Crider & Crider Inc: INDOT bid record
Crider & Crider Inc submitted 40 bids on Indiana DOT contracts in the data, from 12 JAN 2022 to 02 SEP 2026, and was the low bidder on 12 of them (30%). When it was not low, its total sat a median +10% above the low bid.
- Owner
- Indiana DOT
- Low bid volume
- $35,925,213
- Latest bid
- 02 SEP 2026
- Data through
- 05 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 6 | 3 | 50% |
| 2023 | 5 | 0 | 0% |
| 2024 | 10 | 2 | 20% |
| 2025 | 14 | 4 | 29% |
| 2026 | 5 | 3 | 60% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| Seymour | 24 | 10 | 42% |
| Crawfordsville | 6 | 0 | 0% |
| Vincennes | 5 | 2 | 40% |
| Greenfield | 4 | 0 | 0% |
| Fort Wayne | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Liquidated damages | 109-08359 | DOL | 39 | 39 (100%) | $1.00 | $1.00 |
| Contract liens | 109-08360 | DOL | 39 | 39 (100%) | $1.00 | $1.00 |
| Quality adjustments, failed materials | 109-08444 | DOL | 39 | 39 (100%) | $1.00 | $1.00 |
| Quality adjustments, HMA | 109-08440 | DOL | 39 | 39 (100%) | $1.00 | $1.00 |
| Stormwater management budget | 205-12108 | DOL | 37 | 37 (100%) | $1.00 | $1.00 |
| Quality adjustments, failure to maintain temporary erosion and sediment control measures | 109-11362 | DOL | 37 | 37 (100%) | $1.00 | $1.00 |
| Quality adjustments, temporary traffic control devices | 109-08443 | DOL | 35 | 35 (100%) | $1.00 | $1.00 |
| Payment adjustment, PG asphalt binder | 109-09489 | DOL | 32 | 32 (100%) | $1.00 | $1.00 |
| Project estimate adjustment | 109-08463 | DOL | 19 | 19 (100%) | $1.00 | $1.00 |
| Quality adjustments, PCCP | 109-08441 | DOL | 15 | 15 (100%) | $1.00 | $1.00 |
| Quality adjustments, pavement traffic markings | 109-09377 | DOL | 13 | 13 (100%) | $1.00 | $1.00 |
| Construction sign, type A | 801-06640 | EACH | 32 | 12 (38%) | $217.50 | $200.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| E & B Paving LLC | 34 | 12 of 34 |
| Milestone Contractors LP | 34 | 17 of 34 |
| Morphey Construction Inc. | 19 | 3 of 19 |
| Rieth-Riley Construction Co., Inc. | 11 | 5 of 11 |
| Gradex Inc | 10 | 6 of 10 |
| Force Construction Co Inc | 8 | 4 of 8 |
| Ragle, Inc. | 7 | 1 of 7 |
| William Charles Construction Company | 6 | 0 of 6 |
| CLR Inc | 6 | 2 of 6 |
| White Construction LLC | 5 | 4 of 5 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 02 SEP 2026 | R-44461-A | Seymour | SMALL STRUCTURE REPLACEMENT AND PIPE LINING | 5 of 9 | $1,978,114 | +26% |
| 05 AUG 2026 | R-44460-A | Seymour | SMALL STRUCTURE REPLACEMENT | 1 of 8 | $1,471,572 | Low, 4.0% under the second |
| 08 JUL 2026 | R-45311-A | Seymour | SMALL STRUCTURE REPLACEMENT | 2 of 7 | $867,107 | +34% |
| 08 APR 2026 | R-42595-A | Seymour | INTERSECTION IMPROVEMENT WITH ADDED TURN AND TRAVEL LANES | 1 of 4 | $6,452,552 | Low, 1.0% under the second |
| 11 FEB 2026 | R-44897-A | Seymour | SMALL STRUCTURES AND ADA SIDEWALK RAMP CONSTRUCTION | 1 of 4 | $2,646,480 | Low, 3.0% under the second |
| 10 DEC 2025 | R-44051-A | Seymour | SMALL STRUCTURE REPLACEMENT | 1 of 8 | $1,396,263 | Low, 6.0% under the second |
| 08 OCT 2025 | R-43736-A | Seymour | SMALL STRUCTURE REPLACEMENT AND PIPE LINING | 1 of 5 | $810,561 | Low, 3.0% under the second |
| 10 SEP 2025 | R-44765-A | Seymour | SAFETY REVISIONS | 2 of 5 | $6,440,562 | +3.0% |
| 06 AUG 2025 | R-41781-A | Greenfield | ADDED TRAVEL LANES, SMALL STR, BRIDGE WIDENING AND OVERLAY | 4 of 6 | $40,463,220 | +14% |
| 09 JUL 2025 | R-42194-A | Vincennes | INTERSECTION IMPROVEMENT, MEDIAN U-TURN | 3 of 3 | $5,217,586 | +24% |
| 09 JUL 2025 | R-42763-A | Crawfordsville | NEW ROAD CONSTRUCTION | 3 of 5 | $3,762,484 | +11% |
| 09 JUL 2025 | R-44250-A | Crawfordsville | NEW ROAD CONSTRUCTION | 5 of 9 | $4,554,313 | +14% |
| 14 MAY 2025 | R-41079-A | Fort Wayne | NEW INTERCHANGE, BRIDGE AND SIDEWALK CONSTRUCTION | 3 of 6 | $54,792,654 | +8.0% |
| 12 MAR 2025 | R-39270-A | Greenfield | ROAD RECONSTRUCTION, MEDIAN CONSTR AND SMALL STR REPLACEMENT | 2 of 4 | $33,958,726 | +1.0% |
| 12 FEB 2025 | R-41469-A | Vincennes | SMALL STRUCTURE REPLACEMENT AND SLIDE CORRECTION | 1 of 7 | $2,139,248 | Low, 9.0% under the second |
| 12 FEB 2025 | R-43234-A | Vincennes | SMALL STRUCTURE REPLACEMENT | 1 of 8 | $540,364 | Low, 5.0% under the second |
| 12 FEB 2025 | R-43335-A | Seymour | SMALL STRUCTURE REPLACEMENT | 8 of 8 | $1,511,175 | +70% |
| 15 JAN 2025 | R-44764-A | Seymour | SAFETY IMPROVEMENTS | 2 of 4 | $414,250 | +22% |
| 15 JAN 2025 | B-42174-A | Vincennes | BRIDGE REPLACEMENT | 5 of 8 | $3,077,971 | +17% |
| 11 DEC 2024 | R-42804-A | Vincennes | INTERSECTION IMPROVEMENT, ROUNDABOUT | 2 of 3 | $2,105,611 | 0.0% |
| 11 DEC 2024 | R-44240-A | Crawfordsville | NEW INTERCHANGE CONSTRUCTION | 5 of 6 | $66,411,149 | +10% |
| 11 DEC 2024 | B-42397-A | Greenfield | NEW BRIDGE, ACCESS CONTROL AND SURFACE TREATMENT | 4 of 7 | $38,895,407 | +7.0% |
| 11 SEP 2024 | R-42414-A | Seymour | INTERSECTION IMPROVEMENT WITH ADDED TURN LANES | 3 of 5 | $2,424,683 | +3.0% |
| 13 MAR 2024 | R-42277-A | Greenfield | INTERSECTION IMPROVEMENT, ROUNDABOUT AND NEW ROAD CONSTR | 2 of 7 | $4,162,555 | +5.0% |
| 15 FEB 2024 | R-40890-B | Seymour | NEW ROAD AND BRIDGE CONSTRUCTION | 3 of 4 | $13,398,275 | +5.0% |
How this record was read
INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
- Every bid counted here matched its published total to within one dollar; INDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.