INDOT contract R-44764-A bid tabulation
SAFETY IMPROVEMENTS. Let by Indiana DOT on January 15, 2025, Monroe, Seymour. 4 bids received; low bid $340,747 by Edward & Jones Concrete Inc.
- Owner
- Indiana DOT
- Letting
- 15 JAN 2025
- Pay items
- 50
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Edward & Jones Concrete Inc | $340,747 | Low |
| 2 | Crider & Crider Inc | $414,250 | +22% |
| 3 | E & B Paving LLC | $427,427 | +25% |
| 4 | Milestone Contractors LP | $519,148 | +52% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Edward & Jones Concrete Inc | 2. Crider & Crider Inc | 3. E & B Paving LLC | 4. Milestone Contractors LP |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $9,950.00 | $23,150 | $14,015 | $12,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Mobilization and demobilization (110-01001) | LS | 1 | $24,500 | $19,850 | $21,000 | $25,000 |
| 0008 | Clearing right-of-way (201-52370) | LS | 1 | $16,500 | $9,421.75 | $8,500.00 | $10,000 |
| 0009 | Curb, concrete, remove (202-02278) | LFT | 179 | $30.00 | $31.25 | $38.00 | $35.00 |
| 0010 | Curb and gutter, remove (202-02279) | LFT | 98 | $35.00 | $28.50 | $38.00 | $65.00 |
| 0011 | Sidewalk concrete, remove (202-52710) | SYS | 119 | $40.00 | $20.25 | $70.00 | $55.00 |
| 0012 | Excavation, common (203-02000) | CYS | 18 | $175.00 | $1,650.00 | $250.00 | $700.00 |
| 0013 | Subgrade treatment, type III (207-08266) | SYS | 42 | $60.00 | $32.50 | $90.00 | $165.00 |
| 0014 | Subgrade treatment, type IC (207-09935) | SYS | 46 | $102.00 | $97.50 | $120.00 | $165.00 |
| 0015 | Compacted aggregate, no. 53 (301-12234) | CYS | 5 | $165.00 | $389.00 | $450.00 | $595.00 |
| 0016 | HMA patching, full depth, type B (304-12623) | TON | 27 | $495.00 | $300.00 | $305.00 | $400.00 |
| 0017 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 1,282 | $10.00 | $23.50 | $17.25 | $18.00 |
| 0018 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 100 | $250.00 | $333.50 | $325.00 | $400.00 |
| 0019 | HMA wedge and level, type B (402-07451) | TON | 39 | $195.00 | $321.00 | $325.00 | $900.00 |
| 0020 | Brick pavers (604-03643) | SYS | 42 | $262.50 | $285.00 | $220.00 | $250.00 |
| 0021 | Sidewalk, concrete (604-06070) | SYS | 117 | $108.50 | $113.50 | $195.00 | $125.00 |
| 0022 | Curb ramp, concrete (604-08086) | SYS | 203 | $240.00 | $269.00 | $255.00 | $300.00 |
| 0023 | Detectable warning surfaces (604-12083) | SYS | 34 | $420.00 | $496.00 | $360.00 | $400.00 |
| 0024 | Curb, concrete (605-06120) | LFT | 374 | $54.00 | $57.00 | $95.00 | $100.00 |
| 0025 | Curb and gutter, concrete , modified (605-06140) | LFT | 93 | $69.50 | $57.00 | $95.00 | $115.00 |
| 0026 | Center curb, concrete, type D (605-06255) | SYS | 24 | $210.64 | $191.00 | $310.00 | $800.00 |
| 0027 | Water (621-06567) | KGAL | 1 | $32.55 | $100.00 | $0.01 | $0.01 |
| 0028 | Topsoil (621-06570) | CYS | 37 | $150.00 | $70.00 | $180.00 | $350.00 |
| 0029 | Sodding (621-06574) | SYS | 212 | $45.00 | $47.50 | $45.00 | $75.00 |
| 0030 | Concrete, A (702-90915) | CYS | 6 | $250.00 | $269.00 | $1,100.00 | $1,800.00 |
| 0031 | Casting, inlet, adjust to grade (720-12797) | EACH | 1 | $800.00 | $512.00 | $950.00 | $1,400.00 |
| 0032 | Casting, manhole, adjust to grade (720-12798) | EACH | 1 | $800.00 | $600.00 | $1,600.00 | $1,400.00 |
| 0033 | Casting, water valve, adjust to grade (720-94840) | EACH | 2 | $425.00 | $350.00 | $235.00 | $1,400.00 |
| 0034 | Temporary pavement marking, removable, 4 in. (801-06207) | LFT | 665 | $1.55 | $1.50 | $1.60 | $1.60 |
| 0035 | Temporary pavement marking, removable, 5 in. (801-06208) | LFT | 460 | $2.50 | $2.00 | $2.50 | $2.40 |
| 0036 | Construction sign, type A (801-06640) | EACH | 6 | $220.00 | $255.50 | $191.00 | $200.00 |
| 0037 | Construction sign, type B (801-06645) | EACH | 21 | $110.00 | $155.00 | $76.00 | $80.00 |
| 0038 | Maintaining traffic (801-06775) | LS | 1 | $23,500 | $43,000 | $69,050 | $70,000 |
| 0039 | Barricade, type III-B (801-07119) | LFT | 24 | $22.25 | $18.50 | $16.00 | $16.00 |
| 0040 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 195 | $37.75 | $41.50 | $35.00 | $36.00 |
| 0041 | Sign, sheet, and supports, remove (802-07059) | EACH | 10 | $165.00 | $175.00 | $150.00 | $150.00 |
| 0042 | Sign, sheet, relocate (802-07060) | EACH | 8 | $275.00 | $295.00 | $250.00 | $250.00 |
| 0043 | Sign, double-faced, sheet, with legend, 0.080 in. thickness (802-09837) | SFT | 27 | $75.00 | $82.00 | $70.00 | $80.00 |
| 0044 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 81 | $52.75 | $57.00 | $48.00 | $50.00 |
| 0045 | Transverse marking, thermoplastic, crosswalk line, white, 24 in. (808-03439) | LFT | 531 | $16.75 | $14.50 | $8.75 | $9.00 |
| 0046 | Line, thermoplastic, solid, white, 4 in. (808-06703) | LFT | 400 | $3.95 | $1.75 | $1.08 | $1.10 |
| 0047 | Line, remove (808-06716) | LFT | 2,048 | $0.85 | $1.00 | $0.62 | $0.65 |
| 0048 | Line, thermoplastic, solid, yellow, 4 in. (808-75245) | LFT | 1,865 | $3.89 | $1.75 | $1.08 | $1.10 |
| 0049 | Transverse marking, thermoplastic, crosshatch line, yellow, 12 in. (808-75278) | LFT | 46 | $11.25 | $20.00 | $4.38 | $4.40 |
| 0050 | Transverse marking, thermoplastic, stop line, white, 24 in. (808-75297) | LFT | 84 | $16.75 | $18.00 | $8.75 | $9.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of January 15, 2025. Compiled by Mirage Metrics.