INDOT contract R-43747-A bid tabulation

SMALL STRUCTURE REPLACEMENT. Let by Indiana DOT on October 8, 2025, Ripley, Seymour. 6 bids received; low bid $409,858 by 5 Star Company Inc.

Owner
Indiana DOT
Letting
08 OCT 2025
Pay items
58
Data through
05 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
15 Star Company Inc$409,858Low
2Olco Inc$488,670+19%
3Dave Omara Contractor Inc$489,686+19%
4Paul H Rohe Company Inc$515,507+26%
5Morphey Construction Inc.$547,043+33%
6Force Construction Co Inc$624,255+52%
INDOT contract R-43747-A: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. 5 Star Company Inc2. Olco Inc3. Dave Omara Contractor Inc4. Paul H Rohe Company Inc5. Morphey Construction Inc.6. Force Construction Co Inc
0001Construction engineering (105-06845)LS1$7,500.00$13,000$17,000$4,800.00$4,000.00$8,326.00
0002Liquidated damages (109-08359)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0003Contract liens (109-08360)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0004Quality adjustments, HMA (109-08440)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0005Quality adjustments, temporary traffic control devices (109-08443)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0006Quality adjustments, failed materials (109-08444)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0007Project estimate adjustment (109-08463)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0008Payment adjustment, PG asphalt binder (109-09489)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0009Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0010Mobilization and demobilization (110-01001)LS1$35,000$39,094$24,500$25,262$50,000$30,000
0011Clearing right-of-way (201-52370)LS1$2,500.00$16,818$19,177$9,385.00$4,400.00$8,337.00
0012Excavation, common (203-02000)CYS215$40.00$49.46$19.00$85.00$55.00$154.00
0013Borrow (203-02070)CYS33$5.00$94.31$49.00$160.00$62.00$246.00
0014Pump around (205-11626)EACH3$4,000.00$5,853.99$4,400.00$8,600.00$5,000.00$9,313.00
0015Stormwater management budget (205-12108)DOL17,800$1.00$1.00$1.00$1.00$1.00$1.00
0016Stormwater management implementation (205-12616)LS1$4,000.00$5,718.00$8,325.00$4,500.00$990.00$7,916.00
0017Subgrade treatment, type IC (207-09935)SYS224$37.00$53.12$30.00$68.00$52.00$31.00
0018Structure backfill, type 2 (211-09265)CYS73$65.00$89.10$93.00$140.00$107.00$80.00
0019Structure backfill, type 5 (211-09268)CYS63$180.00$260.30$230.00$275.00$215.00$201.00
0020Geotextile for pavement, type 2B (214-12239)SYS250$4.00$5.83$10.00$7.00$6.00$7.50
0021Compacted aggregate, no. 8 (301-12233)CYS43$55.00$102.04$158.00$140.00$160.00$91.00
0022Compacted aggregate, no. 53 (303-01180)TON92$38.00$68.99$48.00$68.00$60.00$44.00
0023Milling, transition (306-08043)SYS540$6.00$10.50$7.00$9.00$12.00$16.00
0024QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005)TON62$175.00$236.04$222.00$195.00$200.00$222.00
0025QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041)TON29$159.00$235.73$222.00$185.00$200.00$222.00
0026QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047)TON93$140.00$187.22$222.00$170.00$200.00$222.00
0027Joint adhesive (401-11526)LFT540$1.00$1.66$0.56$0.80$0.50$0.55
0028Asphalt for tack coat (406-05520)TON1$1,500.00$2,061.49$650.00$950.00$600.00$667.00
0029Cracks in asphalt pavement, fill (408-12028)TON1$1,000.00$3,402.77$2,775.00$5,500.00$2,500.00$2,779.00
0030Milled HMA corrugations, conventional (606-12399)LFT420$13.00$4.00$11.00$12.55$20.00$14.00
0031HMA for approaches, type B (610-07487)TON2$200.00$801.91$222.00$240.00$465.00$222.00
0032Riprap, revetment (616-06405)TON116$55.00$62.75$80.00$84.00$150.00$88.00
0033Geotextile for riprap, type 1A (616-12246)SYS433$3.50$3.67$4.50$5.00$4.00$3.40
0034Geotextile for riprap, type 2A (616-12248)SYS35$3.50$9.30$23.00$25.00$4.00$28.00
0035Geotextile for riprap, type 2B (616-12249)SYS15$3.50$10.30$73.00$40.00$5.00$83.00
0036Mobilization and demobilization for seeding (621-01004)EACH2$200.00$143.90$1,000.00$1,000.00$1,000.00$1,112.00
0037Erosion control blanket (621-02770)SYS1,900$1.50$2.66$1.70$1.50$9.00$1.70
0038Mulched seeding, type R (621-06559)SYS1,900$3.00$3.93$1.70$1.50$9.00$1.70
0039Seed mixture, emergent wetland (621-06737)LBS10$300.00$204.70$300.00$300.00$2,000.00$333.00
0040Computer system equipment (628-11976)EACH2$400.00$1,106.67$1,000.00$960.00$800.00$892.00
0041Field office, type D (628-12683)MOS6$1,200.00$1,286.10$2,400.00$3,700.00$2,000.00$5,947.00
0042Concrete, A, substructure (702-51005)CYS5$2,000.00$3,765.87$2,460.00$3,300.00$4,100.00$2,210.00
0043Concrete, B, footings (702-51015)CYS2$1,200.00$5,040.79$3,795.00$5,890.00$4,000.00$1,430.00
0044Pipe, underdrain outlet, diameter 6 in. (715-05053)LFT30$10.00$50.08$48.00$85.00$58.00$80.00
0045Pipe, type 1, deformed, min. area 10.2 SFT (715-08177)LFT96$348.00$548.77$480.00$500.00$700.00$483.00
0046Concrete anchor, min. area 10.2 SFT (715-08179)EACH2$3,850.00$7,410.37$8,400.00$8,000.00$8,200.00$4,898.00
0047Outlet protector, type 1 (718-06528)EACH1$950.00$1,489.14$1,790.00$4,895.00$1,500.00$2,206.00
0048Pipe liner, cured-in- place, min. area 8.9 SFT (725-11300)LFT100$1,100.00$971.95$1,190.00$1,075.00$950.00$1,302.00
0049Road closure sign assembly (801-04308)EACH5$135.00$125.00$215.00$330.00$194.00$322.00
0050Detour route marker assembly (801-06625)EACH28$79.00$75.00$188.00$125.00$170.00$178.00
0051Construction sign, type A (801-06640)EACH24$180.00$175.00$237.00$235.00$214.00$237.00
0052Construction sign, type B (801-06645)EACH4$78.00$75.00$125.00$145.00$113.00$119.00
0053Maintaining traffic (801-06775)LS1$42,560$18,705$25,000$19,296$22,000$95,388
0054Barricade, type III-A (801-07118)LFT96$9.00$8.00$10.00$17.70$11.00$17.00
0055Barricade, type III-B (801-07119)LFT72$9.00$8.00$10.00$17.70$11.00$17.00
0056Line, multi-component, solid, white, 6 in. (808-10049)LFT280$16.00$15.00$10.00$14.50$10.00$16.00
0057Line, multi-component, broken, yellow, 6 in. (808-12841)LFT35$16.00$15.00$10.00$14.50$15.00$16.00
0058Snowplowable raised pavement marker (808-75998)EACH4$255.00$250.00$125.00$800.00$28.00$889.00
INDOT contract R-43747-A: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

Every contract let that day: INDOT letting of October 8, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy