INDOT contract B-44507-A bid tabulation
BRIDGE DECK REPLACEMENT, REPLACE SUPERSTRUCTURE AND DRAINS. Let by Indiana DOT on September 2, 2026, Posey, Vincennes. 3 bids received; low bid $22,443,055 by Ragle, Inc..
- Owner
- Indiana DOT
- Letting
- 02 SEP 2026
- Pay items
- 186
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ragle, Inc. | $22,443,055 | Low |
| 2 | Blankenberger Brothers Inc | $24,894,000 | +11% |
| 3 | E & B Paving LLC | $28,947,085 | +29% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ragle, Inc. | 2. Blankenberger Brothers Inc | 3. E & B Paving LLC |
|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $59,250 | $115,000 | $180,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, pavement traffic markings (109-09377) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0009 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0010 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0011 | Mobilization and demobilization (110-01001) | LS | 1 | $1,122,500 | $355,000 | $1,447,354 |
| 0012 | Clearing right-of-way (201-52370) | LS | 1 | $449,000 | $183,000 | $104,059 |
| 0013 | Pavement removal (202-02240) | SYS | 1,152 | $25.00 | $35.75 | $43.50 |
| 0014 | Present structure, remove portions, structure no. 1 (202-51328) | LS | 1 | $250,000 | $295,000 | $988,000 |
| 0015 | Present structure, remove portions, structure no. 2 (202-51328) | LS | 1 | $250,000 | $295,000 | $988,000 |
| 0016 | Present structure, remove portions, structure no. 3 (202-51328) | LS | 1 | $275,000 | $310,000 | $1,350,000 |
| 0017 | Present structure, remove portions, structure no. 4 (202-51328) | LS | 1 | $275,000 | $310,000 | $1,350,000 |
| 0018 | Present structure, remove portions, structure no. 5 (202-51328) | LS | 1 | $50,000 | $70,000 | $110,000 |
| 0019 | Present structure, remove portions, structure no. 6 (202-51328) | LS | 1 | $50,000 | $70,000 | $110,000 |
| 0020 | Inlet, remove (202-91385) | EACH | 7 | $275.00 | $670.00 | $774.00 |
| 0021 | Guardrail end treatment, remove (202-93741) | EACH | 6 | $450.00 | $450.00 | $450.00 |
| 0022 | Pipe, remove (202-96133) | LFT | 241 | $50.00 | $51.10 | $43.00 |
| 0023 | Excavation, common (203-02000) | CYS | 4,395 | $45.00 | $39.65 | $34.90 |
| 0024 | Pump around (205-11626) | EACH | 1 | $8,500.00 | $5,100.00 | $6,400.00 |
| 0025 | Stormwater management budget (205-12108) | DOL | 101,342 | $1.00 | $1.00 | $1.00 |
| 0026 | Stormwater management implementation (205-12616) | LS | 1 | $60,000 | $38,000 | $25,334 |
| 0027 | SWQCP preparation (205-12618) | LS | 1 | $3,200.00 | $5,000.00 | $2,600.00 |
| 0028 | Subgrade treatment, type II (207-08264) | SYS | 7,979 | $23.75 | $21.50 | $22.00 |
| 0029 | Subgrade treatment, type IC (207-09935) | SYS | 4,936 | $73.50 | $46.25 | $46.00 |
| 0030 | B borrow (211-02050) | CYS | 86 | $75.00 | $40.95 | $117.00 |
| 0031 | Aggregate for end bent backfill (211-06467) | CYS | 264 | $165.00 | $215.00 | $245.00 |
| 0032 | Structure backfill, type 2 (211-09265) | CYS | 249 | $93.50 | $73.00 | $58.00 |
| 0033 | Structure backfill, type 4 (211-09267) | CYS | 42 | $335.00 | $385.00 | $395.00 |
| 0034 | Flowable backfill, non- removable (213-09269) | CYS | 22 | $550.00 | $680.00 | $1,300.00 |
| 0035 | Geotextile for pavement, type 2A (214-12238) | SYS | 3,405 | $3.50 | $3.50 | $8.70 |
| 0036 | Geotextile for pavement, type 2B (214-12239) | SYS | 5,339 | $3.00 | $5.40 | $9.50 |
| 0037 | Compacted aggregate, no. 8 (301-12233) | CYS | 537 | $106.50 | $101.00 | $121.00 |
| 0038 | Compacted aggregate, no. 53 (301-12234) | CYS | 904 | $120.00 | $115.30 | $81.00 |
| 0039 | Subbase for PCCP (302-06464) | CYS | 316 | $172.50 | $200.25 | $113.00 |
| 0040 | Compacted aggregate, no. 53 (303-01180) | TON | 1,470 | $55.00 | $53.00 | $63.00 |
| 0041 | Widening with HMA, type D (304-07789) | TON | 447 | $210.00 | $162.00 | $182.15 |
| 0042 | HMA patching, full depth, type D (304-12627) | TON | 22 | $370.00 | $830.00 | $604.25 |
| 0043 | Rubblizing PCCP (305-97019) | SYS | 916 | $12.00 | $18.50 | $25.00 |
| 0044 | Milling, profile (306-11872) | SYS | 10,590 | $2.50 | $2.55 | $4.38 |
| 0045 | QC/QA-HMA, 4, 58E, surface, 9.5 MM (401-000009) | TON | 1,192 | $178.00 | $178.00 | $178.00 |
| 0046 | QC/QA-HMA, 4, 58E, intermediate, 19.0 MM (401-000045) | TON | 1,514 | $139.00 | $139.00 | $139.00 |
| 0047 | QC/QA-HMA, 4, 58S, base, 25.0 MM (401-000048) | TON | 2,300 | $108.50 | $108.50 | $108.50 |
| 0048 | Joint adhesive (401-11526) | LFT | 7,881 | $1.25 | $1.25 | $1.25 |
| 0049 | Void reducing asphalt membrane for HMA (401-12439) | LFT | 10,138 | $2.65 | $2.65 | $2.65 |
| 0050 | HMA for temporary pavement, type D (402-10087) | TON | 3,720 | $105.00 | $108.00 | $113.25 |
| 0051 | Asphalt for tack coat (406-05520) | TON | 20 | $500.00 | $500.00 | $500.00 |
| 0052 | Cracks in asphalt pavement, fill (408-12028) | TON | 6 | $2,500.00 | $2,500.00 | $1,500.00 |
| 0053 | Terminal joint, type HMA (503-12477) | LFT | 280 | $400.00 | $460.00 | $425.00 |
| 0054 | Guardrail, remove (601-02241) | LFT | 6,026 | $4.00 | $4.00 | $4.00 |
| 0055 | Guardrail, reset (601-06035) | LFT | 125 | $16.00 | $16.00 | $16.00 |
| 0056 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 1,762 | $25.00 | $25.00 | $25.00 |
| 0057 | Guardrail, MGS W-beam, 6 FT 3 in. spacing , temporary (601-12281) | LFT | 1,576 | $25.00 | $25.00 | $25.00 |
| 0058 | Guardrail, MGS W-beam, double faced, 6 FT 3 in. spacing (601-12284) | LFT | 1,413 | $35.00 | $35.00 | $35.00 |
| 0059 | Guardrail height transition, MGS (601-12289) | EACH | 3 | $1,025.00 | $1,025.00 | $1,025.00 |
| 0060 | Guardrail transition, MGS without curb (601-12292) | EACH | 15 | $3,800.00 | $3,800.00 | $3,800.00 |
| 0061 | Guardrail transition, MGS without curb , temporary (601-12292) | EACH | 6 | $3,800.00 | $3,800.00 | $3,800.00 |
| 0062 | Guardrail end treatment, type OS (601-94689) | EACH | 2 | $3,100.00 | $3,100.00 | $3,100.00 |
| 0063 | Guardrail end treatment, type OS , temporary (601-94689) | EACH | 6 | $3,100.00 | $3,100.00 | $3,100.00 |
| 0064 | Guardrail end treatment, type MS (601-94690) | EACH | 6 | $5,650.00 | $5,650.00 | $5,650.00 |
| 0065 | Barrier delineator (602-06729) | EACH | 224 | $12.00 | $24.50 | $30.00 |
| 0066 | Fence, farm field, 47 in. (603-06040) | LFT | 100 | $48.00 | $48.00 | $48.00 |
| 0067 | Milled HMA corrugations, conventional (606-12399) | LFT | 9,907 | $1.30 | $1.50 | $1.40 |
| 0068 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 1,136 | $220.00 | $233.00 | $345.00 |
| 0069 | Grout for riprap (616-02281) | CYS | 108 | $325.00 | $395.00 | $289.00 |
| 0070 | Riprap, class 1 (616-05688) | TON | 355 | $100.00 | $80.00 | $119.00 |
| 0071 | Riprap, revetment (616-06405) | TON | 1,168 | $85.00 | $79.00 | $97.00 |
| 0072 | Geotextile for riprap, type 1A (616-12246) | SYS | 130.90 | $7.00 | $8.20 | $14.00 |
| 0073 | Geotextile for riprap, type 2A (616-12248) | SYS | 1,136 | $6.25 | $5.50 | $7.50 |
| 0074 | Clean steel bridge, partial, QP-2, bridge no. 1 (619-11050) | LS | 1 | $89,000 | $89,000 | $89,000 |
| 0075 | Clean steel bridge, partial, QP-2, bridge no. 2 (619-11050) | LS | 1 | $89,000 | $89,000 | $89,000 |
| 0076 | Clean steel bridge, QP-2, bridge no. 3 (619-11052) | LS | 1 | $467,000 | $467,000 | $467,000 |
| 0077 | Clean steel bridge, QP-2, bridge no. 4 (619-11052) | LS | 1 | $467,000 | $467,000 | $467,000 |
| 0078 | Disposal of cleaning waste, hazardous, bridge no. 1 (619-12459) | LS | 1 | $1,000.00 | $1,000.00 | $1,000.00 |
| 0079 | Disposal of cleaning waste, hazardous, bridge no. 2 (619-12459) | LS | 1 | $1,000.00 | $1,000.00 | $1,000.00 |
| 0080 | Disposal of cleaning waste, hazardous, bridge no. 3 (619-12459) | LS | 1 | $20,000 | $20,000 | $20,000 |
| 0081 | Disposal of cleaning waste, hazardous, bridge no. 4 (619-12459) | LS | 1 | $20,000 | $20,000 | $20,000 |
| 0082 | Clean steel bridge, top flanges, type QP-2, bridge no. 1 (619-12506) | LS | 1 | $105,000 | $105,000 | $105,000 |
| 0083 | Clean steel bridge, top flanges, type QP-2, bridge no. 2 (619-12506) | LS | 1 | $105,000 | $105,000 | $105,000 |
| 0084 | Clean steel bridge, top flanges, type QP-2, bridge no. 3 (619-12506) | LS | 1 | $118,000 | $118,000 | $118,000 |
| 0085 | Clean steel bridge, top flanges, type QP-2, bridge no. 4 (619-12506) | LS | 1 | $118,000 | $118,000 | $118,000 |
| 0086 | Coat steel bridge, bridge no. 3 (619-51859) | LS | 1 | $180,000 | $180,000 | $180,000 |
| 0087 | Coat steel bridge, bridge no. 4 (619-51859) | LS | 1 | $180,000 | $180,000 | $180,000 |
| 0088 | Coat steel bridge, partial, bridge no. 1 (619-51860) | LS | 1 | $39,000 | $39,000 | $39,000 |
| 0089 | Coat steel bridge, partial, bridge no. 2 (619-51860) | LS | 1 | $39,000 | $39,000 | $39,000 |
| 0090 | Mobilization and demobilization for seeding (621-01004) | EACH | 14 | $1,150.00 | $1,150.00 | $1,150.00 |
| 0091 | Seed mixture, type R (621-06553) | LBS | 773.50 | $17.60 | $17.60 | $17.60 |
| 0092 | Mulching material (621-06565) | TON | 17.20 | $722.00 | $722.00 | $722.00 |
| 0093 | Water (621-06567) | KGAL | 18 | $2.00 | $2.00 | $2.00 |
| 0094 | Sodding (621-06574) | SYS | 3,387 | $10.00 | $6.25 | $6.25 |
| 0095 | Seed mixture, emergent wetland (621-06737) | LBS | 53 | $119.53 | $119.53 | $119.53 |
| 0096 | Seed mixture, floodplain (621-12612) | LBS | 252 | $117.78 | $117.78 | $117.78 |
| 0097 | Computer system equipment (628-11976) | EACH | 2 | $750.00 | $550.00 | $700.00 |
| 0098 | Field office, type D (628-12683) | MOS | 30 | $3,750.00 | $2,700.00 | $3,000.00 |
| 0099 | Topsoil processing and distribution (629-000149) | SYS | 21,249 | $6.00 | $3.90 | $6.49 |
| 0100 | Topsoil amendment budget (629-000150) | DOL | 42,496 | $1.00 | $1.00 | $1.00 |
| 0101 | Dynamic pile load test (701-06011) | EACH | 4 | $2,250.00 | $6,750.00 | $5,500.00 |
| 0102 | Test pile, dynamic, production (701-09557) | LFT | 210 | $100.00 | $75.00 | $275.00 |
| 0103 | Test pile, dynamic, restrike (701-09559) | EACH | 4 | $8,500.00 | $4,000.00 | $7,000.00 |
| 0104 | Automated pile driving data acquisition device (701-12836) | EACH | 1 | $1,500.00 | $12,000 | $6,500.00 |
| 0105 | Pile, steel H, HP 12 X 53 (701-51195) | LFT | 1,530 | $130.00 | $101.50 | $160.00 |
| 0106 | Grates, basins, and fittings, cast iron (702-12076) | EACH | 104 | $1,650.00 | $2,300.00 | $2,600.00 |
| 0107 | Concrete, C, substructure (702-92857) | CYS | 216.90 | $1,150.00 | $1,525.00 | $1,250.00 |
| 0108 | Reinforcing bars, epoxy coated (703-06029) | LBS | 1,845,330 | $1.60 | $1.80 | $1.80 |
| 0109 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 240 | $52.25 | $52.00 | $40.00 |
| 0110 | Inertial profiler, bridge encounter (704-000080) | LS | 1 | $15,000 | $44,700 | $45,000 |
| 0111 | Corrective grinding, bridge encounter (704-000082) | LS | 1 | $30,000 | $147,750 | $150,000 |
| 0112 | Concrete, C, superstructure (704-51002) | CYS | 4,580 | $1,325.00 | $1,875.00 | $1,590.00 |
| 0113 | Railing, concrete type FT (706-09959) | LFT | 8,196 | $60.00 | $59.50 | $51.00 |
| 0114 | Concrete bridge railing transition, type TFT (706-11621) | EACH | 24 | $1,580.00 | $2,600.00 | $2,600.00 |
| 0115 | Surface seal , bridge no. 1 (709-51821) | LS | 1 | $1.00 | $1.00 | $1.00 |
| 0116 | Surface seal , bridge no. 2 (709-51821) | LS | 1 | $1.00 | $1.00 | $1.00 |
| 0117 | Surface seal , bridge no. 3 (709-51821) | LS | 1 | $1.00 | $1.00 | $1.00 |
| 0118 | Surface seal , bridge no. 4 (709-51821) | LS | 1 | $1.00 | $1.00 | $1.00 |
| 0119 | Surface seal , bridge no. 5 (709-51821) | LS | 1 | $1.00 | $1.00 | $1.00 |
| 0120 | Surface seal , bridge no. 6 (709-51821) | LS | 1 | $1.00 | $1.00 | $1.00 |
| 0121 | Patching concrete structures (710-09158) | SFT | 40 | $150.00 | $110.00 | $257.00 |
| 0122 | Retrofit , steel core (711-01772) | EACH | 152 | $925.00 | $250.00 | $925.00 |
| 0123 | Drilled hole (711-51864) | EACH | 144 | $43.50 | $80.00 | $85.00 |
| 0124 | Jacking and supporting steel beams , bridge no. 1 (711-95291) | LS | 1 | $35,000 | $56,000 | $65,000 |
| 0125 | Jacking and supporting steel beams , bridge no. 2 (711-95291) | LS | 1 | $35,000 | $56,000 | $65,000 |
| 0126 | Jacking and supporting steel beams , bridge no. 3 (711-95291) | LS | 1 | $35,000 | $56,000 | $65,000 |
| 0127 | Jacking and supporting steel beams , bridge no. 4 (711-95291) | LS | 1 | $35,000 | $56,000 | $65,000 |
| 0128 | Stud shear connectors (711-96800) | EACH | 56,112 | $4.57 | $5.65 | $4.95 |
| 0129 | Pipe, underdrain outlet, diameter 6 in. (715-05053) | LFT | 893 | $20.50 | $24.90 | $26.00 |
| 0130 | Pipe, type 2, circular, diameter 12 in. (715-05149) | LFT | 96 | $70.00 | $70.80 | $87.00 |
| 0131 | Pipe, type 2, circular, diameter 15 in. (715-05151) | LFT | 94 | $72.50 | $90.30 | $88.00 |
| 0132 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 380 | $22.50 | $22.70 | $23.00 |
| 0133 | Video inspection for pipe (715-09064) | LFT | 190 | $21.10 | $3.00 | $23.00 |
| 0134 | Pipe, roadway drain casting extension (715-10238) | EACH | 104 | $950.00 | $800.00 | $650.00 |
| 0135 | Pipe end section, diameter 12 in. (715-46000) | EACH | 4 | $1,000.00 | $600.00 | $640.00 |
| 0136 | Pipe end section, diameter 15 in. (715-46005) | EACH | 2 | $1,050.00 | $800.00 | $827.00 |
| 0137 | Pipe end section, diameter 18 in. (715-46010) | EACH | 1 | $1,500.00 | $850.00 | $868.00 |
| 0138 | Pipe installation, trenchless, 12 in. (716-07630) | LFT | 305 | $300.00 | $495.00 | $1,329.57 |
| 0139 | Pipe installation, trenchless, 15 in. (716-07631) | LFT | 129 | $365.00 | $610.00 | $1,563.37 |
| 0140 | Pipe installation, trenchless, 18 in. (716-07632) | LFT | 92 | $535.00 | $650.00 | $1,636.98 |
| 0141 | Outlet protector, type 1 (718-06528) | EACH | 9 | $1,150.00 | $1,600.00 | $2,380.00 |
| 0142 | Video inspection for underdrain (718-06532) | LFT | 240 | $16.70 | $3.00 | $4.25 |
| 0143 | Geotextile for underdrains, type 1A (718-12305) | SYS | 392 | $2.50 | $7.00 | $8.00 |
| 0144 | Pipe, plug existing (720-02442) | EACH | 20 | $650.00 | $575.00 | $580.00 |
| 0145 | Inlet, type N12, modified (720-45066) | EACH | 10 | $5,100.00 | $8,600.00 | $11,765 |
| 0146 | Manhole, type C4 (720-45410) | EACH | 6 | $4,600.00 | $6,000.00 | $5,315.00 |
| 0147 | Longitudinal grooving (722-12732) | SYS | 16,504 | $3.00 | $6.75 | $5.00 |
| 0148 | Bridge expansion joint, type SS (724-12771) | LFT | 74 | $225.00 | $535.00 | $625.00 |
| 0149 | Bridge expansion joint, type M (724-12772) | LFT | 148 | $3,100.00 | $2,680.00 | $3,050.00 |
| 0150 | Bearing assembly, elastomeric (726-92406) | EACH | 24 | $3,500.00 | $3,200.00 | $3,500.00 |
| 0151 | Bearing assembly, ptfe (726-95870) | EACH | 24 | $3,700.00 | $4,100.00 | $3,800.00 |
| 0152 | Road closure sign assembly (801-04308) | EACH | 5 | $195.00 | $195.00 | $195.00 |
| 0153 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 155,727 | $1.93 | $1.93 | $1.93 |
| 0154 | Temporary pavement marking, removable, 8 in. (801-06469) | LFT | 7,444 | $2.60 | $2.60 | $2.60 |
| 0155 | Detour route marker assembly (801-06625) | EACH | 29 | $98.00 | $98.00 | $98.00 |
| 0156 | Construction sign, type A (801-06640) | EACH | 103 | $165.00 | $165.00 | $165.00 |
| 0157 | Construction sign, type B (801-06645) | EACH | 18 | $98.00 | $98.00 | $98.00 |
| 0158 | Flashing arrow sign (801-06710) | DAY | 750 | $8.00 | $8.00 | $8.00 |
| 0159 | Maintaining traffic (801-06775) | LS | 1 | $215,000 | $141,271 | $88,905 |
| 0160 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 7 | $3,500.00 | $7,650.00 | $9,835.71 |
| 0161 | Barricade, type III-A (801-07118) | LFT | 72 | $12.00 | $12.00 | $12.00 |
| 0162 | Barricade, type III-B (801-07119) | LFT | 156 | $12.00 | $12.00 | $12.00 |
| 0163 | Temporary crossover drainage pipe (801-07606) | LFT | 1,548 | $62.50 | $54.50 | $92.50 |
| 0164 | Temporary traffic barrier, type 1 (801-08400) | LFT | 8,751 | $30.00 | $49.40 | $47.23 |
| 0165 | Temporary traffic barrier, type 2 (801-08401) | LFT | 5,787 | $32.50 | $46.00 | $32.89 |
| 0166 | Portable changeable message sign (801-11642) | EACH | 4 | $4,350.00 | $8,500.00 | $8,500.00 |
| 0167 | Truck mounted attenuator (801-12042) | DAY | 60 | $350.00 | $500.00 | $236.29 |
| 0168 | Law enforcement officer (801-12324) | HRS | 240 | $75.00 | $75.00 | $75.00 |
| 0169 | Temporary pavement marking, removable, 7 in. (801-12390) | LFT | 60,630 | $2.60 | $2.60 | $2.60 |
| 0170 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 16 | $495.00 | $495.00 | $495.00 |
| 0171 | Temporary worksite speed limit sign assembly, intermittent (801-12930) | EACH | 8 | $495.00 | $495.00 | $495.00 |
| 0172 | Temporary pavement marking, removable, 10 in. (801-12956) | LFT | 5,250 | $3.25 | $3.25 | $3.25 |
| 0173 | Temporary crossover, type B (801-52817) | EACH | 2 | $150,000 | $80,700 | $29,600 |
| 0174 | Reference post (802-04893) | EACH | 6 | $425.00 | $425.00 | $425.00 |
| 0175 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 48 | $32.00 | $32.00 | $32.00 |
| 0176 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 20 | $42.00 | $42.00 | $42.00 |
| 0177 | Sign, ground mounted, reset (802-91122) | EACH | 2 | $250.00 | $250.00 | $250.00 |
| 0178 | Retro-reflectivity testing (808-09381) | LS | 1 | $4,000.00 | $4,000.00 | $4,000.00 |
| 0179 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 7,761 | $0.98 | $0.98 | $0.98 |
| 0180 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 7,761 | $0.98 | $0.98 | $0.98 |
| 0181 | Line, multi-component, broken, white, 6 in. (808-10071) | LFT | 1,943 | $1.25 | $1.25 | $1.25 |
| 0182 | Grooving for pavement markings (808-12032) | LFT | 7,713 | $0.45 | $0.45 | $0.45 |
| 0183 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 23 | $24.95 | $24.95 | $24.95 |
| 0184 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 18 | $24.95 | $24.95 | $24.95 |
| 0185 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 94 | $17.50 | $18.20 | $8.60 |
| 0186 | Snowplowable raised pavement marker (808-75998) | EACH | 70 | $85.00 | $85.00 | $85.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of September 2, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.