INDOT contract B-43795-A bid tabulation
BRIDGE DECK OVERLAY. Let by Indiana DOT on August 6, 2025, Elkhart, Fort Wayne. 3 bids received; low bid $1,529,462 by Milestone Contractors LP.
- Owner
- Indiana DOT
- Letting
- 06 AUG 2025
- Pay items
- 96
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Milestone Contractors LP | $1,529,462 | Low |
| 2 | Rieth-Riley Construction Co., Inc. | $1,622,193 | +6.0% |
| 3 | Laporte Construction Company Inc | $1,754,025 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Milestone Contractors LP | 2. Rieth-Riley Construction Co., Inc. | 3. Laporte Construction Company Inc |
|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $25,000 | $16,999 | $14,074 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $76,000 | $80,000 | $87,000 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $25,000 | $2,000.00 | $6,890.57 |
| 0011 | Pavement removal (202-02240) | SYS | 332 | $60.00 | $85.00 | $63.25 |
| 0012 | Center curb, concrete, remove (202-02273) | SYS | 112 | $50.00 | $95.00 | $115.52 |
| 0013 | Curb, concrete, remove (202-02278) | LFT | 16 | $20.00 | $250.00 | $78.89 |
| 0014 | Casting, remove (202-02772) | EACH | 3 | $275.00 | $1,000.00 | $701.96 |
| 0015 | Present structure, remove portions, structure no. 1 (202-51328) | LS | 1 | $40,000 | $15,000 | $62,000 |
| 0016 | Present structure, remove portions, structure no. 2 (202-51328) | LS | 1 | $50,000 | $20,000 | $55,000 |
| 0017 | Excavation, common (203-02000) | CYS | 165 | $40.00 | $25.00 | $91.40 |
| 0018 | Subgrade treatment, type II (207-08264) | SYS | 116 | $45.00 | $40.00 | $59.34 |
| 0019 | Subgrade treatment, type IC (207-09935) | SYS | 356 | $65.00 | $50.00 | $105.92 |
| 0020 | Flowable backfill, non- removable (213-09269) | CYS | 20 | $400.00 | $400.00 | $527.39 |
| 0021 | Geogrid, type IB (214-11796) | SYS | 116 | $9.00 | $6.00 | $13.69 |
| 0022 | Geotextile for pavement, type 2B (214-12239) | SYS | 356 | $8.00 | $6.00 | $6.71 |
| 0023 | Subbase for PCCP (302-06464) | CYS | 84 | $225.00 | $155.00 | $126.47 |
| 0024 | Compacted aggregate, no. 53 (303-01180) | TON | 74 | $85.00 | $120.00 | $72.18 |
| 0025 | HMA patching, full depth, type C (304-12625) | TON | 80 | $375.00 | $500.00 | $355.00 |
| 0026 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 354 | $12.00 | $35.00 | $3.10 |
| 0027 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 32 | $630.00 | $440.00 | $440.00 |
| 0028 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 4 | $2,500.00 | $1,520.00 | $1,520.00 |
| 0029 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 12 | $800.00 | $690.00 | $690.00 |
| 0030 | Joint adhesive, surface (401-10258) | LFT | 384 | $1.00 | $5.00 | $5.00 |
| 0031 | Joint adhesive, intermediate (401-10259) | LFT | 264 | $1.00 | $5.00 | $5.00 |
| 0032 | Asphalt for tack coat (406-05520) | TON | 0.60 | $1,000.00 | $0.10 | $0.10 |
| 0033 | Guardrail, remove (601-02241) | LFT | 314 | $7.00 | $18.00 | $27.00 |
| 0034 | Guardrail, reset (601-06035) | LFT | 25 | $38.00 | $45.00 | $22.00 |
| 0035 | Guardrail height transition, MGS (601-12289) | EACH | 2 | $1,300.00 | $975.00 | $1,573.00 |
| 0036 | Guardrail height transition, MGS , modified (601-12289) | EACH | 2 | $2,575.00 | $2,400.00 | $1,685.00 |
| 0037 | Guardrail transition, MGS with curb (601-12291) | EACH | 2 | $3,775.00 | $3,500.00 | $3,528.00 |
| 0038 | Guardrail transition, MGS with curb , modified (601-12291) | EACH | 2 | $4,765.00 | $5,000.00 | $3,764.00 |
| 0039 | Barrier delineator (602-06729) | EACH | 18 | $25.00 | $30.00 | $20.00 |
| 0040 | Curb, concrete (605-06120) | LFT | 8 | $350.00 | $350.00 | $375.06 |
| 0041 | Curb, concrete, type B (605-06121) | LFT | 8 | $350.00 | $350.00 | $375.06 |
| 0042 | Center curb, concrete, type C (605-06210) | LFT | 7 | $450.00 | $300.00 | $601.20 |
| 0043 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 332 | $235.00 | $225.00 | $200.00 |
| 0044 | Inspection hole (616-93772) | EACH | 8 | $175.00 | $1,000.00 | $793.61 |
| 0045 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $500.00 | $500.00 | $500.00 |
| 0046 | Mulched seeding, type U (621-06560) | SYS | 200 | $10.74 | $10.74 | $10.74 |
| 0047 | Field office, type A (628-09401) | MOS | 9 | $2,800.00 | $3,000.00 | $4,171.00 |
| 0048 | Field drilled hole in concrete (702-51863) | EACH | 24 | $25.00 | $50.00 | $27.04 |
| 0049 | Concrete, A (702-90915) | CYS | 10.70 | $1,300.00 | $1,500.00 | $1,644.94 |
| 0050 | Reinforcing bars, epoxy coated (703-06029) | LBS | 23,613 | $2.00 | $2.50 | $1.43 |
| 0051 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 53 | $45.00 | $60.00 | $39.87 |
| 0052 | Concrete, C, superstructure (704-51002) | CYS | 1 | $3,000.00 | $1,000.00 | $5,000.00 |
| 0053 | Railing, concrete type FC , modified (706-11600) | CYS | 2 | $2,000.00 | $1,900.00 | $3,146.08 |
| 0054 | Railing, concrete type FT , modified (706-11601) | CYS | 0.80 | $4,200.00 | $3,600.00 | $5,896.04 |
| 0055 | Concrete bridge railing transition, type TFC (706-11620) | EACH | 2 | $8,500.00 | $3,400.00 | $4,427.11 |
| 0056 | Concrete bridge railing transition, type TFT , modified (706-11621) | EACH | 2 | $8,500.00 | $5,500.00 | $4,427.11 |
| 0057 | Surface seal , bridge no. 1 (709-51821) | LS | 1 | $4,541.00 | $632.00 | $1,280.00 |
| 0058 | Surface seal , bridge no. 2 (709-51821) | LS | 1 | $5,322.00 | $3,104.00 | $2,170.00 |
| 0059 | Patching concrete structures (710-09158) | SFT | 84 | $191.00 | $225.00 | $191.00 |
| 0060 | Patching concrete structures , concrete advanced rejuvenation (710-09158) | SFT | 730 | $20.00 | $120.00 | $176.00 |
| 0061 | Casting, type 5, furnish and adjust to grade (720-44030) | EACH | 2 | $2,000.00 | $4,000.00 | $1,620.71 |
| 0062 | Casting, type 15, furnish and adjust to grade (720-44080) | EACH | 1 | $2,300.00 | $3,500.00 | $1,620.73 |
| 0063 | Hydrodemolition (722-01066) | SYS | 1,450 | $71.00 | $85.00 | $102.81 |
| 0064 | Bridge deck overlay budget (722-12380) | DOL | 29,650 | $1.00 | $1.00 | $1.00 |
| 0065 | Bridge deck, remove existing concrete overlay (722-12463) | SYS | 1,450 | $14.00 | $10.00 | $13.82 |
| 0066 | Longitudinal grooving (722-12732) | SYS | 1,782 | $4.00 | $5.00 | $10.45 |
| 0067 | Bridge deck overlay , concrete advanced rejuvenation technology system (722-12899) | SYS | 2,900 | $36.00 | $55.00 | $64.63 |
| 0068 | Bridge deck patching, full depth (722-51401) | SFT | 50 | $25.00 | $1.00 | $45.00 |
| 0069 | Expansion joint sliding plate (724-03855) | LFT | 10 | $1,000.00 | $1,200.00 | $1,918.05 |
| 0070 | Bridge expansion joint, type PCF, replace (724-12776) | LFT | 158 | $100.00 | $100.00 | $169.70 |
| 0071 | Epoxy injection, crack preparation (727-90308) | LFT | 351 | $110.00 | $90.00 | $110.00 |
| 0072 | Epoxy injection, epoxy material (727-90309) | GAL | 4 | $52.00 | $200.00 | $52.00 |
| 0073 | Epoxy injection, furnishing equipment , bridge no. 1 (727-93560) | LS | 1 | $965.00 | $1,100.00 | $965.00 |
| 0074 | Epoxy injection, furnishing equipment , bridge no. 2 (727-93560) | LS | 1 | $965.00 | $1,100.00 | $965.00 |
| 0075 | Temporary pavement message marking, lane indication arrow (801-01504) | EACH | 1 | $149.00 | $149.00 | $150.00 |
| 0076 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 21,820 | $1.99 | $1.99 | $2.00 |
| 0077 | Temporary pavement marking, removable, 8 in. (801-06469) | LFT | 1,885 | $2.49 | $2.49 | $2.50 |
| 0078 | Construction sign, type A (801-06640) | EACH | 64 | $279.00 | $279.00 | $280.00 |
| 0079 | Construction sign, type B (801-06645) | EACH | 33 | $140.00 | $140.00 | $140.00 |
| 0080 | Flashing arrow sign (801-06710) | DAY | 285 | $16.00 | $16.00 | $16.00 |
| 0081 | Maintaining traffic (801-06775) | LS | 1 | $85,000 | $50,000 | $40,000 |
| 0082 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 2 | $8,500.00 | $15,000 | $11,978 |
| 0083 | Barricade, type III-A (801-07118) | LFT | 108 | $21.81 | $21.81 | $22.00 |
| 0084 | Barricade, type III-B (801-07119) | LFT | 48 | $21.81 | $21.81 | $22.00 |
| 0085 | Temporary traffic barrier, anchored, type 2 (801-08508) | LFT | 720 | $60.00 | $150.00 | $54.00 |
| 0086 | Temporary curb ramp (801-11990) | EACH | 4 | $6,500.00 | $100.00 | $1,385.25 |
| 0087 | Law enforcement officer (801-12324) | HRS | 500 | $60.00 | $60.00 | $60.00 |
| 0088 | Temporary pavement marking, removable, 13 in. (801-12391) | LFT | 50 | $12.88 | $12.88 | $13.00 |
| 0089 | Temporary accessible pedestrian path (801-12641) | SYS | 65 | $40.00 | $200.00 | $10.00 |
| 0090 | Temporary pedestrian channelizer (801-12862) | LFT | 656 | $40.00 | $32.43 | $19.39 |
| 0091 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 8 | $974.00 | $974.00 | $975.00 |
| 0092 | Pavement message marking, paint, lane indication arrow (808-06723) | EACH | 2 | $169.00 | $169.00 | $170.00 |
| 0093 | Line, paint, broken, white, 6 in. (808-75002) | LFT | 180 | $0.57 | $0.57 | $1.00 |
| 0094 | Line, paint, solid, yellow, 6 in. (808-75047) | LFT | 1,380 | $0.38 | $0.38 | $1.00 |
| 0095 | Transverse marking, paint, crosshatch line, yellow, 12 in. (808-75078) | LFT | 68 | $5.71 | $5.71 | $6.00 |
| 0097 | Bridge deck overlay, silica fume modified (722-01061) | SYS | 1,450 | $130.00 | $125.00 | $145.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of August 6, 2025. Compiled by Mirage Metrics.