INDOT contract R-42257-A bid tabulation
CONCRETE PVMT RESTORATION, AUXIL LANES AND TRAFFIC SIGNALS. Let by Indiana DOT on August 6, 2025, Hendricks, Crawfordsville. 4 bids received; low bid $8,239,518 by E & B Paving LLC.
- Owner
- Indiana DOT
- Letting
- 06 AUG 2025
- Pay items
- 121
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | E & B Paving LLC | $8,239,518 | Low |
| 2 | Rieth-Riley Construction Co., Inc. | $8,917,413 | +8.0% |
| 3 | Calumet Civil Contractors Inc | $9,381,000 | +14% |
| 4 | Milestone Contractors LP | $9,877,000 | +20% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E & B Paving LLC | 2. Rieth-Riley Construction Co., Inc. | 3. Calumet Civil Contractors Inc | 4. Milestone Contractors LP |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $45,250 | $37,540 | $54,900 | $88,288 |
| 0002 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 6 | $360.00 | $1,233.05 | $150.00 | $1,300.00 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, PCCP (109-08441) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Quality adjustments, pavement traffic markings (109-09377) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0011 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0012 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0013 | Mobilization and demobilization (110-01001) | LS | 1 | $350,000 | $197,000 | $408,943 | $482,000 |
| 0014 | Clearing and grubbing (201-06587) | ACRE | 0.60 | $115,000 | $50,250 | $45,000 | $50,000 |
| 0015 | Clearing right-of-way (201-52370) | LS | 1 | $180,000 | $80,486 | $70,000 | $291,500 |
| 0016 | Pavement removal (202-02240) | SYS | 409 | $20.70 | $31.99 | $19.00 | $50.00 |
| 0017 | Paved side ditch, remove (202-02272) | LFT | 2,573 | $14.00 | $44.06 | $9.00 | $30.00 |
| 0018 | Catch basin, remove (202-02928) | EACH | 3 | $960.00 | $865.33 | $500.00 | $750.00 |
| 0019 | Detector housing, remove (202-90277) | EACH | 14 | $300.00 | $300.00 | $300.00 | $300.00 |
| 0020 | Pipe, remove (202-96133) | LFT | 188 | $20.50 | $46.15 | $25.00 | $50.00 |
| 0021 | Pipe end section, remove (202-98488) | EACH | 15 | $731.00 | $544.43 | $600.00 | $650.00 |
| 0022 | Excavation, common (203-02000) | CYS | 1,745 | $41.00 | $62.43 | $50.00 | $35.00 |
| 0023 | Linear grading (203-08607) | LFT | 28,907 | $1.25 | $2.78 | $3.75 | $6.00 |
| 0024 | Linear grading , guardrail (203-08607) | LFT | 3,540 | $6.50 | $12.63 | $6.25 | $12.00 |
| 0025 | Pump around (205-11626) | EACH | 3 | $13,200 | $547.86 | $5,000.00 | $3,000.00 |
| 0026 | Stormwater management budget (205-12108) | DOL | 260,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0027 | Stormwater management implementation (205-12616) | LS | 1 | $50,723 | $55,901 | $80,000 | $60,000 |
| 0028 | SWQCP preparation (205-12618) | LS | 1 | $2,500.00 | $43,250 | $5,000.00 | $6,500.00 |
| 0029 | Subgrade treatment, type IC (207-09935) | SYS | 11,387 | $27.00 | $52.51 | $34.00 | $42.00 |
| 0030 | Structure backfill, type 1 (211-09264) | CYS | 55 | $30.00 | $51.07 | $65.00 | $100.00 |
| 0031 | Flowable backfill, non- removable (213-09269) | CYS | 20 | $222.00 | $253.26 | $215.00 | $1,200.00 |
| 0032 | Geogrid, type IB (214-11796) | SYS | 1,139 | $3.50 | $1.69 | $3.75 | $2.00 |
| 0033 | Subbase for PCCP (302-06464) | CYS | 190 | $80.00 | $113.43 | $127.00 | $90.00 |
| 0034 | Compacted aggregate, no. 53 (303-01180) | TON | 3,486 | $43.50 | $44.22 | $50.00 | $40.00 |
| 0035 | HMA patching, full depth, type C (304-12625) | TON | 2,475 | $135.00 | $162.13 | $140.00 | $150.00 |
| 0036 | Milling, asphalt, 4 in. (306-08038) | SYS | 100,333 | $2.30 | $4.16 | $4.25 | $5.00 |
| 0037 | Milling, approach (306-08432) | SYS | 10,566 | $3.50 | $3.71 | $4.25 | $4.75 |
| 0038 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 8,737 | $109.00 | $114.23 | $133.00 | $107.00 |
| 0039 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 15,075 | $86.00 | $98.04 | $107.00 | $80.00 |
| 0040 | QC/QA-HMA, 3, 58S, base, 19.0 MM (401-000053) | TON | 1,795 | $102.00 | $103.70 | $100.00 | $120.00 |
| 0041 | Asphalt for tack coat (406-05520) | TON | 39 | $0.01 | $0.01 | $100.00 | $540.00 |
| 0042 | PCCP, 10 in. (502-06327) | SYS | 409 | $85.00 | $118.33 | $110.00 | $55.00 |
| 0043 | Retrofitted tie bars (503-03489) | EACH | 2 | $5.00 | $16.38 | $25.00 | $24.88 |
| 0044 | D-1 contraction joint (503-05240) | LFT | 12 | $30.00 | $16.56 | $20.00 | $60.00 |
| 0045 | PCCP patching, full depth (506-06333) | SYS | 734 | $185.00 | $221.47 | $150.00 | $450.00 |
| 0046 | Cracks in PCCP, rout and seal (507-07482) | LFT | 39 | $3.00 | $5.00 | $50.00 | $6.00 |
| 0047 | Joints in PCCP, saw and seal (507-08272) | LFT | 63 | $3.00 | $3.00 | $50.00 | $5.00 |
| 0048 | Joint repair, partial depth (509-12191) | SFT | 3,532 | $82.00 | $50.58 | $125.00 | $115.00 |
| 0049 | Joint repair, bottom-half (509-12192) | SFT | 296 | $150.00 | $51.33 | $235.00 | $215.00 |
| 0050 | Fence, farm field, reset (603-06060) | LFT | 1,229 | $24.00 | $17.00 | $17.00 | $17.00 |
| 0051 | Center curb, concrete, type C (605-06210) | LFT | 378 | $90.00 | $77.44 | $135.00 | $120.00 |
| 0052 | Milled HMA corrugations, conventional (606-12399) | LFT | 125,484 | $0.55 | $0.54 | $0.37 | $0.50 |
| 0053 | Paved side ditch, type G , clean (607-06365) | LFT | 6,593 | $8.50 | $24.02 | $40.00 | $25.00 |
| 0054 | HMA for approaches, type B (610-07487) | TON | 872 | $150.00 | $159.01 | $150.00 | $150.00 |
| 0055 | Riprap, class 1 (616-05688) | TON | 22 | $65.00 | $121.49 | $100.00 | $105.00 |
| 0056 | Riprap, revetment (616-06405) | TON | 2,398 | $74.11 | $73.17 | $78.00 | $95.00 |
| 0057 | Geotextile for riprap, type 1A (616-12246) | SYS | 4,220 | $4.00 | $2.87 | $3.75 | $1.50 |
| 0058 | Sign, 'DO not disturb' (622-98200) | EACH | 102 | $110.00 | $84.00 | $115.00 | $115.00 |
| 0059 | Computer system equipment (628-11976) | EACH | 2 | $1,500.00 | $1,055.09 | $1,500.00 | $1,500.00 |
| 0060 | Field office, type D (628-12683) | MOS | 24 | $3,841.67 | $3,587.31 | $4,800.00 | $5,000.00 |
| 0061 | Clean existing pipe (715-01354) | LFT | 949 | $12.50 | $22.02 | $9.00 | $15.00 |
| 0062 | Pipe, type 4, circular, diameter 6 in. (715-05048) | LFT | 2,920 | $14.25 | $14.25 | $18.00 | $26.00 |
| 0063 | Pipe, type 1, circular, diameter 15 in. (715-05119) | LFT | 153 | $93.00 | $82.70 | $110.00 | $169.00 |
| 0064 | Pipe, type 1, circular, diameter 18 in. (715-05121) | LFT | 152 | $118.00 | $90.55 | $135.00 | $170.00 |
| 0065 | Pipe end section, diameter 12 in. (715-46000) | EACH | 11 | $1,800.00 | $1,178.24 | $1,500.00 | $1,200.00 |
| 0066 | Pipe end section, diameter 15 in. (715-46005) | EACH | 3 | $1,925.00 | $1,245.45 | $1,550.00 | $1,300.00 |
| 0067 | Pipe end section, diameter 18 in. (715-46010) | EACH | 2 | $2,400.00 | $1,431.12 | $1,600.00 | $1,400.00 |
| 0068 | Video inspection for underdrain (718-06532) | LFT | 2,920 | $2.50 | $1.15 | $1.30 | $1.25 |
| 0069 | Geotextile for underdrains, type 1A (718-12305) | SYS | 2,001 | $2.00 | $2.00 | $1.00 | $1.00 |
| 0070 | Aggregate for underdrains (718-52610) | CYS | 316 | $82.00 | $82.00 | $100.00 | $80.00 |
| 0071 | Inlet, type N12 (720-45065) | EACH | 5 | $4,100.00 | $4,124.24 | $8,000.00 | $7,500.00 |
| 0072 | Catch basin, clean existing (720-99315) | EACH | 5 | $300.00 | $696.56 | $200.00 | $400.00 |
| 0073 | Pipe liner, cured-in- place, min. area 6.5 SFT (725-11294) | LFT | 182 | $714.11 | $877.88 | $735.00 | $815.00 |
| 0074 | Temporary pavement marking, removable, 4 in. (801-06207) | LFT | 73,940 | $1.30 | $1.30 | $0.50 | $1.00 |
| 0075 | Construction sign, type A (801-06640) | EACH | 29 | $175.00 | $175.00 | $283.00 | $175.00 |
| 0076 | Construction sign, type B (801-06645) | EACH | 2 | $100.00 | $100.00 | $95.00 | $100.00 |
| 0077 | Flashing arrow sign (801-06710) | DAY | 365 | $7.00 | $7.00 | $17.00 | $7.00 |
| 0078 | Maintaining traffic (801-06775) | LS | 1 | $230,000 | $232,570 | $196,000 | $396,000 |
| 0079 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 1 | $12,000 | $15,000 | $10,000 | $20,000 |
| 0080 | Temporary traffic barrier, type 2 (801-08401) | LFT | 556 | $79.00 | $42.63 | $80.00 | $160.00 |
| 0081 | Temporary speed feedback assembly (801-12832) | EACH | 2 | $3,013.00 | $3,013.00 | $4,875.00 | $3,013.00 |
| 0082 | Temporary worksite speed limit sign assembly, intermittent (801-12930) | EACH | 4 | $3,000.00 | $3,000.00 | $3,210.00 | $3,000.00 |
| 0083 | Miscellaneous equipment for traffic signals (805-01579) | LS | 1 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 |
| 0084 | Signal pole foundation, 36 in. X 144 in. (805-01815) | EACH | 4 | $5,500.00 | $5,500.00 | $5,500.00 | $5,500.00 |
| 0085 | Transportation of salvageable signal equipment (805-02087) | LS | 1 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 |
| 0086 | Controller and cabinet, type P1 (805-02445) | EACH | 1 | $21,000 | $21,000 | $21,000 | $21,000 |
| 0087 | Radio, interconnect (805-08464) | EACH | 5 | $2,400.00 | $2,400.00 | $2,400.00 | $2,400.00 |
| 0088 | Radio, interconnection system testing (805-08493) | LS | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0089 | Radio antenna (805-11570) | EACH | 4 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0090 | Handhole, signal, type 2 (805-11744) | EACH | 9 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 0091 | Conduit, HDPE, 2 in. schedule 40 (805-11814) | LFT | 1,019 | $28.00 | $28.00 | $28.00 | $28.00 |
| 0092 | Conduit, HDPE, 2 in. schedule 80 (805-11815) | LFT | 2,265 | $30.00 | $30.00 | $30.00 | $30.00 |
| 0093 | Span, catenary, and tether (805-78415) | EACH | 4 | $3,500.00 | $3,500.00 | $3,500.00 | $3,500.00 |
| 0094 | Disconnect hanger (805-78420) | EACH | 4 | $600.00 | $600.00 | $600.00 | $600.00 |
| 0095 | Signal cable, roadway loop, copper, 1C/14 gauge (805-78470) | LFT | 15,021 | $1.25 | $1.25 | $1.25 | $1.25 |
| 0096 | Signal cable, control, copper, 5C/14 gauge (805-78485) | LFT | 262 | $5.00 | $5.00 | $5.00 | $5.00 |
| 0097 | Signal cable, control, copper, 7C/14 gauge (805-78490) | LFT | 54 | $5.25 | $5.25 | $5.25 | $5.25 |
| 0098 | Signal cable, control, copper, 9C/14 gauge (805-78495) | LFT | 939 | $5.50 | $5.50 | $5.50 | $5.50 |
| 0099 | Signal cable, detector lead-in, copper, 2C/16 gauge (805-78510) | LFT | 10,045 | $1.50 | $1.50 | $1.50 | $1.50 |
| 0100 | Signal detector housing (805-78785) | EACH | 34 | $2,200.00 | $2,200.00 | $2,200.00 | $2,200.00 |
| 0101 | Saw cut for roadway loop detector and sealant (805-78795) | LFT | 5,959 | $13.50 | $13.50 | $13.50 | $13.50 |
| 0102 | Signal pole, steel strain, 36 FT (805-81060) | EACH | 4 | $11,000 | $11,000 | $11,000 | $11,000 |
| 0103 | Signal detector housing adjust to grade (805-92951) | EACH | 7 | $7.00 | $400.00 | $400.00 | $400.00 |
| 0104 | Line, remove (808-06716) | LFT | 224,986 | $0.40 | $0.40 | $0.45 | $0.40 |
| 0106 | Retro-reflectivity testing (808-09381) | LS | 1 | $1.00 | $1.00 | $14,115 | $1.00 |
| 0107 | Transverse marking, multi-component, crosshatch line, yellow, 12 in. (808-10042) | LFT | 165 | $6.00 | $6.00 | $40.00 | $6.00 |
| 0108 | Grooving for pavement markings (808-12032) | LFT | 224,707 | $0.50 | $0.50 | $0.85 | $0.50 |
| 0110 | Line, preformed plastic, solid, white, 6 in. (808-75052) | LFT | 73,676 | $6.25 | $6.25 | $5.20 | $6.25 |
| 0111 | Line, preformed plastic, broken, white, 6 in. (808-75055) | LFT | 14,854 | $6.50 | $6.50 | $6.14 | $6.50 |
| 0112 | Line, preformed plastic, solid, yellow, 6 in. (808-75057) | LFT | 59,567 | $6.25 | $6.25 | $5.20 | $6.25 |
| 0114 | Transverse marking, preformed plastic, stop line, white, 24 in. (808-75067) | LFT | 623 | $24.00 | $24.00 | $26.31 | $24.00 |
| 0115 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 767 | $7.00 | $7.79 | $7.00 | $7.00 |
| 0116 | Snowplowable raised pavement marker (808-75998) | EACH | 767 | $42.00 | $42.00 | $27.50 | $42.00 |
| 0117 | Truck mounted attenuator (801-12042) | DAY | 20 | $1,500.00 | $1,599.19 | $200.00 | $600.00 |
| 0118 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 30 | $30.00 | $30.00 | $30.00 | $30.00 |
| 0119 | Transverse marking, preformed plastic, crosswalk line, white, 12 in. (808-06540) | LFT | 192 | $12.00 | $12.00 | $13.16 | $12.00 |
| 0120 | Transverse marking, thermoplastic, yield line, white, 24 in. (808-10118) | LFT | 23 | $20.00 | $20.00 | $20.00 | $20.00 |
| 0121 | Line, preformed plastic, broken, yellow, 6 in. (808-12845) | LFT | 448 | $6.25 | $6.25 | $6.14 | $6.25 |
| 0122 | Pavement message marking, preformed plastic, lane indication arrow (808-75071) | EACH | 59 | $375.00 | $375.00 | $741.00 | $375.00 |
| 0123 | Traffic signal head, no. 3 (805-78205) | EACH | 8 | $1,150.00 | $1,150.00 | $1,150.00 | $1,150.00 |
| 0124 | Traffic signal head, no. 4 (805-78225) | EACH | 2 | $1,325.00 | $1,325.00 | $1,325.00 | $1,325.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of August 6, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.