INDOT contract R-43741-A bid tabulation
HMA OVERLAY AND BRIDGE REHABILITATION. Let by Indiana DOT on January 14, 2026, Decatur, Seymour. 2 bids received; low bid $74,409,900 by John R Jurgensen Company.
- Owner
- Indiana DOT
- Letting
- 14 JAN 2026
- Pay items
- 324
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | John R Jurgensen Company | $74,409,900 | Low |
| 2 | Milestone Contractors LP | $84,750,000 | +14% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. John R Jurgensen Company | 2. Milestone Contractors LP |
|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $379,154 | $1,010,050 |
| 0002 | Construction engineering, GPS rover (105-11823) | LS | 1 | $50,450 | $150,000 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 |
| 0005 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 |
| 0008 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 |
| 0009 | Quality adjustments, pavement traffic markings (109-09377) | DOL | 1 | $1.00 | $1.00 |
| 0010 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 |
| 0011 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 |
| 0012 | Mobilization and demobilization (110-01001) | LS | 1 | $3,000,000 | $4,300,000 |
| 0013 | Partnering overhead (113-01614) | LS | 1 | $12,842 | $100,000 |
| 0014 | Clearing and grubbing (201-06587) | ACRE | 11 | $25,149 | $30,000 |
| 0015 | Clearing right-of-way (201-52370) | LS | 1 | $89,637 | $1,726,000 |
| 0016 | Debris, remove, structure no. 09 (201-90788) | LS | 1 | $17,000 | $15,000 |
| 0017 | Pavement removal (202-02240) | SYS | 145,108 | $9.45 | $5.20 |
| 0018 | Paved side ditch, remove (202-02272) | LFT | 880 | $14.58 | $80.00 |
| 0019 | Curb, concrete, remove (202-02278) | LFT | 228 | $25.84 | $23.60 |
| 0020 | Curb and gutter, remove (202-02279) | LFT | 120 | $24.46 | $24.20 |
| 0021 | Pipe abandon and grout fill (202-02637) | LFT | 678 | $68.20 | $127.00 |
| 0022 | Catch basin, remove (202-02928) | EACH | 9 | $580.71 | $1,075.00 |
| 0023 | Cable barrier, remove (202-12024) | LFT | 22,754 | $1.75 | $4.60 |
| 0024 | Safety terminal, remove (202-12026) | EACH | 11 | $55.00 | $59.10 |
| 0025 | Present structure, remove portions, structure no. 01 (202-51328) | LS | 1 | $10,000 | $30,000 |
| 0026 | Present structure, remove portions, structure no. 09 (202-51328) | LS | 1 | $60,000 | $900,000 |
| 0027 | Present structure, remove portions, structure no. 10 (202-51328) | LS | 1 | $60,000 | $700,000 |
| 0028 | Present structure, remove, structure no. 02 (202-51330) | LS | 1 | $150,000 | $550,000 |
| 0029 | Present structure, remove, structure no. 03 (202-51330) | LS | 1 | $160,000 | $350,000 |
| 0030 | Slopewall, remove (202-51368) | SYS | 872 | $25.00 | $132.00 |
| 0031 | Curb and gutter turnout, remove (202-92953) | SYS | 12 | $52.20 | $104.00 |
| 0032 | Guardrail end treatment, remove (202-93741) | EACH | 23 | $400.00 | $430.00 |
| 0033 | Pipe, remove (202-96133) | LFT | 5,500 | $21.30 | $37.50 |
| 0034 | Excavation, common (203-02000) | CYS | 83,700 | $19.46 | $6.00 |
| 0035 | Borrow (203-02070) | CYS | 18,896 | $24.58 | $6.00 |
| 0036 | Pump around (205-11626) | EACH | 1 | $6,000.00 | $25,000 |
| 0037 | Stormwater management budget (205-12108) | DOL | 846,501 | $1.00 | $1.00 |
| 0038 | Stormwater management implementation (205-12616) | LS | 1 | $67,200 | $650,000 |
| 0039 | SWQCP preparation (205-12618) | LS | 1 | $3,500.00 | $50,000 |
| 0040 | Excavation, foundation, unclassified (206-51230) | CYS | 728 | $50.00 | $96.00 |
| 0041 | Cofferdam (206-51235) | LS | 1 | $1,100,000 | $450,000 |
| 0042 | Subgrade treatment, type II (207-08264) | SYS | 1,953 | $63.03 | $35.50 |
| 0043 | Subgrade treatment, type IC (207-09935) | SYS | 71,187 | $33.46 | $37.00 |
| 0044 | Subgrade treatment, type ibc (207-12635) | SYS | 97,672 | $13.25 | $12.00 |
| 0045 | Structure backfill, type 1 (211-09264) | CYS | 1,285 | $62.19 | $110.00 |
| 0046 | Flowable backfill, non- removable (213-09269) | CYS | 4 | $185.00 | $1,165.00 |
| 0047 | Flowable backfill, removable (213-09270) | CYS | 71 | $170.00 | $323.00 |
| 0048 | Geogrid, type IB (214-11796) | SYS | 65,690 | $1.64 | $1.50 |
| 0049 | Geotextile for pavement, type 2A (214-12238) | SYS | 27,091 | $2.91 | $2.46 |
| 0050 | Geotextile for pavement, type 2B (214-12239) | SYS | 7,144 | $4.21 | $3.50 |
| 0051 | Compacted aggregate, no. 2 (301-12231) | CYS | 8 | $165.00 | $492.00 |
| 0052 | Compacted aggregate, no. 8 (301-12233) | CYS | 3,010 | $118.89 | $103.00 |
| 0053 | Compacted aggregate, no. 53 (301-12234) | CYS | 14,585 | $85.74 | $73.20 |
| 0054 | Subbase for PCCP (302-06464) | CYS | 1,216 | $140.00 | $245.00 |
| 0055 | Compacted aggregate, no. 53 (303-01180) | TON | 38,656 | $43.18 | $40.00 |
| 0056 | HMA patching, full depth, type C (304-12625) | TON | 1,382 | $211.55 | $185.00 |
| 0057 | HMA patching, partial depth, type C (304-12626) | TON | 322 | $391.93 | $292.00 |
| 0058 | HMA patching, full depth, type D (304-12627) | TON | 1,969 | $257.25 | $147.00 |
| 0059 | HMA patching, partial depth, type D (304-12628) | TON | 43 | $546.27 | $550.00 |
| 0060 | Rubblizing PCCP (305-97019) | SYS | 93,221 | $2.78 | $2.20 |
| 0061 | Milling, asphalt, 2 in. (306-08036) | SYS | 172,387 | $1.32 | $1.86 |
| 0062 | Milling, asphalt removal (306-08039) | SYS | 92,939 | $2.16 | $7.50 |
| 0063 | Milling, transition (306-08043) | SYS | 493 | $14.96 | $18.60 |
| 0064 | Milling, asphalt, 1/2 in. (306-08599) | SYS | 57,123 | $1.27 | $3.00 |
| 0065 | Lean concrete base, 9 in. (309-12695) | SYS | 1,022 | $135.31 | $73.50 |
| 0066 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 73 | $183.55 | $210.00 |
| 0067 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 12,657 | $124.45 | $103.50 |
| 0068 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 22 | $383.19 | $259.00 |
| 0069 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 25,628 | $99.78 | $93.50 |
| 0070 | QC/QA-HMA, 4, 58E, intermediate, 19.0 MM (401-000045) | TON | 28,644 | $94.74 | $94.50 |
| 0071 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 90 | $151.76 | $155.00 |
| 0072 | QC/QA-HMA, 4, 58S, base, 25.0 MM (401-000048) | TON | 904 | $158.66 | $100.50 |
| 0073 | QC/QA-HMA, 2, 58S, base, 19.0 MM (401-000052) | TON | 10,369 | $89.21 | $89.50 |
| 0074 | QC/QA-HMA, 4, 58S, base, 19.0 MM (401-000056) | TON | 83,852 | $84.69 | $90.50 |
| 0075 | QC/QA-HMA, 4, 58E, intermediate, OG, 19.0 MM (401-000067) | TON | 21,381 | $88.64 | $90.50 |
| 0076 | Joint adhesive (401-11526) | LFT | 302,673 | $0.68 | $1.00 |
| 0077 | Inertial profiler, HMA (401-12169) | LS | 1 | $6,133.30 | $10,172 |
| 0078 | HMA spray paver emulsion (401-12664) | TON | 623 | $690.00 | $1,000.00 |
| 0079 | HMA wedge and level, type D (402-07787) | TON | 19,067 | $92.77 | $100.50 |
| 0080 | HMA for temporary pavement, type D (402-10087) | TON | 12,467 | $95.71 | $105.50 |
| 0081 | Asphalt for tack coat (406-05520) | TON | 175 | $690.00 | $600.00 |
| 0082 | QC/QA-HMA, 4, 58E, surface, 9.5 MM - SMA (410-000073) | TON | 41,528 | $148.73 | $129.00 |
| 0083 | Void reducing asphalt membrane for SMA (410-12466) | LFT | 276,294 | $3.05 | $4.00 |
| 0084 | SMA spray paver emulsion (410-12665) | TON | 293 | $690.00 | $1,000.00 |
| 0085 | Retrofitted tie bars (503-03489) | EACH | 320 | $37.15 | $70.30 |
| 0086 | D-1 contraction joint (503-05240) | LFT | 1,245 | $23.74 | $23.60 |
| 0087 | PCCP stitching (503-09261) | EACH | 72 | $87.70 | $142.00 |
| 0088 | Jointed reinforced concrete pavement, 12 in. (503-12476) | SYS | 2,420 | $185.00 | $194.00 |
| 0089 | Terminal joint, type HMA (503-12477) | LFT | 472 | $525.00 | $642.00 |
| 0090 | Terminal joint, type PCCP (503-12478) | LFT | 267 | $350.00 | $362.00 |
| 0091 | Expansion joint with load transfer (503-12479) | LFT | 264 | $80.00 | $77.20 |
| 0092 | Terminal joint, retrofit polymer modified asphalt (503-12480) | SFT | 683 | $82.50 | $61.20 |
| 0093 | PCCP patching, full depth (506-06333) | SYS | 1,022 | $298.94 | $203.00 |
| 0094 | Joint repair, partial depth (509-12191) | SFT | 1,148 | $127.73 | $84.70 |
| 0095 | Joint repair, bottom-half (509-12192) | SFT | 98 | $251.25 | $803.00 |
| 0096 | Temporary guardrail, W- beam, 6 FT 3 in. spacing (601-02206) | LFT | 1,313 | $13.00 | $14.00 |
| 0097 | Guardrail, remove (601-02241) | LFT | 28,668 | $1.75 | $1.90 |
| 0098 | Guardrail, reset (601-06035) | LFT | 1,073 | $9.00 | $9.70 |
| 0099 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 30,223 | $19.50 | $21.00 |
| 0100 | Guardrail, MGS W-beam, double faced, 6 FT 3 in. spacing (601-12284) | LFT | 463 | $28.00 | $30.10 |
| 0101 | Guardrail height transition, MGS (601-12289) | EACH | 14 | $1,032.96 | $860.00 |
| 0102 | Guardrail transition, MGS without curb (601-12292) | EACH | 37 | $3,232.97 | $3,226.00 |
| 0103 | Guardrail, MGS W-beam, cable terminal anchor (601-12294) | EACH | 21 | $1,100.00 | $1,183.00 |
| 0104 | Guardrail, post (601-52501) | EACH | 80 | $100.00 | $108.00 |
| 0105 | Guardrail end treatment, type OS (601-94689) | EACH | 27 | $2,150.00 | $2,312.00 |
| 0106 | Guardrail end treatment, type MS (601-94690) | EACH | 3 | $5,250.00 | $5,645.00 |
| 0107 | Temporary guardrail end treatment, type OS (601-97080) | EACH | 8 | $2,000.00 | $2,151.00 |
| 0108 | Barrier delineator (602-06729) | EACH | 80 | $26.57 | $13.00 |
| 0109 | Fence, chain link, reset (603-06065) | LFT | 75 | $14.00 | $15.10 |
| 0110 | Curb, integral concrete, type C , modified (605-06100) | LFT | 92 | $124.85 | $58.80 |
| 0111 | Curb, integral concrete, modified (605-06105) | LFT | 212 | $74.85 | $61.00 |
| 0112 | Curb, concrete (605-06120) | LFT | 44 | $59.85 | $88.30 |
| 0113 | Curb and gutter, concrete, type C (605-06150) | LFT | 120 | $79.85 | $67.22 |
| 0114 | Milled HMA corrugations, conventional (606-12399) | LFT | 203,570 | $0.12 | $0.25 |
| 0115 | Paved side ditch, type B (607-06340) | LFT | 957 | $100.97 | $168.00 |
| 0116 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 2,736 | $175.00 | $234.00 |
| 0117 | HMA for approaches, type B (610-07487) | TON | 471 | $176.75 | $160.50 |
| 0118 | Monument, type C (615-06510) | EACH | 25 | $550.00 | $591.00 |
| 0119 | Monument, type D (615-06515) | EACH | 12 | $105.00 | $113.00 |
| 0120 | Riprap, class 1 (616-05688) | TON | 1,580 | $75.00 | $109.00 |
| 0121 | Riprap, class 2 (616-05689) | TON | 5,576 | $95.00 | $145.00 |
| 0122 | Riprap, revetment (616-06405) | TON | 1,657 | $118.73 | $182.50 |
| 0123 | Riprap, uniform (616-06451) | TON | 274 | $160.09 | $120.00 |
| 0124 | Geotextile for riprap, type 1A (616-12246) | SYS | 9,772 | $2.04 | $4.50 |
| 0125 | Geotextile for riprap, type 2A (616-12248) | SYS | 765 | $2.50 | $4.65 |
| 0126 | Riprap, grouted, 18 in. (616-93019) | SYS | 10 | $210.00 | $492.00 |
| 0127 | Clean steel bridge, partial, QP-1, bridge no. 09 (619-11049) | LS | 1 | $15,000 | $20,431 |
| 0128 | Clean steel bridge, partial, QP-1, bridge no. 10 (619-11049) | LS | 1 | $15,000 | $20,431 |
| 0129 | Clean steel bridge, QP-2, bridge no. 07 (619-11052) | LS | 1 | $145,000 | $82,798 |
| 0130 | Clean steel bridge, QP-2, bridge no. 08 (619-11052) | LS | 1 | $145,000 | $82,798 |
| 0131 | Disposal of cleaning waste, hazardous, bridge no. 01 (619-12459) | LS | 1 | $1,000.00 | $1,075.00 |
| 0132 | Disposal of cleaning waste, hazardous, bridge no. 07 (619-12459) | LS | 1 | $5,000.00 | $2,688.00 |
| 0133 | Disposal of cleaning waste, hazardous, bridge no. 08 (619-12459) | LS | 1 | $5,000.00 | $2,688.00 |
| 0134 | Disposal of cleaning waste, non-hazardous, bridge no. 09 (619-12460) | LS | 1 | $500.00 | $1,075.00 |
| 0135 | Disposal of cleaning waste, non-hazardous, bridge no. 10 (619-12460) | LS | 1 | $500.00 | $1,075.00 |
| 0136 | Coat steel bridge, bridge no. 07 (619-51859) | LS | 1 | $8,000.00 | $53,075 |
| 0137 | Coat steel bridge, bridge no. 08 (619-51859) | LS | 1 | $8,000.00 | $53,075 |
| 0138 | Coat steel bridge, partial, bridge no. 09 (619-51860) | LS | 1 | $500.00 | $8,602.00 |
| 0139 | Coat steel bridge, partial, bridge no. 10 (619-51860) | LS | 1 | $500.00 | $8,602.00 |
| 0140 | Clean and coat bearing assemblies, bridge no. 01 (619-95315) | LS | 1 | $8,000.00 | $21,230 |
| 0141 | Mobilization and demobilization for seeding (621-01004) | EACH | 15 | $800.00 | $860.00 |
| 0142 | Erosion control blanket (621-02770) | SYS | 55,058 | $1.15 | $1.25 |
| 0143 | Seed mixture, type R (621-06553) | LBS | 10,135 | $7.55 | $8.10 |
| 0144 | Mulched seeding, type R (621-06559) | SYS | 840 | $1.90 | $2.05 |
| 0145 | Mulched seeding, type U (621-06560) | SYS | 3,109 | $0.81 | $0.85 |
| 0146 | Mulching material (621-06565) | TON | 123 | $471.00 | $506.00 |
| 0147 | Sodding (621-06574) | SYS | 3,819 | $9.77 | $12.40 |
| 0148 | Seed mixture, floodplain (621-12612) | LBS | 6 | $243.00 | $261.00 |
| 0149 | Cable barrier system, type TL-4 (627-09327) | LFT | 22,754 | $17.75 | $19.10 |
| 0150 | Safety terminal, type TL-3 (627-09330) | EACH | 11 | $5,800.00 | $6,237.00 |
| 0151 | Cable barrier system, type TL-4, reset (627-11647) | LFT | 26,593 | $5.00 | $5.40 |
| 0152 | Field office, type E (628-12684) | MOS | 36 | $7,248.54 | $5,035.00 |
| 0153 | Topsoil processing and distribution (629-000149) | SYS | 251,453 | $5.62 | $5.10 |
| 0154 | Topsoil amendment budget (629-000150) | DOL | 502,906 | $1.00 | $1.00 |
| 0155 | Dynamic pile load test (701-06011) | EACH | 4 | $6,400.00 | $4,010.00 |
| 0156 | Test pile, dynamic, production (701-09557) | LFT | 256 | $60.00 | $77.60 |
| 0157 | Test pile, dynamic, restrike (701-09559) | EACH | 4 | $3,200.00 | $2,005.00 |
| 0158 | Prebored hole, diameter 15 in. (701-09779) | LFT | 576 | $75.00 | $247.00 |
| 0159 | Pile, steel H, HP 12 X 74 (701-95780) | LFT | 4,495 | $75.00 | $133.00 |
| 0160 | Concrete, A, substructure (702-51005) | CYS | 490.20 | $950.00 | $999.00 |
| 0161 | Concrete, B, footings (702-51015) | CYS | 79.20 | $950.00 | $1,483.00 |
| 0162 | Field drilled hole in concrete (702-51863) | EACH | 272 | $40.00 | $27.70 |
| 0163 | Concrete, C, substructure (702-92857) | CYS | 2.60 | $1,650.00 | $8,064.00 |
| 0164 | Reinforcing bars (703-06028) | LBS | 34,240 | $1.47 | $1.58 |
| 0165 | Reinforcing bars, epoxy coated (703-06029) | LBS | 393,002 | $1.56 | $1.80 |
| 0166 | Embedded galvanic anode (703-08247) | EACH | 134 | $75.00 | $43.00 |
| 0167 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 226 | $30.00 | $35.70 |
| 0168 | Concrete, C, superstructure (704-51002) | CYS | 1,013.70 | $1,200.00 | $1,279.00 |
| 0169 | Concrete bridge railing transition, type TPS-1 , modified (706-06353) | EACH | 4 | $6,000.00 | $9,678.00 |
| 0170 | Railing, concrete type FT (706-11601) | CYS | 43.40 | $1,100.00 | $968.00 |
| 0171 | Concrete bridge railing transition, type TFT (706-11621) | EACH | 32 | $4,500.00 | $5,113.00 |
| 0172 | Railing, concrete type C (706-51020) | CYS | 11.90 | $2,000.00 | $3,003.00 |
| 0173 | Fiber wrap concrete casing system (709-04647) | LS | 1 | $50,000 | $99,234 |
| 0174 | Surface seal , bridge no. 01 (709-51821) | LS | 1 | $6,228.00 | $7,445.00 |
| 0175 | Surface seal , bridge no. 02 (709-51821) | LS | 1 | $4,409.00 | $4,946.00 |
| 0176 | Surface seal , bridge no. 03 (709-51821) | LS | 1 | $4,781.00 | $5,253.00 |
| 0177 | Surface seal , bridge no. 04 (709-51821) | LS | 1 | $7,072.00 | $7,140.00 |
| 0178 | Surface seal , bridge no. 05 (709-51821) | LS | 1 | $7,072.00 | $7,140.00 |
| 0179 | Surface seal , bridge no. 06 (709-51821) | LS | 1 | $10,012 | $10,563 |
| 0180 | Surface seal , bridge no. 07 (709-51821) | LS | 1 | $3,844.00 | $4,217.00 |
| 0181 | Surface seal , bridge no. 08 (709-51821) | LS | 1 | $3,844.00 | $4,217.00 |
| 0182 | Surface seal , bridge no. 09 (709-51821) | LS | 1 | $6,268.00 | $6,740.00 |
| 0183 | Surface seal , bridge no. 10 (709-51821) | LS | 1 | $6,268.00 | $6,740.00 |
| 0184 | Surface seal , bridge no. 11 (709-51821) | LS | 1 | $1,848.00 | $2,573.00 |
| 0185 | Surface seal , bridge no. 12 (709-51821) | LS | 1 | $1,848.00 | $2,573.00 |
| 0186 | Patching concrete structures (710-09158) | SFT | 548 | $180.00 | $26.90 |
| 0187 | Structural steel (711-51035) | LBS | 6,400 | $3.00 | $8.49 |
| 0188 | Drilled hole (711-51864) | EACH | 72 | $125.00 | $109.00 |
| 0189 | Jacking and supporting beams , bridge no. 09 (711-51877) | LS | 1 | $28,000 | $18,531 |
| 0190 | Jacking and supporting beams , bridge no. 10 (711-51877) | LS | 1 | $28,000 | $18,531 |
| 0191 | Jacking and supporting superstructure , bridge no. 13 (711-90114) | LS | 1 | $25,000 | $5,034.00 |
| 0192 | Jacking and supporting steel beams (711-95291) | LS | 1 | $25,000 | $5,034.00 |
| 0193 | Safety metal end section, 4:1, diameter 12 in. (715-04611) | EACH | 1 | $3,400.89 | $1,975.00 |
| 0194 | Pipe end section, min. area 6.5 SFT (715-04694) | EACH | 1 | $2,649.59 | $2,340.00 |
| 0195 | Pipe, type 1, circular, diameter 36 in. (715-05019) | LFT | 224 | $261.05 | $110.00 |
| 0196 | Pipe, type 4, circular, diameter 6 in. (715-05048) | LFT | 106,665 | $9.03 | $6.65 |
| 0197 | Pipe, underdrain outlet, diameter 6 in. (715-05053) | LFT | 5,943 | $36.63 | $11.80 |
| 0198 | Pipe, type 1, circular, diameter 24 in. (715-05123) | LFT | 318 | $126.16 | $93.00 |
| 0199 | Pipe, type 2, circular, diameter 12 in. (715-05149) | LFT | 84 | $150.08 | $99.00 |
| 0200 | Pipe, type 2, circular, diameter 15 in. (715-05151) | LFT | 698 | $89.49 | $70.00 |
| 0201 | Pipe, type 2, circular, diameter 18 in. (715-05152) | LFT | 92 | $128.11 | $80.60 |
| 0202 | Pipe, type 2, circular, diameter 21 in. (715-05153) | LFT | 99 | $119.02 | $110.00 |
| 0203 | Pipe, type 2, circular, diameter 24 in. (715-05154) | LFT | 91 | $150.53 | $97.00 |
| 0204 | Pipe, type 3, circular, diameter 21 in. (715-05172) | LFT | 329 | $118.25 | $53.00 |
| 0205 | Pipe, type 3, circular, diameter 24 in. (715-05173) | LFT | 5,500 | $99.56 | $73.00 |
| 0206 | Pipe, type 1, deformed, min. area 5.0 SFT (715-05236) | LFT | 341 | $174.80 | $213.00 |
| 0207 | Pipe, type 1, deformed, min. area 6.5 SFT (715-05238) | LFT | 159 | $206.48 | $279.00 |
| 0208 | Pipe, type 1, deformed, min. area, 8.9 SFT (715-05242) | LFT | 311 | $231.91 | $384.00 |
| 0209 | Pipe, slotted drain, diameter 18 in. , 0.079 in. (715-05424) | LFT | 1,750 | $226.45 | $170.00 |
| 0210 | Pipe extension, circular, diameter 6 in. , cast iron (715-06566) | LFT | 18 | $1,020.00 | $256.00 |
| 0211 | Safety metal end section, 4:1, min. area 7.1 SFT (715-08453) | EACH | 1 | $6,421.58 | $8,637.00 |
| 0212 | Video inspection for pipe (715-09064) | LFT | 1,562 | $2.10 | $2.25 |
| 0213 | Grated box end section, type I, 3:1, min. area 6.28 SFT (715-09307) | EACH | 4 | $7,797.42 | $14,693 |
| 0214 | Pipe, roadway drain casting extension (715-10238) | EACH | 4 | $2,800.00 | $1,773.00 |
| 0215 | Grated box end section, type I, 3:1, min. area 8.9 SFT (715-12068) | EACH | 1 | $10,369 | $16,767 |
| 0217 | Grated box end section, type I, 3:1, diameter 24 in. (715-26770) | EACH | 2 | $7,104.79 | $7,500.00 |
| 0218 | Pipe end section, diameter 12 in. (715-46000) | EACH | 3 | $1,038.99 | $1,600.00 |
| 0219 | Pipe end section, diameter 15 in. (715-46005) | EACH | 5 | $1,208.01 | $1,300.00 |
| 0220 | Pipe end section, diameter 21 in. (715-46015) | EACH | 6 | $1,070.80 | $800.00 |
| 0221 | Pipe end section, diameter 24 in. (715-46020) | EACH | 2 | $1,849.52 | $1,683.00 |
| 0222 | Pipe end section, diameter 36 in. (715-46040) | EACH | 4 | $2,748.95 | $5,430.00 |
| 0223 | Grated box end section, type I, 4:1, diameter 15 in. (715-97402) | EACH | 1 | $6,229.48 | $9,150.00 |
| 0224 | Grated box end section, type I, 3:1, diameter 15 in. (715-97404) | EACH | 4 | $5,233.45 | $7,000.00 |
| 0225 | Grated box end section, type I, 3:1, diameter 18 in. (715-97406) | EACH | 1 | $6,199.29 | $7,556.00 |
| 0226 | Grated box end section, type II, 10:1, diameter 12 in. (715-97559) | EACH | 2 | $8,636.49 | $4,892.00 |
| 0227 | Pipe installation, trenchless, 36 in. (716-07635) | LFT | 224 | $1,003.74 | $950.00 |
| 0228 | HMA for underdrains (718-06526) | TON | 9,531 | $96.56 | $125.00 |
| 0229 | Outlet protector, type 1 (718-06528) | EACH | 48 | $2,308.84 | $1,350.00 |
| 0230 | Outlet protector, type 2 (718-06529) | EACH | 175 | $1,744.84 | $1,292.00 |
| 0231 | Outlet protector, type 3 (718-06531) | EACH | 46 | $1,479.04 | $1,226.00 |
| 0232 | Video inspection for underdrain (718-06532) | LFT | 10,000 | $1.25 | $1.35 |
| 0233 | Geotextile for underdrains, type 1A (718-12305) | SYS | 240 | $1.25 | $1.85 |
| 0234 | Geotextile for underdrains, type 2B (718-12308) | SYS | 71,325 | $2.40 | $3.85 |
| 0235 | Aggregate for underdrains (718-52610) | CYS | 4,323 | $61.38 | $94.47 |
| 0236 | Casting, inlet, adjust to grade (720-12797) | EACH | 21 | $1,163.73 | $3,475.00 |
| 0237 | Inlet, type N12 (720-45065) | EACH | 11 | $5,646.17 | $5,900.00 |
| 0238 | Bridge deck overlay, rigid (722-000134) | SYS | 5,872 | $102.00 | $157.00 |
| 0239 | Bridge deck, remove concrete overlay and surface (722-000183) | SYS | 2,252 | $28.00 | $13.20 |
| 0240 | Hydrodemolition (722-01066) | SYS | 5,698 | $65.00 | $91.10 |
| 0241 | Bridge deck overlay budget (722-12380) | DOL | 99,048 | $1.00 | $1.00 |
| 0242 | Bridge deck, remove concrete surface (722-12464) | SYS | 3,446 | $18.00 | $9.38 |
| 0243 | Longitudinal grooving (722-12732) | SYS | 9,777 | $3.39 | $6.45 |
| 0244 | Bridge deck patching, full depth (722-51401) | SFT | 1,080 | $50.00 | $91.00 |
| 0245 | Bridge deck patching, partial depth (722-51852) | SFT | 1,101 | $2.50 | $2.70 |
| 0246 | Overlay dam (722-51874) | SFT | 398 | $40.00 | $215.00 |
| 0247 | Bridge expansion joint, type PCF (724-12773) | LFT | 68 | $75.00 | $112.00 |
| 0248 | Bearing assembly, elastomeric (726-92406) | EACH | 32 | $2,500.00 | $2,523.00 |
| 0249 | Bearing assembly, elastomeric , modified (726-92406) | EACH | 8 | $1,800.00 | $2,083.00 |
| 0250 | Epoxy injection, epoxy injection adhesive (727-000188) | GAL | 11 | $90.00 | $26.90 |
| 0251 | Epoxy injection, crack preparation (727-90308) | LFT | 114 | $30.00 | $64.86 |
| 0252 | Epoxy injection, furnishing equipment , bridge no. 01 (727-93560) | LS | 1 | $3,000.00 | $1,613.00 |
| 0253 | Epoxy injection, furnishing equipment , bridge no. 06 (727-93560) | LS | 1 | $3,000.00 | $1,613.00 |
| 0254 | Warranted polymer overlay, bridge deck (738-12855) | SYS | 9,169 | $36.80 | $39.60 |
| 0255 | Polymer overlay, other concrete surface (738-12856) | SYS | 1,155 | $36.80 | $39.60 |
| 0256 | Bridge deck, remove existing polymer overlay system (738-12917) | SYS | 10,324 | $6.55 | $3.75 |
| 0257 | Construction sign, type C (801-03290) | EACH | 2 | $289.57 | $1,075.00 |
| 0258 | Road closure sign assembly (801-04308) | EACH | 10 | $281.21 | $538.00 |
| 0259 | Detour route marker assembly, multiple routes (801-06196) | EACH | 29 | $189.62 | $323.00 |
| 0260 | Temporary pavement marking, 6 in. (801-06206) | LFT | 107,439 | $0.61 | $0.60 |
| 0261 | Temporary pavement marking, removable, 5 in. (801-06208) | LFT | 38,618 | $2.79 | $1.43 |
| 0262 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 459,278 | $2.02 | $1.30 |
| 0263 | Temporary transverse pavement marking, removable, 24 in. (801-06218) | LFT | 24 | $7.43 | $53.80 |
| 0264 | Detour route marker assembly (801-06625) | EACH | 34 | $124.69 | $296.00 |
| 0265 | Construction sign, type A (801-06640) | EACH | 251 | $211.46 | $349.00 |
| 0266 | Construction sign, type B (801-06645) | EACH | 19 | $111.11 | $134.00 |
| 0267 | Flashing arrow sign (801-06710) | DAY | 2,493 | $13.57 | $5.40 |
| 0268 | Maintaining traffic (801-06775) | LS | 1 | $2,680,673 | $4,945,791 |
| 0269 | Energy absorbing terminal, CZ, TL-2 (801-07023) | EACH | 2 | $7,014.36 | $4,839.00 |
| 0270 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 10 | $8,032.09 | $7,500.00 |
| 0271 | Barricade, type III-A (801-07118) | LFT | 350 | $14.62 | $26.90 |
| 0272 | Barricade, type III-B (801-07119) | LFT | 105 | $14.62 | $26.90 |
| 0273 | Temporary crossover drainage pipe (801-07606) | LFT | 4,050 | $81.85 | $215.00 |
| 0274 | Temporary traffic barrier, type 1 (801-08400) | LFT | 28,464 | $80.02 | $65.00 |
| 0275 | Temporary traffic barrier, type 2 (801-08401) | LFT | 14,642 | $25.55 | $65.00 |
| 0276 | Temporary pavement marking, removable, 12 in. (801-09087) | LFT | 274 | $3.69 | $5.40 |
| 0277 | Portable changeable message sign (801-11642) | EACH | 24 | $710.76 | $6,989.00 |
| 0278 | Vehicles for advanced slowdown (801-11880) | DAY | 12 | $2,069.32 | $4,037.00 |
| 0279 | Truck mounted attenuator (801-12042) | DAY | 18 | $1,340.54 | $1,546.00 |
| 0280 | Portable signal , bridge no. 06 (801-12081) | LS | 1 | $13,897 | $16,130 |
| 0281 | Law enforcement officer (801-12324) | HRS | 424 | $60.00 | $60.00 |
| 0283 | Queue truck , in use (801-12652) | DAY | 514 | $1,076.88 | $1,189.00 |
| 0284 | Temporary speed feedback assembly (801-12832) | EACH | 2 | $498.57 | $6,989.00 |
| 0285 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 30 | $796.57 | $484.00 |
| 0286 | Temporary pavement marking, 10 in. (801-12955) | LFT | 13,893 | $0.95 | $0.95 |
| 0287 | Temporary pavement marking, removable, 10 in. (801-12956) | LFT | 6,876 | $2.89 | $2.12 |
| 0288 | Temporary crossover, type B (801-52817) | EACH | 3 | $98,779 | $515,000 |
| 0289 | Temporary buzz strips (801-97643) | LFT | 12,096 | $23.26 | $17.70 |
| 0290 | Reference post (802-04893) | EACH | 8 | $250.00 | $188.00 |
| 0291 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 48 | $32.00 | $53.80 |
| 0292 | Sign and supports, wide flange, remove (802-74040) | EACH | 2 | $2,000.00 | $2,366.00 |
| 0293 | Sign post, type A (802-76055) | LFT | 280 | $29.00 | $32.30 |
| 0294 | Sign, ground mounted, reset (802-91122) | EACH | 51 | $300.00 | $296.00 |
| 0295 | Delineator with post, type D1 (804-06725) | EACH | 298 | $72.16 | $30.10 |
| 0296 | Delineator post, flexible, reset (804-97955) | EACH | 175 | $86.57 | $37.60 |
| 0297 | Conduit, PVC, 2 in. (805-06595) | LFT | 258 | $45.00 | $43.00 |
| 0298 | Wire, no. 4 copper, in conduit, bridge 1/C (807-01653) | LFT | 1,700 | $6.00 | $5.90 |
| 0299 | Handhole, lighting (807-02191) | EACH | 4 | $1,800.00 | $2,151.00 |
| 0300 | Transverse marking, remove (808-06368) | LFT | 672 | $5.31 | $5.40 |
| 0301 | Line, remove (808-06716) | LFT | 90,087 | $0.36 | $0.69 |
| 0302 | Transverse marking, paint, stop line, white, 24 in. (808-06726) | LFT | 25 | $4.50 | $26.90 |
| 0303 | Retro-reflectivity testing (808-09381) | LS | 1 | $9,915.00 | $5,914.00 |
| 0304 | Transverse marking, multi-component, crosshatch line, white, 24 in. (808-10038) | LFT | 1,643 | $12.00 | $21.50 |
| 0305 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 126,043 | $1.33 | $1.10 |
| 0306 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 123,726 | $1.33 | $1.10 |
| 0307 | Line, multi-component, broken, white, 6 in. (808-10071) | LFT | 35,014 | $1.33 | $0.55 |
| 0308 | Grooving for pavement markings (808-12032) | LFT | 282,386 | $0.35 | $0.50 |
| 0309 | Line, multi-component, dotted, white, 6 in. (808-12353) | LFT | 2,015 | $1.50 | $5.40 |
| 0310 | Line, preformed plastic, solid, white, 10 in. (808-12666) | LFT | 1,245 | $12.50 | $17.70 |
| 0311 | Line, paint, broken, yellow, 6 in. (808-12764) | LFT | 269 | $1.01 | $0.80 |
| 0312 | Line, multi-component, solid, white, 10 in. (808-12781) | LFT | 8,699 | $2.00 | $1.90 |
| 0313 | Line, preformed plastic, broken, black, 6 in. (808-12783) | LFT | 398 | $7.95 | $10.80 |
| 0314 | Line, paint, solid, white, 6 in. (808-75007) | LFT | 4,018 | $1.01 | $0.80 |
| 0315 | Line, paint, solid, yellow, 6 in. (808-75047) | LFT | 2,943 | $1.01 | $0.80 |
| 0316 | Line, preformed plastic, solid, white, 6 in. (808-75052) | LFT | 1,139 | $7.70 | $10.80 |
| 0317 | Line, preformed plastic, broken, white, 6 in. (808-75055) | LFT | 296 | $7.70 | $10.80 |
| 0318 | Line, preformed plastic, solid, yellow, 6 in. (808-75057) | LFT | 881 | $7.70 | $10.80 |
| 0319 | Prismatic reflector (808-75994) | EACH | 90 | $113.45 | $21.50 |
| 0320 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 866 | $14.05 | $21.50 |
| 0321 | Snowplowable raised pavement marker (808-75998) | EACH | 1,538 | $41.90 | $48.40 |
| 0322 | Line, preformed plastic, solid, white, 24 in. (808-99077) | LFT | 160 | $23.25 | $37.60 |
| 0323 | Automated work zone information system (801-12544) | EACH | 2 | $125,374 | $73,120 |
| 0324 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 20 | $1,064.84 | $2,318.00 |
| 0325 | Grated box end section, type II, 4:1, diameter 12 in. (715-26728) | EACH | 1 | $4,599.61 | $8,405.00 |
| 0326 | Queue truck , standby (801-12652) | DAY | 686 | $198.33 | $717.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of January 14, 2026. Compiled by Mirage Metrics.