INDOT contract B-43993-A bid tabulation

BRIDGE REPLACEMENT. Let by Indiana DOT on August 6, 2025, Greene, Vincennes. 6 bids received; low bid $1,571,866 by Duncan Robertson Inc.

Owner
Indiana DOT
Letting
06 AUG 2025
Pay items
76
Data through
05 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Duncan Robertson Inc$1,571,866Low
2CLR Inc$1,895,967+21%
3Pontem Contractors Inc$2,274,121+45%
4Ragle, Inc.$2,342,301+49%
5E & B Paving LLC$2,409,049+53%
6Milestone Contractors LP$2,572,380+64%
INDOT contract B-43993-A: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Duncan Robertson Inc2. CLR Inc3. Pontem Contractors Inc4. Ragle, Inc.5. E & B Paving LLC6. Milestone Contractors LP
0001Construction engineering (105-06845)LS1$15,000$49,000$50,000$27,250$41,000$16,000
0002Liquidated damages (109-08359)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0003Contract liens (109-08360)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0004Quality adjustments, HMA (109-08440)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0005Quality adjustments, temporary traffic control devices (109-08443)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0006Quality adjustments, failed materials (109-08444)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0007Payment adjustment, PG asphalt binder (109-09489)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0008Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0009Mobilization and demobilization (110-01001)LS1$78,500$94,750$112,900$117,000$115,965$125,000
0010Clearing right-of-way (201-52370)LS1$30,000$38,000$45,100$46,500$47,000$50,000
0011Pavement removal (202-02240)SYS166$35.00$56.00$45.00$30.00$80.00$27.00
0012Present structure, remove, structure no. 1 (202-51330)LS1$75,000$125,000$226,521$220,000$138,900$270,000
0013Pipe, remove (202-96133)LFT115$12.00$10.00$31.13$62.25$28.00$30.00
0014Excavation, common (203-02000)CYS2,255$25.00$58.00$80.00$35.00$70.00$56.00
0015Borrow (203-02070)CYS1,839$35.00$21.00$29.78$35.00$46.00$60.00
0016Excavation, waterway (203-51223)CYS340$55.00$36.00$126.90$35.00$50.00$60.00
0017Stormwater management budget (205-12108)DOL32,523$1.00$1.00$1.00$1.00$1.00$1.00
0018Stormwater management implementation (205-12616)LS1$17,500$5,000.00$48,639$25,000$80,000$20,000
0019SWQCP preparation (205-12618)LS1$2,000.00$1,250.00$5,940.22$1,600.00$2,000.00$2,500.00
0020Excavation, wet (206-51220)CYS130$80.00$95.00$110.95$1.00$200.00$250.00
0021Cofferdam (206-51235)LS1$25,000$10,000$100,000$1.00$155,000$197,420
0022Subgrade treatment, type IC (207-09935)SYS1,908$25.00$42.00$40.91$30.00$33.00$44.00
0023B borrow (211-02050)CYS670$40.00$54.00$55.00$58.50$65.00$60.00
0024Structure backfill, type 1 (211-09264)CYS14$120.00$55.00$100.34$55.00$85.00$70.00
0025Structure backfill, type 4 (211-09267)CYS18$275.00$300.00$289.77$435.00$410.00$350.00
0026Geotextile for pavement, type 2B (214-12239)SYS192$5.00$10.00$10.39$4.25$9.00$9.00
0027Subbase for PCCP (302-06464)CYS48$110.00$125.00$172.17$145.00$105.00$232.00
0028Compacted aggregate, no. 53 (303-01180)TON354$45.00$35.00$50.18$45.00$62.00$50.00
0029Milling, asphalt, 1 1/2 in. (306-08034)SYS183$25.00$14.00$24.29$21.00$35.00$20.00
0030QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002)TON154$158.00$160.00$151.20$144.00$144.00$260.00
0031QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038)TON230$114.00$116.00$109.20$104.00$104.00$165.00
0032QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047)TON551$107.00$97.00$101.85$97.00$97.00$127.00
0033Joint adhesive, surface (401-10258)LFT620$1.70$1.55$1.63$1.55$1.55$1.00
0034Joint adhesive, intermediate (401-10259)LFT545$1.90$1.75$1.84$1.75$1.76$1.00
0035Asphalt for tack coat (406-05521)SYS3,515$0.33$0.30$0.32$0.30$0.30$0.40
0036Guardrail, remove (601-02241)LFT585$7.15$7.00$6.83$6.50$6.50$6.50
0037Guardrail transition, MGS without curb (601-12292)EACH4$3,300.00$3,325.00$3,150.00$3,000.00$3,000.00$3,000.00
0038Guardrail end treatment, type OS (601-94689)EACH4$3,410.00$3,450.00$3,255.00$3,100.00$3,100.00$3,100.00
0039Barrier delineator (602-06729)EACH8$20.00$50.00$132.55$25.00$40.00$35.00
0040Reinforced concrete bridge approach, 12 in. (609-06259)SYS194$210.00$225.00$236.36$230.00$215.00$240.00
0041Monument, type B (615-06505)EACH7$1,210.00$500.00$1,155.00$1,100.00$1,100.00$1,100.00
0042Riprap, revetment (616-06405)TON348$50.00$84.00$58.64$83.64$75.00$90.00
0043Geotextile for riprap, type 1A (616-12246)SYS711$3.50$6.50$3.86$5.65$3.00$3.00
0044Mobilization and demobilization for seeding (621-01004)EACH1$1,650.00$2,500.00$1,575.00$1,500.00$1,500.00$1,500.00
0045Mulched seeding, type R (621-06559)SYS5,560$1.37$1.80$1.31$1.25$1.50$1.25
0046Water (621-06567)KGAL1$0.10$1.00$0.11$0.10$0.10$0.10
0047Sodding (621-06574)SYS142$31.00$8.95$52.45$35.00$30.00$28.00
0048Computer system equipment (628-11976)EACH2$750.00$100.00$1,078.33$750.00$875.00$1,200.00
0049Field office, type D (628-12683)MOS18$2,500.00$1,000.00$2,931.11$3,100.00$2,850.00$3,500.00
0050Plant growth layer (629-12029)SYS5,657$6.00$2.65$14.58$8.50$10.00$4.50
0051Dynamic pile load test (701-06011)EACH4$750.00$750.00$1,399.55$3,500.00$4,500.00$4,000.00
0052Test pile, dynamic, production (701-09557)LFT367$55.00$66.00$70.10$90.00$80.00$50.00
0053Test pile, dynamic, restrike (701-09559)EACH4$750.00$1,500.00$1,399.55$1,500.00$3,750.00$5,000.00
0054Pile shoe, HP 12 X 53 (701-09739)EACH22$225.00$210.00$120.12$185.00$150.00$390.00
0055Reinforced concrete encasement for H piles (701-12709)LFT168$210.00$588.00$342.03$625.00$375.00$570.00
0056Pile, steel H, HP 12 X 53 (701-51195)LFT1,470$70.00$84.00$79.93$90.00$100.00$130.00
0057Reinforcing bars, epoxy coated (703-06029)LBS73,995$1.40$1.90$1.40$1.75$1.60$1.60
0058Threaded tie bar assembly, epoxy coated (703-97936)EACH34$60.00$30.00$49.18$55.00$50.00$62.00
0059Concrete, C, superstructure (704-51002)CYS318$1,115.00$1,325.00$1,181.08$2,200.00$1,550.00$1,500.00
0060Railing, concrete type FC (706-11600)CYS22$1,200.00$1,395.00$1,118.25$1,065.00$1,065.00$1,100.00
0061Concrete bridge railing transition, type TFC (706-11620)EACH4$2,000.00$2,125.00$1,569.75$1,495.00$1,495.00$1,500.00
0062Surface seal (709-51821)LS1$2,500.00$1,900.00$3,675.00$1.00$2,500.00$1.00
0063Pipe, type 3, circular, diameter 24 in. (715-05173)LFT92$100.00$65.00$74.91$85.00$102.00$120.00
0064Pipe end section, diameter 24 in. (715-46020)EACH2$750.00$810.00$760.50$1,500.00$925.00$1,500.00
0065Longitudinal grooving (722-12732)SYS581$10.00$6.75$12.91$6.00$12.00$6.00
0066Road closure sign assembly (801-04308)EACH7$181.00$165.00$372.75$355.00$355.00$355.00
0067Detour route marker assembly (801-06625)EACH42$93.00$85.00$147.00$140.00$140.00$140.00
0068Construction sign, type A (801-06640)EACH37$165.00$150.00$162.75$155.00$155.00$155.00
0069Maintaining traffic (801-06775)LS1$12,500$21,042$50,000$40,000$45,000$2,455.00
0070Barricade, type III-A (801-07118)LFT72$16.50$16.00$17.38$16.55$16.55$16.55
0071Barricade, type III-B (801-07119)LFT42$17.50$17.00$17.38$16.55$16.55$16.55
0072Portable changeable message sign (801-11642)EACH2$5,500.00$5,000.00$4,992.75$4,755.00$4,755.00$4,755.00
0073Reference post (802-04893)EACH1$313.00$315.00$299.25$285.00$285.00$285.00
0074Sign, sheet, and supports, remove (802-07059)EACH6$91.00$60.00$87.15$50.00$83.00$83.00
0075Line, paint, solid, white, 6 in. (808-75007)LFT1,580$1.20$1.20$0.68$0.65$0.65$0.65
0076Line, paint, solid, yellow, 6 in. (808-75047)LFT1,580$1.20$1.20$0.68$0.65$0.65$0.65
INDOT contract B-43993-A: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

Every contract let that day: INDOT letting of August 6, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy