500.00 | $2,462.00 | $3,300.00 | $3,050.00 |
| 0098 | Bridge deck, remove existing polymer overlay system , bridge no. 1 (738-12917) | SYS | 5,989 | $1.05 | $4.25 | $9.10 | $2.00 | $5.50 |
| 0099 | Construction sign, type D (801-03291) | EACH | 3 | $293.00 | $293.00 | $201.00 | $100.00 | $100.00 |
| 0100 | Temporary pavement marking, removable, 4 in. (801-06207) | LFT | 7,130 | $1.45 | $1.45 | $3.30 | $1.30 | $1.30 |
| 0101 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 12,950 | $1.88 | $1.88 | $3.30 | $2.00 | $2.00 |
| 0102 | Temporary transverse pavement marking, 24 in. (801-06216) | LFT | 24 | $11.64 | $11.64 | $4.10 | $10.00 | $10.00 |
| 0103 | Temporary transverse pavement marking, removable, 24 in. (801-06218) | LFT | 24 | $12.91 | $12.91 | $13.00 | $10.00 | $10.00 |
| 0104 | Construction sign, type A (801-06640) | EACH | 26 | $234.00 | $234.00 | $201.00 | $200.00 | $200.00 |
| 0105 | Construction sign, type B (801-06645) | EACH | 7 | $117.00 | $117.00 | $118.00 | $100.00 | $100.00 |
| 0106 | Maintaining traffic (801-06775) | LS | 1 | $58,830 | $40,000 | $626,800 | $55,000 | $90,000 |
| 0107 | Energy absorbing terminal, CZ, TL-2 (801-07023) | EACH | 4 | $9,600.00 | $9,600.00 | $9,874.00 | $12,000 | $9,600.00 |
| 0108 | Barricade, type III-A (801-07118) | LFT | 108 | $15.89 | $15.89 | $19.00 | $16.00 | $16.00 |
| 0109 | Temporary traffic barrier, anchored, type 2 (801-08508) | LFT | 2,160 | $35.00 | $60.00 | $57.00 | $54.00 | $100.25 |
| 0110 | Portable changeable message sign (801-11642) | EACH | 2 | $5,491.00 | $5,491.00 | $5,657.00 | $9,000.00 | $9,000.00 |
| 0111 | Portable signal (801-12081) | LS | 1 | $58,000 | $100,000 | $29,960 | $45,000 | $68,534 |
| 0112 | Driveway assistance device (801-12482) | EACH | 3 | $10,200 | $10,000 | $15,450 | $3,000.00 | $1,500.00 |
| 0113 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 6 | $1,209.00 | $1,209.00 | $1,543.00 | $400.00 | $400.00 |
| 0114 | Temporary buzz strips (801-97643) | LFT | 1,728 | $20.65 | $20.65 | $10.00 | $17.50 | $17.50 |
| 0115 | Reference post (802-04893) | EACH | 3 | $225.00 | $225.00 | $231.00 | $225.00 | $225.00 |
| 0116 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 38 | $14.00 | $14.00 | $14.00 | $14.00 | $14.00 |
| 0117 | Sign, sheet, with legend, 0.100 in. thickness (802-09840) | SFT | 23 | $24.00 | $24.00 | $25.00 | $24.00 | $24.00 |
| 0118 | Sign, ground mounted, reset (802-91122) | EACH | 2 | $350.00 | $350.00 | $360.00 | $350.00 | $350.00 |
| 0119 | Line, remove (808-06716) | LFT | 9,590 | $0.55 | $0.55 | $0.70 | $0.50 | $1.16 |
| 0120 | Retro-reflectivity testing (808-09381) | LS | 1 | $3,000.00 | $3,000.00 | $4,114.00 | $500.00 | $2,000.00 |
| 0121 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 5,580 | $1.75 | $1.75 | $1.00 | $1.50 | $1.75 |
| 0122 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 4,000 | $1.75 | $1.75 | $1.00 | $1.50 | $1.75 |
| 0123 | Grooving for pavement markings (808-12032) | LFT | 4,895 | $2.50 | $1.26 | $0.45 | $2.00 | $2.00 |
| 0124 | Line, multi-component, broken, yellow, 6 in. (808-12841) | LFT | 550 | $1.75 | $1.75 | $2.00 | $1.50 | $1.75 |
| 0125 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 28 | $75.00 | $22.50 | $257.00 | $25.00 | $150.00 |
| 0126 | Snowplowable raised pavement marker (808-75998) | EACH | 24 | $75.00 | $75.00 | $201.00 | $100.00 | $75.00 |
| 0127 | Bridge deck overlay, latex modified (722-51842) | SYS | 6,571 | $98.00 | $120.00 | |||
| 0128 | Bridge deck overlay, silica fume modified (722-01061) | SYS | 6,571 | $82.50 | $100.00 | $89.54 | ||
| 0129 | Guardrail, reset (601-06035) | LFT | 150 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 |
| 0130 | Patching concrete structures (710-09158) | SFT | 15 | $10.00 | $10.00 | $10.00 | $100.00 | $10.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of August 6, 2025. Compiled by Mirage Metrics.