INDOT contract B-44999-A bid tabulation
BRIDGE REPLACEMENT. Let by Indiana DOT on March 12, 2025, Marion, Greenfield. 3 bids received; low bid $6,104,093 by Rieth-Riley Construction Co., Inc..
- Owner
- Indiana DOT
- Letting
- 12 MAR 2025
- Pay items
- 143
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rieth-Riley Construction Co., Inc. | $6,104,093 | Low |
| 2 | Milestone Contractors LP | $6,697,000 | +10% |
| 3 | Superior Construction Co Inc | $7,686,742 | +26% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rieth-Riley Construction Co., Inc. | 2. Milestone Contractors LP | 3. Superior Construction Co Inc |
|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $23,901 | $41,520 | $200,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, pavement traffic markings (109-09377) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0010 | Special maintenance , pothole patching (109-12573) | DOL | 10,000 | $1.00 | $1.00 | $1.00 |
| 0011 | Mobilization and demobilization (110-01001) | LS | 1 | $287,570 | $332,369 | $384,000 |
| 0012 | Clearing right-of-way (201-52370) | LS | 1 | $23,400 | $67,000 | $75,000 |
| 0013 | Pavement removal (202-02240) | SYS | 144 | $20.00 | $88.52 | $15.00 |
| 0014 | Curb and gutter, remove (202-02279) | LFT | 1,727 | $8.36 | $16.57 | $7.99 |
| 0015 | Present structure, remove, structure no. 1 (202-51330) | LS | 1 | $399,441 | $249,512 | $1,077,842 |
| 0016 | Overhead sign structure, cantilever, remove (202-74080) | EACH | 2 | $4,832.09 | $4,260.00 | $4,261.00 |
| 0017 | Bridge bracket assembly, remove (202-74095) | EACH | 2 | $473.00 | $473.00 | $473.00 |
| 0018 | Inlet, remove (202-91385) | EACH | 4 | $758.58 | $649.43 | $800.00 |
| 0019 | Guardrail end treatment, remove (202-93741) | EACH | 4 | $160.00 | $160.00 | $160.00 |
| 0020 | Barrier wall, concrete, remove (202-94954) | LFT | 105 | $40.00 | $248.04 | $100.00 |
| 0021 | Fence right-of-way, remove (202-96531) | LFT | 244 | $6.00 | $6.00 | $6.00 |
| 0022 | Excavation, common (203-02000) | CYS | 9,025 | $38.95 | $35.00 | $34.00 |
| 0023 | Stormwater management budget (205-12108) | DOL | 56,630 | $1.00 | $1.00 | $1.00 |
| 0024 | Stormwater management implementation (205-12616) | LS | 1 | $5,669.83 | $12,502 | $13,000 |
| 0025 | SWQCP preparation (205-12618) | LS | 1 | $11,290 | $3,500.00 | $2,250.00 |
| 0026 | Excavation, foundation, unclassified (206-51230) | CYS | 151 | $176.44 | $67.75 | $110.00 |
| 0027 | Subgrade treatment, type IC (207-09935) | SYS | 4,206 | $33.70 | $27.71 | $36.00 |
| 0028 | B borrow (211-02050) | CYS | 3,752 | $74.12 | $102.00 | $120.00 |
| 0029 | Structure backfill, type 2 (211-09265) | CYS | 252 | $59.13 | $126.63 | $100.00 |
| 0030 | Structure backfill, type 3 (211-09266) | CYS | 2,791 | $70.16 | $102.00 | $120.00 |
| 0031 | Structure backfill, type 5 (211-09268) | CYS | 5 | $173.41 | $310.41 | $200.00 |
| 0033 | Geotextile for pavement, type 2B (214-12239) | SYS | 4,206 | $3.37 | $5.30 | $4.50 |
| 0034 | Compacted aggregate, no. 8 (301-12233) | CYS | 1,365 | $77.50 | $114.01 | $75.00 |
| 0035 | Compacted aggregate, no. 53 (301-12234) | CYS | 42 | $86.34 | $202.26 | $140.00 |
| 0036 | Subbase for PCCP (302-06464) | CYS | 46 | $132.85 | $260.75 | $108.00 |
| 0037 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 211 | $130.44 | $150.00 | $145.00 |
| 0038 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 351 | $109.53 | $115.00 | $122.00 |
| 0039 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 1,231 | $85.17 | $115.00 | $102.00 |
| 0040 | Joint adhesive, surface (401-10258) | LFT | 957 | $0.30 | $1.50 | $1.00 |
| 0041 | Joint adhesive, intermediate (401-10259) | LFT | 957 | $0.35 | $1.50 | $1.00 |
| 0042 | HMA for temporary pavement, type D (402-10087) | TON | 318 | $156.20 | $150.00 | $175.00 |
| 0043 | Asphalt for tack coat (406-05520) | TON | 3 | $0.01 | $565.00 | $0.01 |
| 0044 | Terminal joint, type HMA (503-12477) | LFT | 90 | $175.17 | $550.06 | $380.00 |
| 0045 | Guardrail, remove (601-02241) | LFT | 1,641 | $2.00 | $2.00 | $2.00 |
| 0046 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 125 | $18.00 | $18.00 | $18.00 |
| 0047 | Guardrail height transition, MGS (601-12289) | EACH | 3 | $875.00 | $875.00 | $875.00 |
| 0048 | Guardrail transition, MGS with curb (601-12291) | EACH | 1 | $3,150.00 | $3,150.00 | $3,150.00 |
| 0049 | Guardrail, MGS W-beam, cable terminal anchor (601-12294) | EACH | 1 | $1,300.00 | $1,300.00 | $1,300.00 |
| 0050 | Guardrail end treatment, type OS (601-94689) | EACH | 1 | $2,800.00 | $2,800.00 | $2,800.00 |
| 0051 | Concrete barrier (602-01064) | LFT | 45 | $408.29 | $425.46 | $700.00 |
| 0052 | Barrier delineator (602-06729) | EACH | 9 | $25.45 | $22.00 | $22.51 |
| 0053 | Concrete barrier, modified section (602-11938) | CYS | 8 | $1,987.30 | $1,552.74 | $1,200.00 |
| 0054 | Fence, chain link, 48 in. (603-06045) | LFT | 225 | $37.00 | $37.00 | $37.00 |
| 0055 | Handrail, pedestrian (604-95344) | LFT | 315 | $212.00 | $212.00 | $212.00 |
| 0056 | Curb and gutter, concrete (605-06140) | LFT | 917 | $30.59 | $35.23 | $34.00 |
| 0057 | Curb and gutter, concrete, type C (605-06150) | LFT | 907 | $32.15 | $42.36 | $36.00 |
| 0058 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 218 | $184.16 | $231.52 | $163.00 |
| 0059 | Riprap, class 1 (616-05688) | TON | 17 | $141.58 | $204.60 | $140.00 |
| 0060 | Riprap, revetment (616-06405) | TON | 3,078 | $72.84 | $85.00 | $60.00 |
| 0061 | Geotextile for riprap, type 1A (616-12246) | SYS | 176 | $5.68 | $6.15 | $7.00 |
| 0062 | Geotextile for riprap, type 2A (616-12248) | SYS | 7,352 | $4.35 | $4.89 | $4.00 |
| 0063 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $400.00 | $500.00 | $400.00 |
| 0064 | Fertilizer , for permanent seeding (621-06545) | TON | 4 | $900.00 | $800.00 | $900.00 |
| 0065 | Seed mixture, type U (621-06554) | LBS | 350 | $8.10 | $9.00 | $8.10 |
| 0066 | Mulching material (621-06565) | TON | 4 | $630.00 | $510.00 | $630.00 |
| 0067 | Sodding (621-06574) | SYS | 197 | $11.85 | $10.00 | $11.85 |
| 0068 | Field office, type C (628-09403) | MOS | 18 | $4,670.86 | $2,800.00 | $2,700.00 |
| 0069 | Plant growth layer (629-12029) | SYS | 8,610 | $7.70 | $2.50 | $7.50 |
| 0070 | Dynamic pile load test (701-06011) | EACH | 3 | $4,430.81 | $4,997.65 | $3,300.00 |
| 0071 | Pile, sleeves , MSE (701-08253) | EACH | 12 | $1,909.23 | $1,809.92 | $1,200.00 |
| 0072 | Test pile, dynamic, production (701-09557) | LFT | 225 | $52.86 | $53.50 | $125.00 |
| 0073 | Test pile, dynamic, restrike (701-09559) | EACH | 3 | $1,882.04 | $3,000.00 | $2,200.00 |
| 0074 | Pile shoe, HP 12 X 74 (701-09683) | EACH | 34 | $164.54 | $188.98 | $146.00 |
| 0075 | Pile, steel H, HP 12 X 74 (701-95780) | LFT | 1,855 | $82.80 | $86.00 | $77.00 |
| 0076 | Temporary shoring (702-04325) | LS | 1 | $1.00 | $19,451 | $50,000 |
| 0077 | Concrete, A, substructure (702-51005) | CYS | 111.20 | $1,025.69 | $800.00 | $1,050.00 |
| 0078 | Concrete, B, footings (702-51015) | CYS | 57.90 | $629.36 | $700.00 | $750.00 |
| 0079 | Concrete, C, substructure (702-92857) | CYS | 45.70 | $1,394.21 | $1,300.00 | $1,500.00 |
| 0080 | Reinforcing bars (703-06028) | LBS | 23,542 | $1.28 | $1.50 | $1.20 |
| 0081 | Reinforcing bars, epoxy coated (703-06029) | LBS | 141,675 | $1.28 | $1.50 | $1.30 |
| 0082 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 50 | $55.15 | $51.37 | $50.00 |
| 0083 | Concrete, C, superstructure (704-51002) | CYS | 480.50 | $860.36 | $880.00 | $900.00 |
| 0084 | Concrete bridge railing transition, type TPF-1 (706-06351) | EACH | 2 | $3,184.06 | $9,000.00 | $9,000.00 |
| 0085 | Concrete bridge railing transition, type TPS-1 (706-06353) | EACH | 2 | $3,184.06 | $9,000.00 | $9,500.00 |
| 0086 | Railing, steel type PF-1 (706-11404) | LFT | 234 | $75.00 | $75.00 | $75.00 |
| 0087 | Railing, steel type PS-1 (706-11418) | LFT | 234 | $75.00 | $75.00 | $75.00 |
| 0088 | Railing, concrete type PF-1 (706-11602) | CYS | 13.90 | $2,840.18 | $1,843.88 | $2,000.00 |
| 0089 | Railing, concrete type PS-1 (706-11604) | CYS | 21.60 | $2,580.24 | $1,283.97 | $1,800.00 |
| 0090 | Structural member, concrete, bulb-T beam, 48 in. X 49 in. (707-09634) | LFT | 1,120 | $616.10 | $745.00 | $700.00 |
| 0091 | Surface seal (709-51821) | LS | 1 | $1.06 | $3,500.00 | $11,500 |
| 0092 | Pipe, type 4, circular, diameter 6 in. (715-05048) | LFT | 558 | $3.66 | $24.97 | $26.00 |
| 0093 | Pipe, underdrain outlet, diameter 6 in. (715-05053) | LFT | 32 | $54.05 | $50.00 | $90.00 |
| 0094 | Pipe, type 1, circular, diameter 6 in. (715-05115) | LFT | 35 | $39.95 | $46.19 | $68.00 |
| 0095 | Pipe, type 1, circular, diameter 15 in. (715-05119) | LFT | 27 | $82.23 | $72.76 | $120.00 |
| 0096 | Pipe, type 2, circular, diameter 12 in. (715-05149) | LFT | 522 | $68.25 | $100.50 | $75.00 |
| 0097 | Pipe, type 2, circular, diameter 15 in. (715-05151) | LFT | 66 | $73.55 | $183.70 | $100.00 |
| 0098 | Video inspection for pipe (715-09064) | LFT | 650 | $3.85 | $3.00 | $3.00 |
| 0099 | Pipe end section, diameter 12 in. (715-46000) | EACH | 3 | $796.18 | $1,029.21 | $1,050.00 |
| 0100 | Pipe end section, diameter 15 in. (715-46005) | EACH | 1 | $828.05 | $1,111.66 | $1,100.00 |
| 0101 | Outlet protector, type 1 (718-06528) | EACH | 4 | $1,243.76 | $1,800.63 | $2,584.04 |
| 0102 | Outlet protector, type 3 (718-06531) | EACH | 2 | $1,331.16 | $1,518.06 | $2,195.03 |
| 0103 | Underdrain, patching (718-08308) | LFT | 340 | $31.56 | $28.78 | $41.65 |
| 0104 | Geotextile for underdrains, type 2B (718-12308) | SYS | 434 | $3.88 | $1.94 | $11.42 |
| 0105 | Aggregate for underdrains (718-52610) | CYS | 43 | $62.80 | $104.76 | $75.35 |
| 0106 | Manhole, type C15 (720-03757) | EACH | 1 | $4,855.73 | $4,554.05 | $3,500.00 |
| 0107 | Inlet, type B15, modified (720-93409) | EACH | 1 | $4,149.87 | $4,009.26 | $3,500.00 |
| 0108 | Inlet, type C15, modified (720-93411) | EACH | 4 | $4,340.42 | $3,836.48 | $3,500.00 |
| 0109 | Inlet, type B15 (720-98174) | EACH | 4 | $3,373.86 | $3,811.40 | $4,200.00 |
| 0110 | Inlet, type C15 (720-98555) | EACH | 2 | $5,985.83 | $3,815.56 | $4,200.00 |
| 0111 | Longitudinal grooving (722-12732) | SYS | 960 | $3.74 | $3.39 | $3.49 |
| 0112 | Bearing assembly, elastomeric (726-92406) | EACH | 10 | $1,712.46 | $1,953.83 | $2,000.00 |
| 0113 | Face panels, concrete (731-93945) | SFT | 9,460 | $46.58 | $60.26 | $43.63 |
| 0114 | Wall erection (731-93946) | SFT | 9,460 | $27.28 | $20.00 | $22.37 |
| 0115 | Leveling pad, concrete (731-93947) | LFT | 558 | $54.73 | $88.37 | $55.00 |
| 0116 | Construction sign, type C (801-03290) | EACH | 2 | $245.00 | $392.00 | $245.00 |
| 0117 | Road closure sign assembly (801-04308) | EACH | 5 | $295.00 | $372.00 | $295.00 |
| 0118 | Temporary pavement marking, 4 in. (801-06203) | LFT | 5,640 | $0.25 | $0.66 | $0.25 |
| 0119 | Temporary pavement marking, 5 in. (801-06204) | LFT | 718 | $0.28 | $1.54 | $0.28 |
| 0120 | Temporary pavement marking, removable, 8 in. (801-06469) | LFT | 2,720 | $3.95 | $4.79 | $3.95 |
| 0121 | Detour route marker assembly (801-06625) | EACH | 30 | $98.00 | $217.00 | $98.00 |
| 0122 | Construction sign, type A (801-06640) | EACH | 54 | $165.00 | $296.00 | $165.00 |
| 0123 | Construction sign, type B (801-06645) | EACH | 4 | $89.00 | $99.00 | $89.00 |
| 0124 | Temporary raised pavement marker, grade 1 (801-06649) | EACH | 332 | $7.95 | $31.00 | $7.95 |
| 0125 | Maintaining traffic (801-06775) | LS | 1 | $195,925 | $175,000 | $400,000 |
| 0126 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 4 | $6,050.00 | $6,050.00 | $6,050.00 |
| 0127 | Barricade, type III-A (801-07118) | LFT | 48 | $14.00 | $17.00 | $14.00 |
| 0128 | Barricade, type III-B (801-07119) | LFT | 36 | $14.00 | $20.00 | $14.00 |
| 0129 | Temporary traffic barrier, type 2 (801-08401) | LFT | 2,280 | $32.77 | $40.54 | $21.00 |
| 0130 | Law enforcement officer (801-12324) | HRS | 100 | $60.00 | $60.00 | $60.00 |
| 0131 | Sign post, timber, 6 in. X 8 in. (802-01946) | LFT | 126 | $94.10 | $94.10 | $94.20 |
| 0132 | Sign post, timber, 6 in. X 6 in. (802-03776) | LFT | 66 | $84.90 | $84.90 | $84.90 |
| 0133 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 51 | $36.50 | $36.50 | $36.50 |
| 0134 | Sign, panel, with legend (802-07057) | SFT | 320 | $61.40 | $61.40 | $61.40 |
| 0135 | Sign, sheet, and supports, remove (802-07059) | EACH | 9 | $186.00 | $186.00 | $186.00 |
| 0136 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 24 | $38.50 | $38.50 | $38.50 |
| 0137 | Sign, overhead, remove (802-74050) | EACH | 4 | $1,484.00 | $1,484.00 | $1,484.00 |
| 0138 | Delineator post (804-06770) | EACH | 4 | $70.00 | $260.00 | $85.00 |
| 0139 | Line, remove (808-06716) | LFT | 6,988 | $0.65 | $0.59 | $0.65 |
| 0140 | Retro-reflectivity testing (808-09381) | LS | 1 | $3,500.00 | $5,960.00 | $3,500.00 |
| 0141 | Line, preformed plastic, solid, white, 6 in. (808-75052) | LFT | 5,221 | $5.95 | $5.99 | $5.95 |
| 0142 | Line, preformed plastic, broken, white, 6 in. (808-75055) | LFT | 1,438 | $6.14 | $7.33 | $6.15 |
| 0143 | Line, preformed plastic, solid, yellow, 6 in. (808-75057) | LFT | 5,221 | $5.95 | $5.99 | $5.95 |
| 0144 | Grooving for pavement markings (808-12032) | LFT | 10,812 | $0.44 | $1.03 | $0.44 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of March 12, 2025. Compiled by Mirage Metrics.