INDOT contract B-43883-A bid tabulation
SCOUR PROTECTION. Let by Indiana DOT on December 10, 2025, Marion, Greenfield. 5 bids received; low bid $771,695 by Morphey Construction Inc..
- Owner
- Indiana DOT
- Letting
- 10 DEC 2025
- Pay items
- 38
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Morphey Construction Inc. | $771,695 | Low |
| 2 | William Charles Construction Company | $815,000 | +6.0% |
| 3 | E & B Paving LLC | $860,200 | +11% |
| 4 | Rieth-Riley Construction Co., Inc. | $864,323 | +12% |
| 5 | Beaty Construction Inc | $1,018,753 | +32% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Morphey Construction Inc. | 2. William Charles Construction Company | 3. E & B Paving LLC | 4. Rieth-Riley Construction Co., Inc. | 5. Beaty Construction Inc |
|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $10,000 | $25,000 | $12,500 | $9,800.00 | $15,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Mobilization and demobilization (110-01001) | LS | 1 | $40,000 | $50,000 | $43,500 | $38,455 | $50,000 |
| 0009 | Clearing and grubbing (201-01015) | LS | 1 | $30,000 | $30,000 | $28,915 | $50,340 | $50,000 |
| 0010 | Paved side ditch, remove (202-02272) | LFT | 22 | $150.00 | $135.00 | $85.00 | $125.33 | $75.00 |
| 0011 | Slopewall, remove (202-51368) | SYS | 1,091 | $55.00 | $45.00 | $125.00 | $50.15 | $50.00 |
| 0012 | Stormwater management budget (205-12108) | DOL | 8,900 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0013 | Stormwater management implementation (205-12616) | LS | 1 | $7,000.00 | $10,000 | $12,500 | $17,982 | $5,000.00 |
| 0014 | Flowable backfill, non- removable (213-09269) | CYS | 15 | $400.00 | $700.00 | $1,200.00 | $386.64 | $325.00 |
| 0016 | Guardrail, reset (601-06035) | LFT | 800 | $10.50 | $10.50 | $10.50 | $10.50 | $10.50 |
| 0017 | Temporary guardrail end treatment, type OS (601-97080) | EACH | 2 | $4,570.00 | $4,570.00 | $4,570.00 | $4,570.00 | $4,570.00 |
| 0018 | Paved side ditch, type A (607-06335) | LFT | 22 | $280.00 | $300.00 | $350.00 | $96.96 | $125.00 |
| 0019 | Riprap, class 2 (616-05689) | TON | 103 | $180.00 | $400.00 | $150.00 | $324.01 | $130.00 |
| 0020 | Riprap, revetment (616-06405) | TON | 3 | $140.00 | $900.00 | $500.00 | $655.38 | $750.00 |
| 0021 | Geotextile for riprap, type 1A (616-12246) | SYS | 118 | $4.00 | $30.00 | $11.00 | $8.47 | $4.00 |
| 0022 | Slopewall, concrete, 5 in. (616-51366) | SYS | 1,091 | $175.00 | $150.00 | $225.00 | $311.99 | $200.00 |
| 0023 | Field office, type C (628-09403) | MOS | 6 | $3,000.00 | $3,000.00 | $3,000.00 | $4,943.90 | $4,500.00 |
| 0024 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 10,110 | $4.00 | $2.30 | $2.31 | $2.31 | $2.31 |
| 0025 | Construction sign, type A (801-06640) | EACH | 17 | $195.00 | $204.00 | $192.00 | $204.00 | $204.00 |
| 0026 | Construction sign, type B (801-06645) | EACH | 8 | $98.00 | $130.00 | $130.00 | $130.00 | $130.00 |
| 0027 | Maintaining traffic (801-06775) | LS | 1 | $98,234 | $110,230 | $63,495 | $77,415 | $300,000 |
| 0028 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 4 | $5,845.00 | $5,845.00 | $5,845.00 | $5,845.00 | $5,845.00 |
| 0029 | Temporary traffic barrier, type 2 (801-08401) | LFT | 1,000 | $85.00 | $52.00 | $20.00 | $55.30 | $55.00 |
| 0030 | Portable changeable message sign (801-11642) | EACH | 5 | $3,500.00 | $1,990.00 | $1,592.00 | $1,990.00 | $1,990.00 |
| 0031 | Truck mounted attenuator (801-12042) | DAY | 20 | $800.00 | $300.00 | $500.00 | $1,410.26 | $1,000.00 |
| 0032 | Temporary worksite speed limit sign assembly, intermittent (801-12930) | EACH | 4 | $1,500.00 | $1,875.00 | $1,875.00 | $1,875.00 | $1,875.00 |
| 0033 | Cofferdam (206-51235) | LS | 1 | $50,000 | $125,000 | $120,000 | $9,222.63 | $90,000 |
| 0034 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 0035 | Seed mixture, floodplain (621-12612) | LBS | 7 | $1,000.00 | $1,000.00 | $600.00 | $600.00 | $1,000.00 |
| 0036 | Construction sign, type C (801-03290) | EACH | 2 | $195.00 | $313.00 | $313.00 | $313.00 | $313.00 |
| 0037 | Road closure sign assembly (801-04308) | EACH | 1 | $295.00 | $206.00 | $206.00 | $206.00 | $206.00 |
| 0038 | Detour route marker assembly (801-06625) | EACH | 19 | $195.00 | $178.00 | $178.00 | $178.00 | $178.00 |
| 0039 | Barricade, type III-A (801-07118) | LFT | 24 | $16.00 | $11.00 | $11.00 | $11.00 | $11.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of December 10, 2025. Compiled by Mirage Metrics.