INDOT contract B-43799-A bid tabulation

BRIDGE DECK OVERLAY. Let by Indiana DOT on September 10, 2025, Miami, Wabash, Fort Wayne. 6 bids received; low bid $987,375 by Milestone Contractors LP.

Owner
Indiana DOT
Letting
10 SEP 2025
Pay items
79
Data through
05 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Milestone Contractors LP$987,375Low
2E & B Paving LLC$1,136,360+15%
3Rieth-Riley Construction Co., Inc.$1,314,493+33%
4Pioneer Associates Inc$1,350,799+37%
5Beaty Construction Inc$1,391,873+41%
6Laporte Construction Company Inc$1,409,503+43%
INDOT contract B-43799-A: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Milestone Contractors LP2. E & B Paving LLC3. Rieth-Riley Construction Co., Inc.4. Pioneer Associates Inc5. Beaty Construction Inc6. Laporte Construction Company Inc
0001Construction engineering (105-06845)LS1$20,000$20,000$15,000$17,360$5,202.40$8,901.40
0002Liquidated damages (109-08359)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0003Contract liens (109-08360)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0004Quality adjustments, HMA (109-08440)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0005Quality adjustments, temporary traffic control devices (109-08443)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0006Quality adjustments, failed materials (109-08444)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0007Project estimate adjustment (109-08463)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0008Payment adjustment, PG asphalt binder (109-09489)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0009Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0010Mobilization and demobilization (110-01001)LS1$49,000$55,000$65,500$67,500$248,978$68,000
0011Clearing right-of-way (201-52370)LS1$10,000$11,000$13,000$28,500$12,380$12,000
0012Pavement removal (202-02240)SYS240$70.00$40.00$50.00$60.00$34.92$47.75
0013Present structure, remove portions, structure no. 1 (202-51328)LS1$100,000$120,000$82,000$85,250$54,466$200,000
0014Bridge railing, remove (202-62420)LFT80$30.00$50.00$105.00$110.00$73.67$80.54
0015Excavation, common (203-02000)CYS125$65.00$120.00$60.00$130.00$62.40$60.18
0016Stormwater management budget (205-12108)DOL1,800$1.00$1.00$1.00$1.00$1.00$1.00
0017Stormwater management implementation (205-12616)LS1$2,500.00$15,000$7,500.00$8,600.00$7,523.17$12,950
0018Subgrade treatment, type IC (207-09935)SYS540$50.00$60.00$55.00$65.00$50.78$55.73
0019Aggregate for end bent backfill (211-06467)CYS40$150.00$100.00$150.00$190.00$117.37$95.50
0020Geotextile for pavement, type 2B (214-12239)SYS540$6.00$10.00$7.00$7.00$6.26$5.20
0021Compacted aggregate, no. 53 (301-12234)CYS48$110.00$120.00$145.00$120.00$87.22$108.70
0022Subbase for PCCP (302-06464)CYS60$190.00$120.00$85.00$230.00$182.76$91.10
0023Compacted aggregate, no. 53 (303-01180)TON131$55.00$60.00$60.00$75.00$54.54$58.19
0024Milling, transition (306-08043)SYS725$6.00$11.25$8.00$5.00$9.00$4.40
0025QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002)TON85$160.00$225.00$185.00$160.00$160.00$185.00
0026QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038)TON45$157.00$210.00$230.00$157.00$157.00$230.00
0027QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047)TON180$133.00$140.00$155.00$133.00$133.00$155.00
0028Joint adhesive (401-11526)LFT810$0.55$0.50$0.50$0.55$0.55$0.05
0029Asphalt for tack coat (406-05521)SYS1,015$0.45$0.25$0.75$0.45$0.45$0.75
0030Terminal joint, type HMA (503-12477)LFT87$400.00$250.00$450.00$500.00$351.96$318.64
0031Joints in PCCP, filled (507-08271)LFT72$18.00$5.00$15.00$40.00$5.00$5.00
0032Guardrail transition, type TGB (601-01522)EACH1$2,670.00$2,670.00$2,670.00$2,670.00$2,670.00$3,343.00
0033Guardrail terminal system, W-beam curved, type 3 (601-01846)EACH1$2,660.00$2,660.00$2,660.00$2,660.00$2,660.00$3,254.00
0034Guardrail, remove (601-02241)LFT340$6.00$6.00$6.00$6.00$6.00$5.00
0035Hand dig guardrail post holes (601-09238)EACH2$85.00$85.00$85.00$85.00$85.00$208.00
0036Guardrail transition, MGS without curb (601-12292)EACH3$3,125.00$3,125.00$3,125.00$3,125.00$3,125.00$3,345.00
0037Guardrail end treatment, type OS (601-94689)EACH3$3,475.00$3,475.00$3,475.00$4,300.00$3,475.00$3,478.00
0038Barrier delineator (602-06729)EACH8$30.00$40.00$25.00$35.00$31.30$25.00
0039Reinforced concrete bridge approach, 12 in. (609-06259)SYS249$175.00$175.00$185.00$235.00$178.73$156.06
0040HMA for approaches, type B (610-07487)TON2$195.00$500.00$185.00$195.00$195.00$800.00
0041Field office, type C (628-09403)MOS8$3,300.00$2,500.00$3,350.00$3,700.00$3,941.92$3,500.00
0042Field drilled hole in concrete (702-51863)EACH80$45.00$50.00$58.00$50.00$77.38$35.96
0043Reinforcing bars, epoxy coated (703-06029)LBS24,807$2.50$1.20$2.50$2.00$1.45$1.40
0044Threaded tie bar assembly, epoxy coated (703-97936)EACH48$50.00$40.00$62.00$60.00$44.72$41.56
0045Concrete, C, superstructure (704-51002)CYS35.80$2,000.00$1,200.00$2,250.00$2,500.00$2,686.01$1,350.00
0046Railing, concrete type FC (706-09960)LFT30.50$150.00$76.00$275.00$350.00$382.15$200.00
0047Concrete bridge railing transition, type TFC , modified (706-11620)EACH4$3,300.00$3,200.00$3,850.00$3,900.00$4,037.89$2,808.06
0048Fiber wrap concrete casing system (709-04647)LS1$15,900$15,900$15,900$20,000$15,900$15,900
0049Surface seal , bridge no. 1 (709-51821)LS1$5,000.00$10,000$6,512.00$6,500.00$3,400.00$6,512.00
0050Surface seal , bridge no. 2 (709-51821)LS1$2,000.00$10,000$2,980.00$3,000.00$7,300.00$2,980.00
0051Patching concrete structures (710-09158)SFT58$17.03$200.00$31.33$17.00$17.03$17.03
0052Jacking and supporting superstructure , bridge no. 1 (711-90114)LS1$25,000$50,000$62,500$50,500$73,709$172,084
0053Pipe, end bent drain, diameter 6 in. (715-05407)LFT100$15.00$30.00$25.00$25.00$20.05$18.38
0054Geotextile for underdrains, type 2B (718-12308)SYS51$20.00$10.00$13.00$12.00$44.35$20.07
0055Bridge deck overlay, rigid (722-000134)SYS1,243$60.00$75.00$155.00$160.00$68.25$149.07
0056Hydrodemolition (722-01066)SYS1,243$50.00$75.00$68.00$85.00$62.26$77.12
0057Bridge deck overlay budget (722-12380)DOL20,400$1.00$1.00$1.00$1.00$1.00$1.00
0058Bridge deck, remove concrete surface (722-12464)SYS1,243$5.00$10.00$12.00$9.00$18.74$6.60
0059Longitudinal grooving (722-12732)SYS1,485$3.50$6.00$12.00$5.00$4.26$9.48
0060Bridge deck patching, full depth (722-51401)SFT1,120$9.50$30.00$40.00$25.00$111.98$57.00
0061Bearing assembly, elastomeric (726-92406)EACH24$900.00$1,600.00$1,250.00$1,500.00$621.03$746.95
0062Warranted polymer overlay, bridge deck (738-12855)SYS777$45.15$45.15$55.00$50.00$50.03$45.15
0063Polymer overlay, other concrete surface (738-12856)SYS187$24.00$24.00$35.00$25.00$32.33$24.00
0064Road closure sign assembly (801-04308)EACH20$325.00$325.00$325.00$325.00$325.00$325.00
0065Detour route marker assembly (801-06625)EACH66$130.00$130.00$130.00$130.00$130.00$130.00
0066Construction sign, type A (801-06640)EACH42$180.00$180.00$180.00$180.00$180.00$180.00
0067Construction sign, type B (801-06645)EACH21$100.00$100.00$100.00$100.00$100.00$100.00
0068Maintaining traffic (801-06775)LS1$10,000$38,420$46,000$29,750$50,260$16,416
0069Barricade, type III-A (801-07118)LFT184$16.00$16.00$16.00$16.00$16.00$16.00
0070Barricade, type III-B (801-07119)LFT284$16.00$16.00$16.00$16.00$16.00$16.00
0071Portable changeable message sign (801-11642)EACH2$5,213.00$5,213.00$5,213.00$5,200.00$5,213.00$5,213.00
0072Sign, ground mounted, reset (802-91122)EACH2$330.00$330.00$330.00$330.00$330.00$208.00
0073Line, multi-component, solid, white, 6 in. (808-10049)LFT1,033$1.50$1.50$1.50$1.50$1.50$1.50
0074Line, multi-component, solid, yellow, 6 in. (808-10057)LFT1,033$1.50$1.50$1.50$1.50$1.50$1.50
0076Line, paint, solid, yellow, 6 in. (808-75047)LFT464$1.00$1.00$1.00$1.00$1.00$1.00
0077Snowplowable raised pavement marker, remove (808-75996)EACH25$50.00$5.00$35.00$24.00$28.67$50.00
0078Snowplowable raised pavement marker (808-75998)EACH13$75.00$75.00$75.00$250.00$75.00$75.00
0079Line, paint, solid, white, 6 in. (808-75007)LFT464$1.00$1.00$1.00$1.00$1.00$1.00
0080Railroad flagging budget (107-12976)DOL24,000$1.00$1.00$1.00$1.00$1.00$1.00
INDOT contract B-43799-A: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

Every contract let that day: INDOT letting of September 10, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy