INDOT contract B-43993-A bid tabulation
BRIDGE REPLACEMENT. Let by Indiana DOT on August 6, 2025, Greene, Vincennes. 6 bids received; low bid $1,571,866 by Duncan Robertson Inc.
- Owner
- Indiana DOT
- Letting
- 06 AUG 2025
- Pay items
- 76
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Duncan Robertson Inc | $1,571,866 | Low |
| 2 | CLR Inc | $1,895,967 | +21% |
| 3 | Pontem Contractors Inc | $2,274,121 | +45% |
| 4 | Ragle, Inc. | $2,342,301 | +49% |
| 5 | E & B Paving LLC | $2,409,049 | +53% |
| 6 | Milestone Contractors LP | $2,572,380 | +64% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Duncan Robertson Inc | 2. CLR Inc | 3. Pontem Contractors Inc | 4. Ragle, Inc. | 5. E & B Paving LLC | 6. Milestone Contractors LP |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $15,000 | $49,000 | $50,000 | $27,250 | $41,000 | $16,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $78,500 | $94,750 | $112,900 | $117,000 | $115,965 | $125,000 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $30,000 | $38,000 | $45,100 | $46,500 | $47,000 | $50,000 |
| 0011 | Pavement removal (202-02240) | SYS | 166 | $35.00 | $56.00 | $45.00 | $30.00 | $80.00 | $27.00 |
| 0012 | Present structure, remove, structure no. 1 (202-51330) | LS | 1 | $75,000 | $125,000 | $226,521 | $220,000 | $138,900 | $270,000 |
| 0013 | Pipe, remove (202-96133) | LFT | 115 | $12.00 | $10.00 | $31.13 | $62.25 | $28.00 | $30.00 |
| 0014 | Excavation, common (203-02000) | CYS | 2,255 | $25.00 | $58.00 | $80.00 | $35.00 | $70.00 | $56.00 |
| 0015 | Borrow (203-02070) | CYS | 1,839 | $35.00 | $21.00 | $29.78 | $35.00 | $46.00 | $60.00 |
| 0016 | Excavation, waterway (203-51223) | CYS | 340 | $55.00 | $36.00 | $126.90 | $35.00 | $50.00 | $60.00 |
| 0017 | Stormwater management budget (205-12108) | DOL | 32,523 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0018 | Stormwater management implementation (205-12616) | LS | 1 | $17,500 | $5,000.00 | $48,639 | $25,000 | $80,000 | $20,000 |
| 0019 | SWQCP preparation (205-12618) | LS | 1 | $2,000.00 | $1,250.00 | $5,940.22 | $1,600.00 | $2,000.00 | $2,500.00 |
| 0020 | Excavation, wet (206-51220) | CYS | 130 | $80.00 | $95.00 | $110.95 | $1.00 | $200.00 | $250.00 |
| 0021 | Cofferdam (206-51235) | LS | 1 | $25,000 | $10,000 | $100,000 | $1.00 | $155,000 | $197,420 |
| 0022 | Subgrade treatment, type IC (207-09935) | SYS | 1,908 | $25.00 | $42.00 | $40.91 | $30.00 | $33.00 | $44.00 |
| 0023 | B borrow (211-02050) | CYS | 670 | $40.00 | $54.00 | $55.00 | $58.50 | $65.00 | $60.00 |
| 0024 | Structure backfill, type 1 (211-09264) | CYS | 14 | $120.00 | $55.00 | $100.34 | $55.00 | $85.00 | $70.00 |
| 0025 | Structure backfill, type 4 (211-09267) | CYS | 18 | $275.00 | $300.00 | $289.77 | $435.00 | $410.00 | $350.00 |
| 0026 | Geotextile for pavement, type 2B (214-12239) | SYS | 192 | $5.00 | $10.00 | $10.39 | $4.25 | $9.00 | $9.00 |
| 0027 | Subbase for PCCP (302-06464) | CYS | 48 | $110.00 | $125.00 | $172.17 | $145.00 | $105.00 | $232.00 |
| 0028 | Compacted aggregate, no. 53 (303-01180) | TON | 354 | $45.00 | $35.00 | $50.18 | $45.00 | $62.00 | $50.00 |
| 0029 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 183 | $25.00 | $14.00 | $24.29 | $21.00 | $35.00 | $20.00 |
| 0030 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 154 | $158.00 | $160.00 | $151.20 | $144.00 | $144.00 | $260.00 |
| 0031 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 230 | $114.00 | $116.00 | $109.20 | $104.00 | $104.00 | $165.00 |
| 0032 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 551 | $107.00 | $97.00 | $101.85 | $97.00 | $97.00 | $127.00 |
| 0033 | Joint adhesive, surface (401-10258) | LFT | 620 | $1.70 | $1.55 | $1.63 | $1.55 | $1.55 | $1.00 |
| 0034 | Joint adhesive, intermediate (401-10259) | LFT | 545 | $1.90 | $1.75 | $1.84 | $1.75 | $1.76 | $1.00 |
| 0035 | Asphalt for tack coat (406-05521) | SYS | 3,515 | $0.33 | $0.30 | $0.32 | $0.30 | $0.30 | $0.40 |
| 0036 | Guardrail, remove (601-02241) | LFT | 585 | $7.15 | $7.00 | $6.83 | $6.50 | $6.50 | $6.50 |
| 0037 | Guardrail transition, MGS without curb (601-12292) | EACH | 4 | $3,300.00 | $3,325.00 | $3,150.00 | $3,000.00 | $3,000.00 | $3,000.00 |
| 0038 | Guardrail end treatment, type OS (601-94689) | EACH | 4 | $3,410.00 | $3,450.00 | $3,255.00 | $3,100.00 | $3,100.00 | $3,100.00 |
| 0039 | Barrier delineator (602-06729) | EACH | 8 | $20.00 | $50.00 | $132.55 | $25.00 | $40.00 | $35.00 |
| 0040 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 194 | $210.00 | $225.00 | $236.36 | $230.00 | $215.00 | $240.00 |
| 0041 | Monument, type B (615-06505) | EACH | 7 | $1,210.00 | $500.00 | $1,155.00 | $1,100.00 | $1,100.00 | $1,100.00 |
| 0042 | Riprap, revetment (616-06405) | TON | 348 | $50.00 | $84.00 | $58.64 | $83.64 | $75.00 | $90.00 |
| 0043 | Geotextile for riprap, type 1A (616-12246) | SYS | 711 | $3.50 | $6.50 | $3.86 | $5.65 | $3.00 | $3.00 |
| 0044 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $1,650.00 | $2,500.00 | $1,575.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 0045 | Mulched seeding, type R (621-06559) | SYS | 5,560 | $1.37 | $1.80 | $1.31 | $1.25 | $1.50 | $1.25 |
| 0046 | Water (621-06567) | KGAL | 1 | $0.10 | $1.00 | $0.11 | $0.10 | $0.10 | $0.10 |
| 0047 | Sodding (621-06574) | SYS | 142 | $31.00 | $8.95 | $52.45 | $35.00 | $30.00 | $28.00 |
| 0048 | Computer system equipment (628-11976) | EACH | 2 | $750.00 | $100.00 | $1,078.33 | $750.00 | $875.00 | $1,200.00 |
| 0049 | Field office, type D (628-12683) | MOS | 18 | $2,500.00 | $1,000.00 | $2,931.11 | $3,100.00 | $2,850.00 | $3,500.00 |
| 0050 | Plant growth layer (629-12029) | SYS | 5,657 | $6.00 | $2.65 | $14.58 | $8.50 | $10.00 | $4.50 |
| 0051 | Dynamic pile load test (701-06011) | EACH | 4 | $750.00 | $750.00 | $1,399.55 | $3,500.00 | $4,500.00 | $4,000.00 |
| 0052 | Test pile, dynamic, production (701-09557) | LFT | 367 | $55.00 | $66.00 | $70.10 | $90.00 | $80.00 | $50.00 |
| 0053 | Test pile, dynamic, restrike (701-09559) | EACH | 4 | $750.00 | $1,500.00 | $1,399.55 | $1,500.00 | $3,750.00 | $5,000.00 |
| 0054 | Pile shoe, HP 12 X 53 (701-09739) | EACH | 22 | $225.00 | $210.00 | $120.12 | $185.00 | $150.00 | $390.00 |
| 0055 | Reinforced concrete encasement for H piles (701-12709) | LFT | 168 | $210.00 | $588.00 | $342.03 | $625.00 | $375.00 | $570.00 |
| 0056 | Pile, steel H, HP 12 X 53 (701-51195) | LFT | 1,470 | $70.00 | $84.00 | $79.93 | $90.00 | $100.00 | $130.00 |
| 0057 | Reinforcing bars, epoxy coated (703-06029) | LBS | 73,995 | $1.40 | $1.90 | $1.40 | $1.75 | $1.60 | $1.60 |
| 0058 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 34 | $60.00 | $30.00 | $49.18 | $55.00 | $50.00 | $62.00 |
| 0059 | Concrete, C, superstructure (704-51002) | CYS | 318 | $1,115.00 | $1,325.00 | $1,181.08 | $2,200.00 | $1,550.00 | $1,500.00 |
| 0060 | Railing, concrete type FC (706-11600) | CYS | 22 | $1,200.00 | $1,395.00 | $1,118.25 | $1,065.00 | $1,065.00 | $1,100.00 |
| 0061 | Concrete bridge railing transition, type TFC (706-11620) | EACH | 4 | $2,000.00 | $2,125.00 | $1,569.75 | $1,495.00 | $1,495.00 | $1,500.00 |
| 0062 | Surface seal (709-51821) | LS | 1 | $2,500.00 | $1,900.00 | $3,675.00 | $1.00 | $2,500.00 | $1.00 |
| 0063 | Pipe, type 3, circular, diameter 24 in. (715-05173) | LFT | 92 | $100.00 | $65.00 | $74.91 | $85.00 | $102.00 | $120.00 |
| 0064 | Pipe end section, diameter 24 in. (715-46020) | EACH | 2 | $750.00 | $810.00 | $760.50 | $1,500.00 | $925.00 | $1,500.00 |
| 0065 | Longitudinal grooving (722-12732) | SYS | 581 | $10.00 | $6.75 | $12.91 | $6.00 | $12.00 | $6.00 |
| 0066 | Road closure sign assembly (801-04308) | EACH | 7 | $181.00 | $165.00 | $372.75 | $355.00 | $355.00 | $355.00 |
| 0067 | Detour route marker assembly (801-06625) | EACH | 42 | $93.00 | $85.00 | $147.00 | $140.00 | $140.00 | $140.00 |
| 0068 | Construction sign, type A (801-06640) | EACH | 37 | $165.00 | $150.00 | $162.75 | $155.00 | $155.00 | $155.00 |
| 0069 | Maintaining traffic (801-06775) | LS | 1 | $12,500 | $21,042 | $50,000 | $40,000 | $45,000 | $2,455.00 |
| 0070 | Barricade, type III-A (801-07118) | LFT | 72 | $16.50 | $16.00 | $17.38 | $16.55 | $16.55 | $16.55 |
| 0071 | Barricade, type III-B (801-07119) | LFT | 42 | $17.50 | $17.00 | $17.38 | $16.55 | $16.55 | $16.55 |
| 0072 | Portable changeable message sign (801-11642) | EACH | 2 | $5,500.00 | $5,000.00 | $4,992.75 | $4,755.00 | $4,755.00 | $4,755.00 |
| 0073 | Reference post (802-04893) | EACH | 1 | $313.00 | $315.00 | $299.25 | $285.00 | $285.00 | $285.00 |
| 0074 | Sign, sheet, and supports, remove (802-07059) | EACH | 6 | $91.00 | $60.00 | $87.15 | $50.00 | $83.00 | $83.00 |
| 0075 | Line, paint, solid, white, 6 in. (808-75007) | LFT | 1,580 | $1.20 | $1.20 | $0.68 | $0.65 | $0.65 | $0.65 |
| 0076 | Line, paint, solid, yellow, 6 in. (808-75047) | LFT | 1,580 | $1.20 | $1.20 | $0.68 | $0.65 | $0.65 | $0.65 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of August 6, 2025. Compiled by Mirage Metrics.