INDOT contract R-43893-A bid tabulation
SMALL STRUCTURE REPLACEMENT AND PIPE LINING. Let by Indiana DOT on April 9, 2025, St. Joseph, LaPorte. 4 bids received; low bid $1,731,320 by Milestone Contractors LP.
- Owner
- Indiana DOT
- Letting
- 09 APR 2025
- Pay items
- 60
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Milestone Contractors LP | $1,731,320 | Low |
| 2 | Superior Construction Co Inc | $1,744,137 | +1.0% |
| 3 | HRP Construction Inc | $2,251,125 | +30% |
| 4 | Rieth-Riley Construction Co., Inc. | $2,369,899 | +37% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Milestone Contractors LP | 2. Superior Construction Co Inc | 3. HRP Construction Inc | 4. Rieth-Riley Construction Co., Inc. |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $19,220 | $21,820 | $15,000 | $9,220.00 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, PCCP (109-08441) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $85,000 | $86,500 | $225,000 | $168,655 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $51,000 | $17,000 | $50,000 | $21,130 |
| 0011 | Structures and obstructions, remove (202-01000) | LS | 1 | $24,498 | $10,000 | $50,000 | $52,602 |
| 0012 | Pavement removal (202-02240) | SYS | 457 | $34.40 | $15.00 | $30.00 | $39.96 |
| 0013 | Excavation, common (203-02000) | CYS | 435 | $56.10 | $43.00 | $100.00 | $131.97 |
| 0014 | Pump around (205-11626) | EACH | 3 | $2,500.00 | $0.01 | $1.00 | $4,250.18 |
| 0015 | Stormwater management budget (205-12108) | DOL | 39,466 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0016 | Stormwater management implementation (205-12616) | LS | 1 | $1,400.00 | $10,000 | $30,000 | $48,864 |
| 0017 | Subgrade treatment, type IC (207-09935) | SYS | 522 | $56.50 | $40.00 | $55.00 | $75.53 |
| 0018 | Structure backfill, type 2 (211-09265) | CYS | 1,378 | $82.60 | $115.00 | $225.00 | $224.81 |
| 0019 | Geotextile for pavement, type 2A (214-12238) | SYS | 522 | $7.70 | $4.00 | $7.00 | $9.61 |
| 0020 | Geotextile for pavement, type 2B (214-12239) | SYS | 4,520 | $6.10 | $5.00 | $15.00 | $10.59 |
| 0021 | Compacted aggregate, no. 5 (301-12232) | CYS | 174 | $105.00 | $70.00 | $100.00 | $148.97 |
| 0022 | Compacted aggregate, no. 8 (301-12233) | CYS | 245 | $104.80 | $100.00 | $325.00 | $244.75 |
| 0023 | Subbase for PCCP (302-06464) | CYS | 131 | $158.00 | $115.00 | $125.00 | $150.93 |
| 0024 | Compacted aggregate, no. 53 (303-01180) | TON | 68 | $73.30 | $70.00 | $150.00 | $118.47 |
| 0025 | PCCP, 11 in. (502-06328) | SYS | 457 | $150.00 | $120.00 | $187.00 | $361.44 |
| 0026 | D-1 contraction joint (503-05240) | LFT | 274 | $16.00 | $40.00 | $15.50 | $27.70 |
| 0027 | Expansion joint with load transfer (503-12479) | LFT | 57 | $26.00 | $52.00 | $25.00 | $64.45 |
| 0028 | Milled PCCP corrugations, conventional (606-11064) | LFT | 293 | $4.00 | $4.00 | $4.00 | $4.00 |
| 0029 | Riprap, class 1 (616-05688) | TON | 175 | $198.90 | $150.00 | $150.00 | $173.95 |
| 0030 | Riprap, class 2 (616-05689) | TON | 99 | $207.50 | $150.00 | $175.00 | $136.54 |
| 0031 | Riprap, revetment (616-06405) | TON | 255 | $117.40 | $125.00 | $100.00 | $133.19 |
| 0032 | Geotextile for riprap, type 1A (616-12246) | SYS | 518 | $4.50 | $7.00 | $7.00 | $137.08 |
| 0033 | Mobilization and demobilization for seeding (621-01004) | EACH | 5 | $400.00 | $400.00 | $400.00 | $400.00 |
| 0034 | Mulched seeding, type U (621-06560) | SYS | 2,943 | $3.82 | $3.82 | $10.00 | $3.82 |
| 0035 | Field office, type C (628-09403) | MOS | 8 | $2,500.00 | $2,400.00 | $2,500.00 | $4,253.20 |
| 0036 | Waterproofing membrane type 2 (714-000086) | SFT | 905 | $9.70 | $3.00 | $25.00 | $16.64 |
| 0037 | Pipe, type 4, circular, diameter 6 in. (715-05048) | LFT | 147 | $19.50 | $25.00 | $40.00 | $64.62 |
| 0038 | Pipe, underdrain outlet, diameter 6 in. (715-05053) | LFT | 8 | $116.60 | $55.00 | $250.00 | $260.02 |
| 0039 | Pipe, type 1, circular, diameter 96 in. (715-05145) | LFT | 285 | $1,960.00 | $2,130.00 | $1,650.00 | $1,754.37 |
| 0040 | Pipe extension, circular, diameter 66 in. , CMP (715-06338) | LFT | 10 | $2,550.00 | $1,000.00 | $2,500.00 | $2,993.23 |
| 0041 | Concrete anchor, diameter 72 in. (715-06357) | EACH | 2 | $12,700 | $15,000 | $15,000 | $22,513 |
| 0042 | Concrete anchor, diameter 96 in. (715-06691) | EACH | 2 | $14,970 | $20,000 | $17,500 | $24,602 |
| 0043 | Concrete anchor, diameter 66 in. (715-07626) | EACH | 2 | $12,690 | $15,000 | $15,000 | $24,304 |
| 0044 | Pipe extension, circular, diameter 72 in. , CMP (715-09370) | LFT | 10 | $2,607.00 | $1,000.00 | $3,000.00 | $2,329.25 |
| 0045 | Geotextile for underdrains, type 1A (718-12305) | SYS | 152 | $6.00 | $7.00 | $4.00 | $1.64 |
| 0046 | Aggregate for underdrains (718-52610) | CYS | 14 | $188.50 | $135.00 | $250.00 | $145.81 |
| 0047 | Pipe liner, cured-in- place, 72 in. (725-10203) | LFT | 128 | $1,087.00 | $1,200.00 | $1,300.00 | $1,130.73 |
| 0048 | Pipe liner, cured-in- place, 66 in. (725-11299) | LFT | 141 | $988.00 | $1,100.00 | $1,200.00 | $1,027.87 |
| 0049 | Road closure sign assembly (801-04308) | EACH | 3 | $275.00 | $275.00 | $275.00 | $275.00 |
| 0050 | Detour route marker assembly (801-06625) | EACH | 22 | $179.00 | $179.00 | $179.00 | $179.00 |
| 0051 | Construction sign, type A (801-06640) | EACH | 31 | $199.00 | $199.00 | $199.00 | $199.00 |
| 0052 | Construction sign, type B (801-06645) | EACH | 8 | $179.00 | $179.00 | $179.00 | $179.00 |
| 0053 | Maintaining traffic (801-06775) | LS | 1 | $7,950.00 | $20,000 | $15,000 | $7,950.00 |
| 0054 | Barricade, type III-A (801-07118) | LFT | 72 | $22.00 | $22.00 | $22.00 | $22.00 |
| 0055 | Portable changeable message sign (801-11642) | EACH | 2 | $4,200.00 | $4,200.00 | $4,200.00 | $4,200.00 |
| 0056 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 147 | $10.00 | $10.00 | $10.00 | $10.00 |
| 0057 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 147 | $10.00 | $10.00 | $10.00 | $10.00 |
| 0058 | Grooving for pavement markings (808-12032) | LFT | 294 | $10.00 | $10.00 | $10.00 | $10.00 |
| 0059 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 4 | $20.00 | $25.00 | $25.00 | $171.62 |
| 0060 | Snowplowable raised pavement marker (808-75998) | EACH | 4 | $100.00 | $100.00 | $100.00 | $100.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of April 9, 2025. Compiled by Mirage Metrics.