INDOT contract R-43804-A bid tabulation
HMA OVERLAY MINOR STRUCTURAL AND SMALL STRUCTURE PIPE LINING. Let by Indiana DOT on October 8, 2025, Noble, Whitley, Fort Wayne. 4 bids received; low bid $10,429,917 by E & B Paving LLC.
- Owner
- Indiana DOT
- Letting
- 08 OCT 2025
- Pay items
- 110
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | E & B Paving LLC | $10,429,917 | Low |
| 2 | Phend & Brown Inc | $11,583,416 | +11% |
| 3 | Brooks Construction Company Inc | $13,349,345 | +28% |
| 4 | Milestone Contractors LP | $13,553,000 | +30% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E & B Paving LLC | 2. Phend & Brown Inc | 3. Brooks Construction Company Inc | 4. Milestone Contractors LP |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $65,000 | $25,000 | $20,000 | $10,080 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, pavement traffic markings (109-09377) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0011 | Mobilization and demobilization (110-01001) | LS | 1 | $500,000 | $525,000 | $650,000 | $650,642 |
| 0012 | Clearing right-of-way (201-52370) | LS | 1 | $223,000 | $100,000 | $50,000 | $140,200 |
| 0013 | Delineator post, remove (202-04435) | EACH | 2 | $50.00 | $25.00 | $50.00 | $200.00 |
| 0014 | Sign, remove (202-74035) | EACH | 1 | $50.00 | $75.00 | $169.00 | $200.00 |
| 0015 | Detector housing, remove (202-90277) | EACH | 4 | $50.00 | $350.00 | $533.00 | $533.00 |
| 0016 | Guardrail end treatment, remove (202-93741) | EACH | 22 | $325.00 | $325.00 | $325.00 | $325.00 |
| 0017 | Post, remove (202-94747) | EACH | 1 | $100.00 | $100.00 | $150.00 | $500.00 |
| 0018 | Pipe, remove (202-96133) | LFT | 40 | $182.99 | $75.00 | $31.00 | $75.00 |
| 0019 | Excavation, common (203-02000) | CYS | 60 | $79.66 | $200.00 | $96.00 | $225.00 |
| 0020 | Excavation, unclassified (203-02020) | CYS | 1,049 | $12.00 | $50.00 | $60.00 | $40.50 |
| 0021 | Linear grading (203-08607) | LFT | 105 | $20.43 | $50.00 | $18.00 | $210.00 |
| 0022 | Lightweight aggregate (203-09036) | CYS | 913 | $12.00 | $255.00 | $182.00 | $264.00 |
| 0023 | Excavation, waterway (203-51223) | CYS | 20 | $124.79 | $200.00 | $96.00 | $230.00 |
| 0024 | Pump around (205-11626) | EACH | 2 | $25,000 | $22,500 | $20,000 | $22,200 |
| 0025 | Stormwater management budget (205-12108) | DOL | 14,440 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0026 | Stormwater management implementation (205-12616) | LS | 1 | $15,000 | $10,000 | $18,300 | $9,000.00 |
| 0027 | Subgrade treatment, type IC (207-09935) | SYS | 21,339 | $5.60 | $30.00 | $48.00 | $59.00 |
| 0028 | B borrow (211-02050) | CYS | 138 | $12.00 | $95.00 | $91.00 | $84.00 |
| 0029 | Structure backfill, type 5 (211-09268) | CYS | 27 | $365.00 | $870.00 | $711.00 | $895.00 |
| 0030 | Geogrid, type IB (214-11796) | SYS | 20,571 | $0.10 | $1.00 | $4.00 | $1.00 |
| 0031 | Geotextile for pavement, type 1B (214-12237) | SYS | 2,054 | $0.25 | $3.00 | $8.00 | $2.00 |
| 0032 | Compacted aggregate, no. 53 (303-01180) | TON | 5,989 | $39.78 | $40.00 | $32.00 | $40.00 |
| 0033 | HMA patching, full depth, type C (304-12625) | TON | 13,578 | $130.00 | $115.00 | $205.00 | $140.00 |
| 0034 | HMA patching, partial depth, type C (304-12626) | TON | 472 | $130.00 | $195.00 | $205.00 | $130.00 |
| 0035 | Milling, asphalt, 2 in. (306-08036) | SYS | 217,142 | $2.10 | $2.50 | $3.00 | $2.00 |
| 0036 | Milling, transition (306-08043) | SYS | 2,520 | $2.70 | $5.00 | $3.00 | $2.00 |
| 0037 | Milling, approach (306-08432) | SYS | 16,338 | $8.00 | $6.80 | $5.00 | $2.00 |
| 0038 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 17,990 | $88.00 | $92.00 | $89.00 | $102.00 |
| 0039 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 29,983 | $70.00 | $84.00 | $79.00 | $95.00 |
| 0040 | Joint adhesive (401-11526) | LFT | 89,136 | $0.20 | $0.35 | $0.30 | $0.20 |
| 0041 | Inertial profiler, HMA (401-12169) | LS | 1 | $5,000.00 | $10,500 | $10,000 | $4,500.00 |
| 0042 | Void reducing asphalt membrane for HMA (401-12439) | LFT | 89,136 | $1.50 | $2.25 | $2.25 | $2.25 |
| 0043 | Asphalt for tack coat (406-05520) | TON | 204 | $600.00 | $700.00 | $725.00 | $1,500.00 |
| 0044 | Guardrail terminal system, W-beam, curved, type 3 (601-01846) | EACH | 12 | $2,800.00 | $2,800.00 | $2,800.00 | $2,800.00 |
| 0045 | Guardrail, remove (601-02241) | LFT | 1,248 | $2.50 | $2.50 | $2.50 | $2.50 |
| 0046 | Hand dig guardrail post holes (601-09238) | EACH | 50 | $100.00 | $100.00 | $100.00 | $100.00 |
| 0047 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 1,263 | $22.00 | $22.00 | $22.00 | $22.00 |
| 0048 | Guardrail height transition, MGS (601-12289) | EACH | 4 | $1,050.00 | $1,050.00 | $1,050.00 | $1,050.00 |
| 0049 | Guardrail end treatment, type OS (601-94689) | EACH | 10 | $3,125.00 | $3,125.00 | $3,125.00 | $3,125.00 |
| 0050 | Sidewalk, concrete (604-06070) | SYS | 16 | $372.34 | $550.00 | $952.00 | $1,000.00 |
| 0051 | Milled HMA corrugations, sinusoidal (606-12400) | LFT | 134,397 | $0.50 | $0.60 | $0.60 | $0.50 |
| 0052 | HMA for approaches, type B (610-07487) | TON | 3,737 | $160.00 | $110.00 | $120.00 | $130.00 |
| 0053 | Mailbox assembly, reset, single (611-08232) | EACH | 93 | $350.00 | $350.00 | $350.00 | $350.00 |
| 0054 | Right-of-way marker (615-06490) | EACH | 2 | $275.00 | $275.00 | $275.00 | $550.00 |
| 0055 | Casting adjust to grade, monument (615-06525) | EACH | 18 | $1,010.00 | $850.00 | $850.00 | $850.00 |
| 0056 | Riprap, class 1 (616-05688) | TON | 64 | $124.46 | $225.00 | $162.00 | $120.00 |
| 0057 | Riprap, class 2 (616-05689) | TON | 138 | $87.01 | $200.00 | $154.00 | $120.00 |
| 0058 | Riprap, revetment (616-06405) | TON | 18 | $194.44 | $210.00 | $130.00 | $120.00 |
| 0059 | Riprap, uniform (616-06451) | TON | 16 | $216.22 | $380.00 | $182.00 | $130.00 |
| 0060 | Geotextile for riprap, type 1A (616-12246) | SYS | 282 | $0.66 | $20.00 | $3.00 | $15.00 |
| 0061 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $600.00 | $600.00 | $500.00 | $600.00 |
| 0062 | Erosion control blanket (621-02770) | SYS | 405 | $3.25 | $3.25 | $2.65 | $3.25 |
| 0063 | Mulched seeding, type R (621-06559) | SYS | 1,890 | $3.06 | $3.06 | $3.00 | $3.06 |
| 0064 | Sodding (621-06574) | SYS | 50 | $52.50 | $52.50 | $40.00 | $62.50 |
| 0065 | Seed mixture, emergent wetland (621-06737) | LBS | 0.02 | $20,300 | $20,300 | $40,000 | $20,955 |
| 0066 | Field office, type D (628-12683) | MOS | 12 | $4,000.00 | $5,000.00 | $4,000.00 | $4,000.00 |
| 0067 | Concrete anchor, diameter 66 in. (715-07626) | EACH | 2 | $9,524.61 | $13,500 | $7,413.00 | $5,000.00 |
| 0068 | Video inspection for pipe (715-09064) | LFT | 105 | $31.00 | $31.00 | $31.00 | $31.00 |
| 0069 | Pipe installation, trenchless, 66 in. (716-09822) | LFT | 105 | $4,018.48 | $3,250.00 | $3,300.00 | $2,430.00 |
| 0070 | Casting, inlet, adjust to grade (720-12797) | EACH | 3 | $1,500.00 | $2,350.00 | $1,000.00 | $1,800.00 |
| 0071 | Casting, manhole, adjust to grade (720-12798) | EACH | 5 | $1,500.00 | $2,450.00 | $550.00 | $1,000.00 |
| 0072 | Casting, water valve, adjust to grade (720-94840) | EACH | 3 | $500.00 | $900.00 | $150.00 | $150.00 |
| 0073 | Pipe liner, cured-in- place, 72 in. (725-10203) | LFT | 567 | $1,301.00 | $1,650.00 | $1,700.00 | $1,537.09 |
| 0074 | Temporary pavement message marking, lane indication arrow (801-01504) | EACH | 9 | $125.00 | $171.00 | $125.00 | $250.00 |
| 0075 | Temporary pavement message marking, 'only' (801-01505) | EACH | 3 | $200.00 | $224.00 | $200.00 | $250.00 |
| 0076 | Road closure sign assembly (801-04308) | EACH | 11 | $450.00 | $261.00 | $450.00 | $300.00 |
| 0077 | Temporary pavement marking, 6 in. (801-06206) | LFT | 387,160 | $0.34 | $0.05 | $0.30 | $0.10 |
| 0078 | Temporary transverse pavement marking, 6 in. (801-06214) | LFT | 123 | $3.75 | $3.11 | $3.75 | $5.00 |
| 0079 | Temporary transverse pavement marking, 24 in. (801-06216) | LFT | 227 | $15.00 | $11.24 | $15.00 | $17.00 |
| 0080 | Detour route marker assembly (801-06625) | EACH | 29 | $150.00 | $167.00 | $150.00 | $150.00 |
| 0081 | Construction sign, type A (801-06640) | EACH | 102 | $300.00 | $218.00 | $300.00 | $230.00 |
| 0082 | Construction sign, type B (801-06645) | EACH | 4 | $150.00 | $107.00 | $150.00 | $150.00 |
| 0083 | Maintaining traffic (801-06775) | LS | 1 | $150,673 | $175,000 | $374,572 | $600,000 |
| 0084 | Barricade, type III-A (801-07118) | LFT | 140 | $20.00 | $15.81 | $20.00 | $18.00 |
| 0085 | Barricade, type III-B (801-07119) | LFT | 144 | $20.00 | $15.81 | $20.00 | $18.00 |
| 0086 | Temporary transverse pavement marking, removeable, 12 in. (801-11662) | LFT | 45 | $1.50 | $13.44 | $4.50 | $5.00 |
| 0087 | Law enforcement officer (801-12324) | HRS | 200 | $60.00 | $60.00 | $60.00 | $60.00 |
| 0088 | Construction signs mobile (801-92448) | DAY | 540 | $2.50 | $10.00 | $1.00 | $150.00 |
| 0089 | Sign post, square, type 2, reinforced anchor base (802-05702) | LFT | 25 | $50.00 | $21.00 | $30.00 | $30.00 |
| 0090 | Sign, sheet, with legend, 0.100 in. thickness (802-09840) | SFT | 3 | $50.00 | $25.00 | $34.75 | $34.75 |
| 0091 | Delineator post, flexible, type I (804-11920) | EACH | 2 | $75.00 | $100.00 | $100.00 | $104.00 |
| 0092 | Conduit, PVC, 2 in. schedule 40 (805-08214) | LFT | 50 | $25.00 | $50.00 | $44.35 | $44.35 |
| 0093 | Signal cable, roadway loop, copper, 1C/14 gauge (805-78470) | LFT | 648 | $2.00 | $0.75 | $3.06 | $3.06 |
| 0094 | Signal cable, detector lead-in, copper, 2C/16 gauge (805-78510) | LFT | 300 | $3.00 | $4.00 | $3.54 | $3.54 |
| 0095 | Signal detector housing (805-78785) | EACH | 4 | $2,500.00 | $2,500.00 | $2,047.00 | $2,047.00 |
| 0096 | Saw cut for roadway loop detector and sealant (805-78795) | LFT | 188 | $16.00 | $15.00 | $20.71 | $20.71 |
| 0097 | Retro-reflectivity testing (808-09381) | LS | 1 | $2,500.00 | $2,500.00 | $2,500.00 | $3,250.00 |
| 0098 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 120,886 | $1.00 | $1.00 | $1.00 | $1.05 |
| 0099 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 84,429 | $1.00 | $1.00 | $1.00 | $1.05 |
| 0100 | Line, multi-component, broken, white, 6 in. (808-10071) | LFT | 240 | $1.00 | $1.00 | $1.00 | $1.05 |
| 0101 | Grooving for pavement markings (808-12032) | LFT | 193,580 | $0.10 | $0.41 | $0.10 | $0.50 |
| 0102 | Line, multi-component, solid, white, 10 in. (808-12781) | LFT | 92 | $5.00 | $5.00 | $5.00 | $2.50 |
| 0103 | Line, multi-component, broken, yellow, 6 in. (808-12841) | LFT | 6,710 | $1.00 | $1.00 | $1.00 | $1.05 |
| 0104 | Transverse marking, thermoplastic, crosshatch line, white, 12 in. (808-75260) | LFT | 45 | $10.00 | $10.00 | $10.00 | $6.00 |
| 0105 | Transverse marking, thermoplastic, stop line, white, 24 in. (808-75297) | LFT | 227 | $20.00 | $12.00 | $20.00 | $20.00 |
| 0106 | Transverse marking, thermoplastic, crosswalk line, white, 6 in. (808-75300) | LFT | 123 | $5.00 | $7.00 | $5.00 | $3.00 |
| 0107 | Pavement message marking, thermoplastic, lane indication arrow (808-75320) | EACH | 9 | $150.00 | $175.00 | $150.00 | $250.00 |
| 0108 | Pavement message marking, thermoplastic, 'only' (808-75325) | EACH | 3 | $250.00 | $45.00 | $250.00 | $250.00 |
| 0109 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 1,515 | $9.17 | $9.00 | $6.00 | $6.00 |
| 0110 | Snowplowable raised pavement marker (808-75998) | EACH | 620 | $50.00 | $45.00 | $50.00 | $65.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of October 8, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.