INDOT contract B-43998-A bid tabulation

BRIDGE DECK OVERLAY, SMALL STRUCTURES AND DRAINS CONSTR. Let by Indiana DOT on January 14, 2026, Lawrence, Vincennes. 5 bids received; low bid $2,921,032 by Ragle, Inc..

Owner
Indiana DOT
Letting
14 JAN 2026
Pay items
130
Data through
05 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Ragle, Inc.$2,921,032Low
2CLR Inc$3,016,445+3.0%
3E & B Paving LLC$3,096,960+6.0%
4Milestone Contractors LP$3,641,280+25%
5American Contracting & Services Inc$3,686,374+26%
INDOT contract B-43998-A: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Ragle, Inc.2. CLR Inc3. E & B Paving LLC4. Milestone Contractors LP5. American Contracting & Services Inc
0001Construction engineering (105-06845)LS1$25,000$100,000$20,000$7,900.00$20,000
0002Liquidated damages (109-08359)DOL1$1.00$1.00$1.00$1.00$1.00
0003Contract liens (109-08360)DOL1$1.00$1.00$1.00$1.00$1.00
0004Quality adjustments, HMA (109-08440)DOL1$1.00$1.00$1.00$1.00$1.00
0005Quality adjustments, temporary traffic control devices (109-08443)DOL1$1.00$1.00$1.00$1.00$1.00
0006Quality adjustments, failed materials (109-08444)DOL1$1.00$1.00$1.00$1.00$1.00
0007Project estimate adjustment (109-08463)DOL1$1.00$1.00$1.00$1.00$1.00
0008Payment adjustment, PG asphalt binder (109-09489)DOL1$1.00$1.00$1.00$1.00$1.00
0009Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362)DOL1$1.00$1.00$1.00$1.00$1.00
0010Mobilization and demobilization (110-01001)LS1$146,000$155,000$150,000$182,100$184,319
0011Clearing right-of-way (201-52370)LS1$116,500$125,000$120,000$145,680$75,000
0012Debris, remove, structure no. CLV 42443 (201-90788)LS1$10,000$1,500.00$4,100.00$5,500.00$15,000
0013Pavement removal (202-02240)SYS182$48.50$85.00$72.25$108.00$90.00
0014Paved side ditch, remove (202-02272)LFT70$10.50$30.00$22.25$37.00$45.00
0015Present structure, remove portions, structure no. 1 (202-51328)LS1$125,000$50,000$82,500$80,110$75,000
0016Bridge railing, remove (202-62420)LFT64$86.50$105.00$103.25$225.00$90.00
0017Pipe, remove (202-96133)LFT100$26.50$25.00$38.25$25.00$50.00
0018Excavation, common (203-02000)CYS78$37.50$92.00$77.50$104.00$300.00
0019Excavation, unclassified (203-02020)CYS1,000$25.00$25.00$20.00$78.00$100.00
0020Linear grading (203-08607)LFT410$4.50$15.00$17.00$18.00$25.00
0021Pump around (205-11626)EACH2$10,000$7,500.00$1,476.00$24,975$8,000.00
0022Stormwater management budget (205-12108)DOL60,380$1.00$1.00$1.00$1.00$1.00
0023Stormwater management implementation (205-12616)LS1$12,500$5,000.00$22,100$11,642$50,000
0024SWQCP preparation (205-12618)LS1$2,450.00$2,200.00$1,900.00$2,500.00$10,000
0025Excavation, foundation, unclassified (206-51230)CYS48$160.00$77.00$108.50$320.00$200.00
0026Cofferdam (206-51235)LS1$200,000$20,000$254,500$108,000$210,000
0027Subgrade treatment, type IC (207-09935)SYS443$47.50$60.00$51.00$88.00$95.00
0028Aggregate for end bent backfill (211-06467)CYS48$125.00$150.00$196.00$165.00$175.00
0029Structure backfill, type 2 (211-09265)CYS735$45.00$75.00$65.00$70.00$155.00
0030Geotextile for pavement, type 2A (214-12238)SYS607$5.00$8.00$6.00$5.00$10.00
0031Geotextile for pavement, type 2B (214-12239)SYS443$5.00$11.00$7.25$8.00$9.00
0032Compacted aggregate, no. 2 (301-12231)CYS16$110.00$190.00$246.00$482.00$225.00
0033Compacted aggregate, no. 8 (301-12233)CYS34$175.00$225.00$140.00$311.00$180.00
0034Subbase for PCCP (302-06464)CYS44$130.00$225.00$237.25$250.00$200.00
0035Compacted aggregate, no. 53 (303-01180)TON20$53.25$105.00$161.50$245.00$75.00
0036Milling, asphalt, 1 1/2 in. (306-08034)SYS954$6.00$11.00$16.00$8.00$15.00
0037Milling, transition (306-08043)SYS754$6.00$13.00$10.25$18.00$15.00
0038Milling, asphalt, 7 in. (306-12937)SYS2,212$17.50$12.00$15.50$16.00$20.00
0039QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002)TON185$229.00$260.00$229.00$385.00$229.00
0040QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005)TON183$133.00$133.00$133.00$200.00$133.00
0041QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038)TON37$560.00$634.00$560.00$800.00$560.00
0042QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041)TON305$109.00$109.00$109.00$130.00$109.00
0043QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047)TON88$305.00$346.00$305.00$360.00$305.00
0044QC/QA-HMA, 3, 58S, base, 19.0 MM (401-000053)TON365$104.00$104.00$104.00$132.00$104.00
0045Joint adhesive (401-11526)LFT5,796$1.25$1.25$1.25$0.70$1.25
0046Asphalt for tack coat (406-05521)SYS4,968$0.25$0.25$0.25$0.16$0.25
0047Cracks and joints in asphalt pavement, rout and seal (408-07478)TON2$1,170.50$1,170.50$1,170.50$1,600.00$1,170.50
0048Guardrail, remove (601-02241)LFT625$4.00$5.00$4.00$4.00$4.00
0049Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281)LFT138$22.00$25.00$22.00$22.00$22.00
0050Guardrail height transition, MGS (601-12289)EACH7$875.00$875.00$875.00$875.00$875.00
0051Guardrail transition, MGS without curb (601-12292)EACH4$3,150.00$3,150.00$3,150.00$3,150.00$3,150.00
0052Guardrail end treatment, type OS (601-94689)EACH1$2,850.00$5,000.00$2,850.00$2,850.00$2,850.00
0053Fence, farm field, reset (603-06060)LFT50$22.00$15.00$22.00$22.00$22.00
0054Paved side ditch, type A (607-06335)LFT60$90.00$65.00$118.00$135.00$250.00
0055Reinforced concrete bridge approach, 12 in. (609-06259)SYS184$235.00$275.00$387.00$325.00$225.00
0056Riprap, class 1 (616-05688)TON311$123.50$135.00$257.00$225.00$175.00
0057Riprap, class 2 (616-05689)TON150$106.25$111.00$120.00$180.00$160.00
0058Riprap, revetment (616-06405)TON558$76.50$54.00$111.50$135.00$145.00
0059Geotextile for riprap, type 1A (616-12246)SYS1,038$3.15$9.00$8.00$4.10$8.00
0060Clean steel bridge, QP-2, bridge no. 1 (619-11052)LS1$180,000$150,000$175,233$170,000$180,000
0061Disposal of cleaning waste, hazardous, bridge no. 1 (619-12459)LS1$10,000$4,500.00$5,154.00$5,000.00$10,000
0062Coat steel bridge, bridge no. 1 (619-51859)LS1$60,000$75,000$92,770$90,000$60,000
0063Clean drains (619-98427)EACH8$50.00$35.00$103.50$45.98$250.00
0064Mobilization and demobilization for seeding (621-01004)EACH3$1,050.00$1,695.00$1,000.00$1,500.00$1,500.00
0065Erosion control blanket (621-02770)SYS10,680$1.46$1.35$1.75$1.75$1.75
0066Seed mixture, type R (621-06553)LBS448$7.90$9.50$12.00$12.00$12.00
0067Mulched seeding, type R (621-06559)SYS1,042$0.91$3.15$2.75$2.75$2.75
0068Sodding (621-06574)SYS287$35.00$20.00$20.00$20.00$20.00
0069Seed mixture, floodplain (621-12612)LBS11$159.00$300.00$30.00$300.00$300.00
0070Computer system equipment (628-11976)EACH2$750.00$100.00$540.00$1,644.43$800.00
0071Field office, type D (628-12683)MOS12$3,200.00$1,000.00$3,300.00$3,500.00$6,000.00
0072Topsoil processing and distribution (629-000149)SYS10,680$3.08$2.50$3.00$21.40$7.00
0073Topsoil amendment budget (629-000150)DOL21,350.44$1.00$1.00$1.00$1.00$1.00
0074Concrete, C, substructure (702-92857)CYS14.60$2,600.00$3,000.00$3,093.00$7,000.00$4,000.00
0075Reinforcing bars, epoxy coated (703-06029)LBS14,418$1.60$2.50$2.25$3.00$2.25
0076Threaded tie bar assembly, epoxy coated (703-97936)EACH108$48.50$40.00$32.00$35.00$60.00
0077Concrete bridge railing transition, type TFC (706-11620)EACH4$5,000.00$3,500.00$5,154.00$8,000.00$7,000.00
0078Surface seal , bridge no. 1 (709-51821)LS1$9,656.78$7,500.00$9,954.00$9,656.78$20,000
0079Surface seal , bridge no. 2 (709-51821)LS1$5,675.87$4,400.00$5,851.00$5,675.87$14,000
0080Patching concrete structures (710-09158)SFT643$175.00$75.00$257.00$249.00$249.00
0081Structural steel (711-51035)LBS4,290$0.75$1.00$5.25$8.00$4.00
0082Jacking and supporting steel beams , bridge no. 1 (711-95291)LS1$50,000$25,000$16,879$13,500$25,000
0083Bolt, remove (711-96479)EACH56$41.50$125.00$92.00$89.29$150.00
0084Pipe, type 1, circular, diameter 36 in. (715-05019)LFT100$760.00$1,405.00$840.00$800.00$1,120.00
0085Pipe, underdrain outlet, diameter 6 in. (715-05053)LFT50$25.00$55.00$60.00$65.00$60.00
0086Pipe, end bent drain, diameter 6 in. (715-05407)LFT82$18.50$55.00$19.00$13.00$70.00
0087Pipe PVC, 6 in. (715-91361)LFT5$400.00$375.00$206.25$185.00$150.00
0088Outlet protector, type 1 (718-06528)EACH2$1,450.00$2,500.00$2,740.00$3,000.00$4,000.00
0089Geotextile for underdrains, type 1A (718-12305)SYS104$4.85$9.00$8.25$9.00$8.00
0090Bridge deck overlay, rigid (722-000134)SYS1,586$100.00$175.00$103.25$130.00$150.00
0091Bridge deck, remove concrete overlay and surface (722-000183)SYS1,586$10.00$15.00$15.50$15.00$25.00
0092Hydrodemolition (722-01066)SYS1,586$73.50$140.00$82.50$72.00$130.00
0093Bridge deck overlay budget (722-12380)DOL32,000$1.00$1.00$1.00$1.00$1.00
0094Longitudinal grooving (722-12732)SYS1,756$5.00$8.00$6.25$4.02$10.00
0095Bridge deck patching, full depth (722-51401)SFT286$60.00$25.00$52.00$74.75$65.00
0096Bridge deck patching, partial depth (722-51852)SFT244$2.50$2.50$4.25$4.00$4.00
0097Overlay dam (722-51874)SFT42$84.50$150.00$237.00$180.00$100.00
0098Bridge expansion joint, type PCF (724-12773)LFT42$96.50$300.00$103.25$250.00$120.00
0099Bridge expansion joint, type SS, replace (724-12774)LFT42$680.00$950.00$1,031.00$800.00$860.00
0100Silicone joint sealant (724-12918)LFT24$15.00$17.00$1.00$1.00$130.00
0101Pipe liner, cured-in- place, 36 in. (725-08293)LFT80$1,200.00$1,205.00$800.00$950.00$1,500.00
0102Bearing assembly, elastomeric (726-92406)EACH14$3,500.00$4,200.00$1,907.00$3,900.00$4,400.00
0103Warranted polymer overlay, bridge deck (738-12855)SYS1,350$45.58$47.50$39.25$38.00$38.00
0104Road closure sign assembly (801-04308)EACH2$300.00$400.00$232.00$232.00$300.00
0105Temporary pavement marking, removable, 6 in. (801-06209)LFT15,880$1.69$1.80$2.03$2.03$1.69
0106Temporary transverse pavement marking, removable, 24 in. (801-06218)LFT24$14.00$12.00$11.59$11.59$14.00
0107Temporary pavement marking, removable, 24 in. (801-06577)LFT24$14.00$12.00$11.59$11.59$14.00
0108Detour route marker assembly (801-06625)EACH45$130.00$75.00$191.00$191.00$130.00
0109Construction sign, type A (801-06640)EACH53$180.00$175.00$176.00$176.00$180.00
0110Construction sign, type B (801-06645)EACH8$100.00$75.00$92.00$92.00$100.00
0111Maintaining traffic (801-06775)LS1$92,250$93,907$80,559$146,000$90,000
0112Energy absorbing terminal, CZ, TL-3 (801-07024)EACH2$6,150.00$8,000.00$6,150.00$6,150.00$8,000.00
0113Barricade, type III-A (801-07118)LFT120$15.00$12.00$13.00$13.00$15.00
0114Barricade, type III-B (801-07119)LFT96$15.00$12.00$14.00$14.00$15.00
0115Temporary traffic barrier, type 2 (801-08401)LFT612$40.00$40.00$36.50$59.00$65.00
0116Temporary traffic barrier, anchored, type 2 (801-08508)LFT495$48.50$96.00$46.50$72.00$70.00
0117Portable changeable message sign (801-11642)EACH2$5,155.00$2,275.00$4,185.31$4,060.00$5,155.00
0118Truck mounted attenuator (801-12042)DAY28$450.00$100.00$220.00$268.00$250.00
0119Portable signal (801-12081)LS1$75,000$65,000$30,415$30,000$20,000
0120Driveway assistance device (801-12482)EACH1$5,000.00$1,500.00$3,000.00$3,000.00$5,000.00
0121Reference post (802-04893)EACH3$215.00$150.00$215.00$215.00$215.00
0122Sign post, square, type 1, reinforced anchor base (802-05701)LFT42$26.00$30.00$26.00$26.00$26.00
0123Sign, sheet, with legend, 0.100 in. thickness (802-09840)SFT10$26.00$30.00$26.00$26.00$26.00
0124Line, remove (808-06716)LFT8,365$0.50$0.50$1.12$1.12$0.50
0125Line, paint, broken, yellow, 6 in. (808-12764)LFT40$0.75$0.85$37.31$37.31$0.75
0126Line, paint, solid, white, 6 in. (808-75007)LFT5,060$0.67$0.85$1.22$1.22$0.67
0127Line, paint, solid, yellow, 6 in. (808-75047)LFT5,140$0.55$0.85$1.20$1.20$0.55
0128Prismatic reflector (808-75994)EACH9$14.00$25.00$28.00$14.00$100.00
0129Snowplowable raised pavement marker, remove (808-75996)EACH52$24.50$25.00$13.00$30.00$25.00
0130Snowplowable raised pavement marker (808-75998)EACH52$45.55$65.00$75.00$75.00$50.00
INDOT contract B-43998-A: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

Every contract let that day: INDOT letting of January 14, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy